Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 39490
Docket No. MW-38309
09-3-NRAB-00003-040239
(04-3-239)

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.


(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:


STATEMENT OF CLAIM:





Form I Award No. 39490
Page 2 Docket No. MW-38309
09-3-NRAB-00003-040239
(04-3-239)
FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




By letter dated June 24, 2002, the Carrier advised the Organization's General Chairman as follows:








By letter dated June 28, 2002, the Organization protested the Carrier's decision to contract out the work and asked the Carrier to "[k]indly contact the System Office . . . at your earliest convenience to arrange a mutually agreeable date, place and time to conference this notice."
Form 1 Award No. 39490
Page 3 Docket No. MW-38309
09-3-NRAB-00003-040239
(04-3-239)















The Organization received the Carrier's July 12 letter on July 15, 2002. According to the Organization's letter of July 17, its General Chairman spoke with the Carrier on July 15 and was advised that the Carrier's designated official would be out of town until July 18 and arrangements were discussed about conferencing contracting out notices on July 19 or 22, 2002. In its July 17 letter, the General Chairman requested the Carrier to "(p]lease contact me at my home office on which day we could conference these contracting out notices.


Conference on various contracting out notices including the work involved in this dispute was held on July 19.


The contractor began performing the disputed work in this matter on July 15, 2002.

Form 1 Award No. 39490
Page 4 Docket No. MW-38309
09-3-NRAB-00003-040239
(04-3-239)
The relevant Rules provide:









First, the contracted work falls ". . . within the scope of this Agreement . . ." as stated in Rule 1.3. The described work is classic maintenance-of-way work.


Second, if the June 24 letter from the Carrier is deemed to be the notice to the Organization, in its June 28, 2002 letter, the Organization asked the Carrier to "[k]indly contact the System Office . . . at your earliest convenience to arrange a mutually agreeable date, place and time to conference this notice." From this record, the Carrier did not contact the Organization as requested. But under Rule 1.4, "[ilf the General Chairman, or his representative, requests a meeting to discuss matters relating to the said contracting transaction, the designated representative of the Carrier shall promptly meet with him for that purpose." There was no "prompt . . ." meeting as requested. The Carrier did not respond to the Organization's request to meet.

Form 1 Award No. 39490
Page 5 Docket No. MW-38309
09-3-NRAB-00003-040239
(04-3-239)

Third, if the July 12, 2002 letter from the Carrier is deemed to be the notice to the Organization, it is untimely. Rule 1.3 provides that ". . . the Carrier shall notify the General Chairman involved, in writing, as far in advance of the date of the contracting transaction as is practicable and in any event not less than fifteen (15) days prior thereto." The contractor began the work on July 15, 2002 - less than the 15 day notice requirement period found in Rule 1.3.


Fourth, if the July 12, 2002 letter is a clarification of the Carrier's June 24 letter, the notice remains untimely. From this record, after receiving the Carrier's July 12 notice, the Organization again attempted to arrange a conference, only to be told that the Carrier's representative was out of town and would not be available for conference until July 19 - the date the conference was held. But the work commenced on July 15. Therefore, because the Carrier delayed the conference until after the work commenced, for this particular contracting transaction, the Carrier rendered the notice and conference provisions of Rules 1.3 -1.5 meaningless.


The claim therefore has merit. As a remedy, the Claimant shall be made whole as requested in the claim for the lost work opportunities.




      Claim sustained.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 2nd day of February 2009.