Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40082
Docket No. MW-40712
09-3-NRAB-00003-080583

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.

(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE: (
(Union Pacific Railroad Company

STATEMENT OF CLAIM:



The Agreement was violated when the Carrier assigned outside forces (Balfour Beatty) to perform Maintenance of Way and Structures Department work (track construction and related work) at approximately Mile Posts 803.45 and 804.25 on the Rawlins Subdivision beginning on April 2, 2007 and continuing (System File J-0752U-266/1478630).



Form 1 Award No. 40082
Page 2 Docket No. MW-40712
09-3-NRAB-00003-080583

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:



respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21,1934. -

Division of the Adjustment Board has jurisdiction over the dispute involved

herein.



The Organization asserts that the Carrier assigned outside forces to perform track construction and related work at approximately Mile Posts 803.45 and 804.25 on the Rawlins Subdivision beginning on April 2, 2007 and continuing. The Carrier defends on the ground that the project was owned by DOUR BTS, Inc. and that company and not the Carrier hired the contractor to perform the work.


The Carrier produced a contract between it and DOUR BTS dated May 23, 2006 which provides, in pertinent part:




Form 1 Award No. 40082
Page 3 Docket No. MW-40712
09-3-NRAB-00003-080583

























Form 1 Award No. 40082
Page 4 Docket No. MW-40'712
09-3-NRAB-00003-080583
split switch derail in Track A at or near Engineering Station
4+64, install a pre-cast concrete bridge in Track A over
Sweetwater Creek, and install all of Track B and Track C as
shown on Exhibit A.
~x















Form I Award No. 40082
Page S Docket No. MW-40712
09-3-NRAB-00003-080583
2. Maintain all appurtenances to the Track (other than an automatic
signal system), including without limitation, gates, fences, bridges;
undertrack unloading pits, loading or unloading devices and
warning signs above, below or beside the Track.
Article 22. INDUSTRY TO CONVEY OWNERSHIP OF TRACK.


In its claim letter of May 26, 2007, the Organization asserts the following work was improperly assigned to outside forces:



The work described by the Organization in its claim is the work which DOUD BTS - and not the Carrier - was responsible to perform under Article 6 of the agreement between the Carrier and DOUD BTS. Further, that contract specifically provides that at the time the work was performed, DOWD BTS owned that portion of
Form I Award No. 40082
Page 6 Docket No. MW-40712
09-3-NRAB-00003-080583

the track on which the work was performed. See Articles 11 and 22 of the Agreement between the Carrier and DOUD BTS.


". . . As noted in Third Division Award 31234, the Board has long held that where work is not performed at the Carrier's instigation, under its control, at its expense or exclusively for its benefit, contracting is not a violation of the Scope Rule of the Agreement." Third Division Award 37143. Given the terms of the agreement between the Carrier and DOUR BTS, the principle in Third Division Award 37143 governs. The Carrier did not own the property or control this work when it was performed. No Agreement violation has been shown.










This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.



                      By Order of Third Division


Dated at Chicago, Illinois, this 19th day of November 2009.