NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 39758
Docket No. MW-38332
09-3-04-3-268
Award No. 39761
Docket No. MW-38350
09-3-04-3-290
Award No 39764
Docket No.
MW-38469
09-3-04-3-440
Award No. 39767
Docket No. MW-38532
09-3-04-3-520
Award No. 39770
Docket No. MW-38727
09-3-05-3-127
Award No. 39759
Docket No. MW-38339
09-3-04-3-278
Award No. 39762
Docket No. MW-38354
09-3-04-3-294
Award No. 39765
Docket No.
MW-38494
09-3-04-3-469
Award No. 39768
Docket No. MW-38534
09-3-04-3-522
(Brotherhood of Maintenance of Way Employes
PARES TO DISPUTE: (
(CSX Transportation, Inc-
Award No. 39760
Docket No. MW-38346
09-3-04-3-286
Award No. 39763
Docket No. MW-38463
09-3-04-3-418
A.No_ 39766
Docket No. MW-38529
09-3-04-3-516
Award No. 39769
Docket No. MW 38702
09-3-05-3-107
STATEMENT OF CLAIM: As shown in the above mentioned Docket Nos. and not
repeated herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the disputes were certified to the Third Division of the Adjustment Board
ex parte by the petitioning party; and
Under date of May 18, 2009, the petitioning party addressed a formal
communication to the Arbitration Assistant requesting withdrawal of these cases from
further consideration by the Division which request is hereby granted.
Page 2 Award No. 39'758 et al
Docket No. MW-38332 et al
09-3-NRAB-00003-04026$ et al
(04-3-26$ et al)
AWARD
Claims withdrawn.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 26th day of June 2009.