Form I NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 38988
Docket No. MW-38269
08-3-NRAB-00003-040197
(04-3-197)

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.



(Consolidated Rail Corporation

"Claim of the System Committee of the Brotherhood that:



Form 1 Award No. 38988
Page 2 Docket No. MW-38269
08-3-NRAB-00003-040197
(04-3-197)
FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




This claim protests the Carrier's use of a contractor to construct new tracks in the South Philadelphia Yard, which work is claimed by the Organization to be scope covered. The Organization also asserts that it was not given proper notice of the contracting of the work as required by the Scope Rule of the Agreement.


The Carrier asserts that it gave proper notice to the Organization and also asserts that the Board does not have jurisdiction over this dispute because the work involved was a necessary part of the construction work needed to implement the CSX-NS acquisition of Conrail.


Article I, Section 1(h) of the January 14, 1999 Arbitrated Implementing Agreement (issued pursuant to Article I, Section 4 of the New York Dock Conditions pursuant to Finance Docket No. 33388, Decision 89 off the Surface Transportation Board which approved the Conrail Transaction) provides:



Form 1 Award No. 38988
Page 3 Docket No. MW-38269
08-3-NRAB-00003-040197
(04-3-197)
Operating Plan and to achieve the benefits of the transaction as
approved by the STB in Finance Docket No. 33398."
Thus, it appears that this contracting dispute falls under the Arbitrated
Implementing Agreement. Therefore, as argued by the Carrier, the Board lacks
jurisdiction to consider the claim. See First Division Award 25983:





Further, see Third Division Award 24804 ("This Board has no authority to review an arbitration award issued pursuant to the New York Dock Conditions.").


The Organization argues that the disputed work did not appear on the list of projects planned for outside contractors furnished by the Carrier, this is therefore not a dispute arising under Article I, Section 1(h) of the January 14, 1999 Arbitrated Implementing Agreement, but is a contracting dispute falling under the Scope Rule of the Agreement; and the Board has jurisdiction to consider this dispute. However, given the substantial jurisdictional question raised by the Carrier; the language in

Form I Award No. 38988
Page 4 Docket No. MW-38269


Article I, Section I (h) of the January 14, 1999 Arbitrated Implementing Agreement; and the clearly established precedent that the Board has no jurisdiction to consider disputes arising under implementing agreements established pursuant to New York Dock, the question of whether the work in dispute fell within the purview of Article I, Section 1(h) of the January 14, 1999 Arbitrated Implementing Agreement can only be decided by a duly authorized board constituted pursuant to New York Dock.




      Claim dismissed.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago,. Illinois, this 27th day of March 2008.