Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 39907
Docket No. SG-38733
09-3-NRAB-00003-050137
(05-3-137)

The Third Division consisted of the regular members and in addition Referee Steven X Bierig when award was rendered.


(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE: (


STATEMENT OF CLAIM



FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, fmds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.

Form 1 Award No. 39907
Page 2 Docket No. SG-38733
09-3-NRAB-00003-050137
(05-3-137)



The Claimant in this case is P. W. Darity, who at the time this claim arose, was assigned to the monthly-rated position of Signal Maintainer, Position No. 835. The Claimant was headquartered at Greenvale, Texas, and his scheduled work days were Monday through Friday, from 7:00 A.M. to 4:00 P.M., with one hour for lunch. As this was a monthly-rated assignment, the Claimant's stand-by day was Saturday, and Sunday was the assigned rest day.



to repair a track light. The light had become inoperable because a Maintenance of Way crew working in the area had accidentally severed a track-wire causing an outage. The Claimant claimed two hours and 40 minutes of overtime. The Carrier denied the claim on the basis that trouble calls that occur on an employee's stand-by day are considered covered by the monthly rate of pay.


The Organization appealed the above-captioned disallowance, contending that the Claimant should be compensated for the overtime on January 10, 2004 because the work of repairing the light was "planned ordinary maintenance" that qualifies the Claimant to be paid for such work over and above his monthly compensation at the overtime rate. Said work was outside the scope of work that could be required of the Claimant without compensation on his stand-by day.


Conversely, the Carrier takes the position that the Organization cannot meet its burden of proof in this matter. The Carrier contends that the work involved the replacement of a track light, which displays the color of a signal. The failure of such an apparatus is an emergency condition requiring immediate attention and is not ordinary maintenance. While it is uncontested that the Maintenance of Way work was preplanned, it certainly cannot be said that the outage of the track light was foreseeable. This was clearly an emergency situation that required immediate attention. It was not within the realm of ordinary maintenance.


After a careful review of all facts and circumstances in this case, the Board finds in favor of the Carrier. As noted above, the burden of proof is on the Organization to prove that the Claimant was performing ordinary maintenance

Form 1 Award No. 39907
Page 3 Docket No. SG-38733
09-3-NRAB-00003-050137
(05-3-137)

when he was called to replace the track light. The Organization failed to meet that burden. We find that the Carrier properly characterized the work as emergency work and not ordinary maintenance. Accordingly, the claim is denied.








This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimants) not be made.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 31st day of August 2009.