Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40077
Docket No. MW-40643
09-3-NRAB-00003-080471
The Third Division consisted of the red members and in addition Referee
Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE: (
(Union Pacific Railroad Company
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (KRW and HTI) to perform Maintenance of Way and
Structures Department work (load and haul ballast) at a
derailment site at Mile Post 147 in the vicinity of Grand Island,
Nebraska on March 15 and 16, 2007, instead of Messrs. J.
Mumm, D. Rice, R. Winter, K. Gute, R. Mostek and D. Overly
(System File R-0752U-30111473576).
(2) As a consequence of the violation referred to in Part (1) above,
Claimants J. Mumm, D. Rice, R. Winter, K. Gute, R. Mostek
and D. Overly shall now each be compensated for twenty-one
(21) hours at their respective and applicable rates of pay."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21,1934.
Form 1 Award No. 40077
Page 2 Docket No. MW-40643
09-3-NRAB-00003-080471
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
The Organization asserts that during the period beginning at 3:00 P.M. on
March 15 and continuing until Noon on March 16, 2007, the Carrier improperly
utilized contractors to perform work at a derailment that blocked the main lines
near Grand Island, Nebraska.
The record shows that three contractors were called in to assist in clearing
the derailment - Hulcher, KRW and HTI. The contractors' forces supplemented the
Carrier's forces and the Claimants were fully employed and working overtime
during the time worked by the contractors.
The Organization points out that although there were three contractors at the
site, the claim only protests the Carrier's use of two of the contractors - KRW and
HTI. According to a statement provided by the Organization:
".
. . Hulcher was the contractor being used to get the wreckage
cleared away and the new panels laid. We filed no claim involving
Hulcher.
When the crew I was on was sent home KRW and HTI were doing
nothing but watching us work. There were 4 panels left to lay,
which our guys were doing with Hulcher doing the heavy lifting.
The only thing KRW did for the emergency situation was to dump
stockpiled rock on the last 4 panels. We had the REOs and the
equipment to do that."
Third Division Award 20527 sets forth the standard for an "emergency:"
"We have heretofore defined an emergency as `an unforeseen
combination of circumstances which calls for immediate action'
Form 1 Award No. 40077
Page 3 Docket No. MW-40643
09-3-NRAB-00003-080471
(Award 10965) . . . . [I]t is well established that the Carrier, in an
emergency, has broader latitude in assigning work than under
normal circumstances; in an emergency Carrier may assign such
employees as its judgment indicates are required and it is not
compelled to follow normal Agreement procedures."
And, as discussed in Third Division Award 32862, ". . . [t]he burden rests
with the Carrier to demonstrate the existence of the emergency."
The Carrier has sufficiently shown that the derailment constituted an
emergency. The tracks were blocked and they had to be opened. Indeed, the
statement provided by the Organization acknowledges that there was
an ". . . emergency situation . . . ."
However, as shown by the provided statement, the Organization seeks to
parse out work at the end of the emergency, asserting that Carrier forces could have
done the work. In this case, that argument is not persuasive.
The Organization is correct that there comes a point when an emergency
ends. See e.g., Third Division Award 40080 where the Board found that a snow
emergency ended by the second and third days after the major snow event and it
was improper to use outside forces on those days. The same cannot be said for this
case. The period involved was from March 15, beginning at 3:00 P.M. and
continuing until March 16, 2007 at Noon - a period of only 21 hours. Even
according to the statement provided by the Organization, when the Carrier's forces
were sent home, "[t]here were 4 panels left to lay, which our guys were doing with
Hulcher doing the heavy lifting." When the Carrier's forces were sent home, the
emergency had not yet come to an end. With respect to one of the contractors, the
statement further provides that the contractor's forces ". . . dump[ed] stockpiled
rock on the last 4 panels" thereby showing that the contractor's forces participated
in the last phase of the emergency work. In this case, we cannot find that the
emergency ended to the extent that the Carrier's ". . . broader latitude in assigning
work than under normal circumstances . . ." (Third Division Award 20527) had
come to an end.
This claim shall therefore be denied.
Form 1 Award No. 40077
Page 4 Docket No. MW-40643
09-3-NRAB-00003-080471
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 19th day of November