The Third Division consisted of the regular members and in addition Referee Brian Clauss when award was rendered.
The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier of carriers and the employee or employees involved in this ate are respectively crier and employee within the meaning of the Railway r Act, as approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
The Organization protested subcontractors performing bridge repair work at the kocations cited in the Statement of Claim.
The Organization maintains that the instant work of performing bridge repairs was not emergency work; rather (1) it was clearly the work of the Claimants (2) the Carrier did not conduct good faith discussions with the Organization about contracting out and (3) the Claimants were willing and able to perform the work, but the Carrier did not give them a good faith opportunity to have the work assigned to them. By reducing the workforce by more than 50 percent, the Carrier has not operated in good faith and now seeks to avoid having Organization members perform scope covered work through subcontracting. The Organization claims that the Carrier was obligated to supplement the workforce to meet its responsibilities.
The Carrier responds that the bridge repairs were pursuant. to an emergency and the notice requirements for contracting therefore do not apply.
The Board carefully reviewed the evidence and finds that the Organization failed to prove a violation of the Agreement in this case. The Carrier admitted that no notice was served on the Organization involving the two bridges. The Carrier asserted that no Form I Award No. 39724
notices were sent because the repair work was emergency work that was discovered during an inspection of the bridges. The bridges at issue were repaired pursuant to an emergency as detailed in the Carrier's letter dated May 7, ?.004. Specifically, the bridge at MP 64.11 was found to have a severe defect in that the eastern approach had settled requiring headwall replacement. The bridge at Me 74.52 was found is be leaning and repairs needed to be completed as quickly as possible. The Carrier cited both bridge repairs as emergencies and the Organization did not provide evidence to the contrary.
There were emergency situations at MP 64.11 and MP 74.52 - a sees bridge requiring a wall replacement and a leaning bridge certainly suggest that immediate action is required. We find that the cement was not violated in these emergency situations when no notice was served on the Organization - because the emergency situations required immediate action. (See Third Division Award 30818.) Accordingly, the claim is denied.
This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.