Form I NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40075
Docket No. MW-40385
09-3-NRAB-00003-080179
The Third Division consisted of the red members and in addition Referee
_ __ __~ H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes Division
( IBT Rail Conference
PARTIES TO DISPUTE: (
(Union Pacific Railroad Company (former Chicago and
( North Western Transportation Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Morrison Blacktop) to perform Maintenance of Way
and Structures Department work (dig trenches for ribbon rail
and back fill after rail was laid in) across crossings between
Mile Posts 104 and 112.5 on the Geneva Subdivision on August
9,11 and 31, 2006 (System File 3SW-2177Tt1463207 CNW).
(2) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with a proper advanced written
notice of its intent to contract out the above-referenced work or
make a good-faith attempt to reach an understanding
concerning such contracting as required by Rule 1(b).
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, Claimants D. Coy, Jr., K. Spooner and S.
Silquero shall now each be compensated for twenty-four (24)
hours at their respective straight time rates of pay."
Form 1 Award No. 40075
Page 2 Docket No. MW-40385
09-3-NRAB-00003-080179
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
By letter dated June 8, 2006, the Carrier advised the Organization's General
Chairman of a ". . . 15-day notice of our intent to contract the following work"
specifying the following:
"Locations: Geneva Subdivision, Peoria Subdivision
Specific work: - Contractor using equipment to haul material and
equipment, cut grade, remove crossing material and debris from the
area during the renewal and upgrade of road crossings; start date is
June 21, 2006 continuing until June 22, 2007.
The work is such that the Company is not adequately equipped to
handle the work or time requirements must be met which are
beyond the capabilities of Company forces to meet."
According to the Carrier's November 16, 2006 letter, on June 16, 2006 a
conference was held on the notice.
Form 1
Page 3
Award No. 40075
Docket No. MW-403$5
09-3-NRAB-00003-080179
The instant claim protests the Carrier's use of contractor's forces on August
9, 11 and 31, 2006 who, according to the Organization's September 26, 2006 claim
letter:
". . . performed
Maintenance of Way duties by digging a trench
across approximately eight (8) road crossings located between M.P.
104 and M.P. 1125 (sic) on the Geneva Subdivision. The trenches
were filled back in with P gravel after ribbon rail was laid through
the crossings. Each of the three (3) contractor employees rendered
eight (8) hours per day or a total of twenty four (24) man hours
performing the Maintenance of Way work. The Contractor
employees used a Skid Loader, shovels, and Dump Truck to
accomplish the task."
According to the Carrier:
"Morrison Blacktop was hired to remove the waste blacktop
removed from the crossings during the above operations. They also
assisted with filling in the trenches to help expediate the reopening
of the road crossings. During these operations all of our available
people and machines were being used in other parts of the operation.
Not using Morrison Blacktop would have resulted in the closing of
several public crossing for days instead of a few hours [interrupting
traffic and public safety for an unacceptable amount of time."
The Carrier asserts that this type of work has been contracted out in the past.
Further, according to the Carrier, the Claimants were working on the dates set
forth in the claim.
The record shows that advance written notice to the Organization for the
contracting of work was given by the Carrier; conference was held between the
parties on that notice; the disputed work was covered by the notice; and the type of
work involved has been previously contracted out by the Carrier.
The Carrier's assertion that Morrison Blacktop was used because ". . . all of
our available people and machines were being used in other parts of the operation
Form 1 Award No. 40075
Page 4 Docket No. MW-403$5
09-3-NRAB-00003-080179
[and n]ot using Morrison Blacktop would have resulted in the closing of several
public crossing for days instead of a few hours [i]nterrupting traffic and public
safety for an unacceptable amount of time" has not been sufficiently refuted by the
Organization. Rule 1(B) allows the Carrier to contract out work if ". . . work is such
that the Company is not adequately equipped to handle the work; or time
requirements must be met which are beyond the capabilities of Company forces to
meet." The burden of proof is on the Organization. The Organization fazed to
refute the assertions of the Carrier that the use of Morrison Blacktop was
permissible under Rule 1(B).
This claim shall therefore be denied.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 19th day of November 2009.