Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 38205
Docket No. MW-37790
07-3-03-3-159

The Third Division consisted of the regular members and in addition Referee Elizabeth C. Wesman when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:














Form 1 Award No. 38205
Page 2 Docket No. NM-37790
07-3-03-3-159
rates of pay for the aforesaid work performed by the outside
forces on September 13, 14, 15 and 16, 2002 and the Claimants
shall be compensated for an equal and proportionate share of
the total number of man-hours expended by the outside forces
in the performance of the aforesaid work beginning September
17, 2002 and continuing.'

FINDINGS:



evidPnrP. findc that-

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




On Thursdav. Sentomher 12_ 2(1(12_ a r1r,railvnPnt nrrnrrprt naar An f'nr~**c Christi Yard at approximately Mile Post 157.00. Resulting damage included a derailed locomotive and damage to the main line. The Carrier called in Lone Star Contractors to clear the derailment and get the main line back into service.


The Organization filed the above claim on September 16, 2002. It contended that the work performed at the derailment site by the outside contractor was work "highly recognized" as maintenance of way work. It insisted that the work at issue was thus covered under the Scope Rule of the Agreement and should rightfully have been performed by BMWE-represented employees. Accordingly, the Organization argued that the Carrier was obliged to give the Local Chairman notification of its intent to contract out and make a "Pond faith attemm" to come to an nndPrctanrlina regarding the contracting out of the work to be performed, before giving the work to an outside contractor. The Organization demanded that the Claimants named be compensated for the work opportunity lost.

T
corm i Award No. 38205
Page 3 Docket No. MW-37790


The claim was denied by letter of October 9, 2002. The Carrier denied having violated any portion of the Agreement. It further insisted that, without prejudice to its position that it had not violated the Agreement, there was no basis for the monetary clainlC_ The claim wne enhentrnnntlv nrn"rneenrl in +hn _c_~l manner including conference on the property on December 2, 2002.



worn, ----

WHICH was sent to the Organization on July 29, 2002, made no mention of the work at issue. It also contends that the site at issue was not a derailment site and that the work involved in the project at issue was clearly scope covered work. It further insists that the Carrier's need to contract out the work in this case was precipitated by its own failure to maintain an adequate workforce, not by any emergency situation.


The Carrier contends that the nruaniantinn'c claim is withmit merit fnr several reasons. First, it insists that the work at issue was utterly unrelated to the referenced subcontracting notice - rather, it involved an emergency derailment repair. Moreover, because it was an emergency, there clearly was not time to notify


*l.n ll-n.n----6-- ....7 ae,._ _~____ __r__

aax~ vi pacu,naavaa and engage in discussions r egardtng perlorlnance of the contracted out work. Second, it notes that according to its records all Claimants were employed on the dates in question and some had worked overtime during that period. Thus they were unavailable to do the work at issue. Finally, the Carrier notes that the Organization failed to prove that the work at issue was work reserved exclusively to BMWE-represented employees. The Carrier contends that there is and has been a mixed practice of using BMWE-represented employees as well as other employees and/or occasional outside contractors to perform the work at issrle.


The Board reviewed the record with care. We find that the Organization failed to meet its initial burden of presenting ~a. prima facie case that the work was


Y~C~Y·7~f~ ~'/1 ~-hn / a Y/7nll~f.nlln% "~aurvv duc O'~Uwc TDUlv a7 al

aa.pv,l.u a.V uaa. vasuaaaa.taeavai. LGGAUJG Luc v7t.V1JG ~U1G 15 gcneini in natur_e, the Organization must proffer evidence that the work was customarily and historically performed by BMWE-represented employees. (See for example, Third Division Award 29034). This burden cannot be met merely by assertion. The Organization provided no evidence that the work at issue was customarily and historically reserved to BMWE-represented employees.

Form 1 Award No. 38205
Page 4 Docket No. MW-37790
07-3-03-3-159

Furthermore, the Organization provided no evidence to contradict the
Carrier's position that such derailment work was normally contracted out. The
Board notes that the Carrier provided the Organization with an extensive list of the


coratr acwr N iecorueu worcc aor the Carrier. Moreover, there is no evidence in the record to contradict the Carrier's assertion that it does not have the equipment or manpower to perform such derailment work, especially not within the time frame involved following a derailment. (See, for example Third Division Awards 37991and 37008.)







This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimants) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 18th day of May 2007.