Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 38202
Docket No. MW-37720
07-3-03-3-76

The Third Division consisted of the regular members and in addition Referee Elizabeth C. Wesman when award was rendered.

(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CP Rail System (former Delaware and Hudson
( Railway Company)

STATEMENT OF CLAIM:





Form 1 Award No. 3$202
T_- 2 Docket No. rvrW-37720
07-3-03-3-76

FINDINGS:


evidence, finds that:


are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.



involved herein.




intention to en_gaL_e a contractor "to assist MOW forces at Kenwond lntermndnl Area." The Organization responded on November 6, 2001. In that letter, the Organization stated its position that the Carrier had employees in the Track Department and System Equipment Operators who were capable of performing the

.. 1. ; nd-: T1 !' :_ ... 7:.,a a a.t "11w.- -.; ,_~.: ~ l,.aa,._. wr____~_>._ __ 11
YIV111111 qneJLlUll. LUCG Lral11v1 LCNIICU LU LUC VlgaUleallUU 1CtLC1 Uil ivvvetUuel 10,
2001. In that letter, it stated that while BMWE-represented employees would "do
all track work," it would "not have equipment nor staff to do work beyond the track
work."


it alleged that the Carrier had violated various Articles in the Agreement when it
contracted out work to be performed in Kenwood Yard in Albanv. New York.
Specifically, the Organization objected to the use of an outside contractor to do
bulldozer and steamroller work, which it maintained was normally performed by
System Equipment Operators. In particular, the Organization contended that the
!~._-,-;ov t,a.7 .>;.,infoa 1?**to XT- 1 st- c,._..,. n-t- ..a l-w-...a:- is ..r wl.-
~,uaaaa.a aau~a vavaula.u L1uiL. 11U. 1 - L116. iJ~UFG LVUUG - a ULL ~Fj1VUUXA ll V1 LUC
Agreement. Appendix H reads, in pertinent part, as follows:


Form 1 Award No. 38202
Page 3 Docket No. MW-.37720
07-3-03-3-76



+hn++h- ll---»t...,+:,.... 1_.a _a .. _i.. _..~:_.. _r..L_ _ _.e_ .. >__

,uwa tall, va~aaaaraaavu uau reicivcu ampm lwm:e U1 111C VYUIli Lo VC done, that the BMWE had, in fact, done all the track work in the project at issue and that the contractor had merely been assisting in the work in which BMWE-represented employees were involved. The Carrier also pointed out that the Claimant had been working during the period at issue and thus suffered no financial loss as a result of the project.


In its appeal the Organization restated its position that the Carrier had violated the Agreement, and noted particularly an attached statement to its claim in which the Claimant pointed out that he was not only capable of operating the machines used by the contractor at Kenwood, but that he was the Operator that did


+faa rsreelinrt .~»~l rpm».,u+s»e, ~._ ab waa,Yw~,uaa1,h- th. T *.~ a_1 F ..:hL-. .a T7 -.__ , 7 :7--~

S 1acca aaac auacxaaivuaa laa,ulaf a1. ~G11WVVU ZalU was originally built. That appeal was subsequently denied and the claim was processed in the usual manner including conference on the property.


There is no dispute on this record that the Claimant was fully qualified as a System Equipment Operator and was capable of operating both a bulldozer and a steamroller. Further, the Carrier acknowledges that the Claimant was, in fact, involved in the original building of the Kenwood Yard. The Organization argues that the Carrier should have rescheduled the Claimant to perform the work and/or permitted him to perform the work during regular and weekend overtime hours.




work at issue. Moreover, given the history of the construction of the Kenwood
Yard, it is also clear that the work at issue in this claim is generally performed by
BMWE-represented employees. While the Carrier asserted that it was not possible
to assign the Claimant the work at issue, ii has provided only that assertion and has
not successfully countered the Organization's position that the specific work of
operating a bulldozer and steamroller should have been assigned to the Claimant
under the provisions of Article 11.8 of the Agreement. That Article states:


Form 1 Award No. 38202
n.,.,._ A ,~_ _,__~7
i arc VockCG 1V o. 1VI W-3 7 72U
07-3-03-3-76
Based upon the foregoing, the Board finds that the Parties should make a
joint review of the Carrier's records and determine what part of the work
performed by the contractor on the dates named in the above claim involved the
work that should have been allocated to the Claimant, i.e., bulldozer and
steamroller work. That review should include the Claimant's availahility for
straight time or overtime. Once the Claimant's available hours are determined, he
should be reimbursed to the extent of his determined availability, at the straight
and/or overtime rate as appropriate.





This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is tranemittnrl to thn »ortinc





Dated at Chicago, Illinois, this 18th day of May 2007.