Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 39605
Docket No. SG-39148
09-3-NRAB-00003-050609
(05-3-609)


Joan Parker when award was rendered..

(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Northeast Illinois Regional Commuter Rail
( Corporation (Metra)

STATEMENT OF CLAIM:







FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.

Form 1 Award No. 39605
Page 2 Docket No. SG-39148
09-3-NRAB-00003-050609
(05-3-609)

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




At the time this dispute arose, Claimants C. Alvarez, O. Ducksworth, M. E. Kendryna, W. R. Kirkpatrick, R. S. Porus, and R. W. Sorensen were assigned to the Maintenance Signal Gang headquartered at Western Avenue on the Milwaukee Operating District. They were working in positions subject to the General Rules Agreement between Metra and the Brotherhood of Railroad Signalmen, effective March 1,1984, as amended.


In conjunction with the Southwest Service expansion project, the Carrier contracted out bridge replacement work. This dispute arose because the Carrier used the contractor to install conduit for signal cables across bridge decks on Metra's Southwest Service at Mile Pole 27.10 on July 24, 2004. The Organization submitted a claim on behalf of the six claimants, contending that the Carrier violated the Scope Rule by using non-covered employees to perform the work, and it requested that each Claimant be paid eight hours at the straight time rate to compensate them for the lost work opportunity.


The Carrier denied the claim, which was processed in the usual and proper manner and ultimately discussed in conference. The parties' positions remained unchanged, and the Organization therefore submitted the dispute to this Board for adjudication.


The Organization rejects the Carrier's assertions that the work in question required specialized equipment and was part of bridge structure and design. It insists that the work was scope covered signal work and that the Carrier was obligated to negotiate any deviations from the Agreement's requirements. In response to the Carrier's contention that it was not required to piecemeal projects, the Organization argues that the Carrier failed to show that assigning the work to BRS-represented employees would have irreparably delayed the project or resulted in some other hardship. According to the Organization, there was nothing unique

Form 1 Award No. 39605
Page 3 Docket No. SG-39148
09-3-NRAB-00003-050609
(05-3-609)

about the work in dispute; conduit systems are routinely installed by signal employees, even spanning bridges. Given the Carrier's violation of the Agreement, the Organization submits that the Claimants are entitled to a financial remedy.


The- Carrier denies any violation of the Agreement or past practice. It takes the position that the work was part of bridge design, which is not covered by the Scope Rule. Moreover, the disputed work required a specialized piece of equipment, a concrete core drill, which was not possessed by the Carrier. The bridge designer used a firm that specializes in performing the type of work at issue (Concrete Core Drilling Contractors) which core drilled holes in both back walls of the bridge for installation of the conduit. Finally, the Carrier submits that it was not required to piecemeal a project that had been contracted out, which, in essence, is what this claim requests.


- It is undisputed that the work at issue was the installation of conduit as part













40 the bridge.The concrete core drill is a large heavy piece of
Form 1 Award No. 39605
Page 4 Docket No. SG-39148
09-3-NRAB-00003-050609
(05-3-609)
equipment, scaffold was [required] to provide a platform to drill
from and the drill has to be anchored to the backwall to core the
holes. The concrete drill is a specialized. piece of equipment and the
work is generally work performed by Concrete Core Drilling
Contractors. Our signal gangs have star drills for drilling conduit;
however, star drills are for holes up to about 2-1/2" in diameter."
Clearly, the work involved was specialized, necessitating a piece of machinery
that the Carrier did not even own and requiring the retention of a firm that
specializes in core drilling. The Organization acknowledges that installation of the
conduit was just part of the total work. Essentially, therefore, it wanted the Carrier
to piecemeal the project. In these circumstances, however, there was no contractual
requirement for the Carrier to carve out the installation of the conduits and to
assign this work to BRS-represented employees. Such action could have caused
significant delay and jeopardized the manufacturers' warranty for the pre-cast
concrete bridge deck as a result of improper drilling.







This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.



                      By Order of Third Division


Dated at Chicago, Illinois, this 1st day of April 2009.