Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 38948
Docket No. MW-38267
08-3-NRAB-00003-040195
(04-3-195)

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.


(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





Form 1 Award No. 38948
Page 2 Docket No. MW-38267
08-3-NRAB-00003-040195
(04-3-195)
period beginning August 19 through 29, 2003 and he shall be
compensated at his applicable rate of pay for the all hours
expended by the outside forces beginning August 30, 2003 and
continuing."

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and ail the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.













Form 1 Award No. 38948
Page 3 Docket No. MW-38267
08-3-NRAB-00003-040195
(04-3-195)
Bids are being accepted from sub-contractors and it is anticipated
the work will begin within the next 30 to 45 days."
By letter dated April 29, 2003, the Carrier further detailed the work it
intended to contract out.

Conference was held between the parties on May 8, 2003 and agreement was not reached on the parties' differences concerning the contracting out of the work. This claim followed.







The Carrier's notice and conference obligations were met under Rule 29. Notice was given to the Organization by the Carrier's letters dated April 23 and 29 and conference was held on May 8, 2003. The claim states the work commenced August 19, 2003. We find the Carrier's letters sufficiently and timely put the Organization on notice of the scope and specifics of the work the Carrier intended to contract out as required by Rule 29.

Form 1 Award No. 38948
Page 4 Docket No. MW-38267
08-3-NRAB-00003-040195


This was obviously a major project. The Carrier asserted in its April 12, 2004 letter on the property that "[tlhe BMWE work force of Carrier is more than sufficient for its size and this Carrier cannot in any manner justify more employees and equipment expenses for special and/or unforeseen work projects." Upon our review of the record as a whole, we find that the Organization has not shown as Rule 29 requires that the Carrier's position that the work ". . . cannot be performed by the regular forces of the respective sub-departments . . :' is erroneous or that the Carrier acted in other than good faith as alleged by the Organization.


                        AWARD


      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 29th day of February 2008.