- Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 39614
Docket No. MW-38190
09-3-NRAB-00003-040078
(04-3-78)











Form 1 Award No. 39614
Page 2 Docket No. MW-38190
09-3-NRAB-00003-040078
(04-3-78)
contracting force in cleaning the Right of Way of scrap ties and
debris."'

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




This case involves the question of whether the contracting out of the construction of two new main lines, a new bridge and yard modifications in conjunction with the Marysville Railroad Relocation Project properly encompassed cleaning the right-of-way of scrap, scrap ties and debris associated with the project. Although initially disputed by the Organization, its claim in the instant case does not include a claim that the work involving the actual construction was improperly noticed or contracted out pursuant to the parties' Agreement.


The Carrier's original notice to the Organization, dated July 8, 2002 (Service Order No. 24911) listed as "Specific Work: Construct Two New Main Lines, New Bridge, and Make Yard Modifications in Conjunction with Marysville Railroad Relocation Project." The Organization's response, dated July 15, complained, in part, that the Carrier's notice did not ". . . provide . . . a full description of the work to be contracted . . . ."


The Carrier argues that the work at issue - the clean-up performed by the contractor - was incidental to the work associated with the installation of a new embankment. The Carrier also contends that it is not obligated to "piecemeal" the work in the manner claimed by the Organization and that Article IV of the 1968 National Agreement was superseded by Rule 52 - Contracting.

Form 1 Award No. 39614
Page 3 Docket No. MW-38190
09-3-NRAB-00003-040078
(04-3-78)

The Carrier's assertion that it is not obligated to "piecemeal" project work to afford the Organization the right to a portion of it is not especially relevant to the instant case. It must be clear the Board in no way overturns established precedent with respect to a Carrier's right to avoid the "piecemeal" of work, nor does it disturb precedent with respect to a "mixed past practice" analysis. However, it is not necessary to reach either question inasmuch as the Board finds the notice, in the first instance, did not adequately define the scope of work to include debris removal - clearly work of which BMWE-represented employees are capable of performing and have performed in the past - and, therefore, deprived the Organization of its right to enter into informed discussions about the proposed contracting.


As stated in Public Law Board No. 7100, Award 13, "[b]oth the spirit and letter of the December 11, 1981 letter clearly puts upon the Carrier the burden of providing sufficient notice to the Organization in terms of both calendar notice as well as reasons for the subcontracting in order to demonstrate `good faith efforts to reduce the incidence of subcontracting and increase the use of maintenance of way forces . . . .'"


Special Board of Adjustment No. 1016, Award 28, cited by Carrier illustrates the point:



Simply put, the Carrier's obligation included describing to the Organization its intention to contract for the debris removal work even where, in the Carrier's view, it was part and parcel of a larger project. Its failure to do so violated the Agreement.

Form 1 Award No. 39614
Page 4 Docket No. MW-38190
09-3-NRAB-00003-040078
(04-3-78)

While the claim is partially sustained based on the facts presented, the claimed remedy is not sustained. There is insufficient evidence of a loss of earnings to justify a monetary remedy, an established prerequisite to making such an award. (See, e.g., Public Law Board No. 1844, Award 13). In these circumstances, longstanding precedent requires instead the Carrier to issue proper notice in future similar circumstances.








This Board, after consideration of the dispute identified above, hereby orders that as award favorable to the Claimants) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 1st day of April 2009.

0