(06-3-642)


(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE:
                  (CSX Transportation, Inc.


                    STATEMENT OF CLAIM: As shown in Docket No. SG-39790 and not repeated herein.


                  FINDINGS: The Third Division of the Adjustment Board finds:


That the dispute was certified to the Third Division of the Adjustment Board ex pane by the petitioning party; and

Under date of March 25, 2008, a formal communication was addressed to the Arbitration Assistant requesting withdrawal of this case from further consideration by the Division which request is hereby granted.

                        AWARD


      Claim withdrawn.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 22nd day of April 2008.