NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40263
Docket No. MW-35828
10-3-99-3-833
Award No. 40266
Docket No. MW-39473
10-3-06-3-244
Award No. 40269
Docket No. MW-39541
10-3-06-3-326
Award No. 40272
Docket No. MW-39630
10-3-06-3-418
Award No. 40275
Docket No. MW-39946
10-3-07-3-101
PARTIES TO DISPUTE: (
Award No. 40264
Docket No. MW-37309
10-3-02-3-326
Award No. 40267
Docket No. MW-39536
10-3-06-3-308
Award No. 40270
Docket No. MW-39626
10-3-06-3-399
Award No. 40273
Docket No. MW-39687
10-3-06-3-544
(Brotherhood of Maintenance of Way Employes
(BNSF Railway Company
Award No. 40265
Docket No. MW-37310
10-3-02-3-327
Award No. 40268
Docket No. MW-39540
10-3-06-3-325
Award No. 40271
Docket No. MW-39627
10-3-06-3-408
Award No. 40274
Docket No. MW-39759
10-3-06-3-586
STATEMENT OF CLAIM: As shown in the above mentioned Docket Nos. and not
repeated herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the disputes were certified to the Third Division of the Adjustment Board
ex parte by the petitioning party; and
Page 2 Award No. 40263 et al
Docket No. MW-35828 et al
10-3-99-3-833 et al
Under date of December 10, 2009, formal communications were addressed to the
Arbitration Assistant requesting withdrawal of these cases from further consideration
by the Division which requests are hereby granted.
AWARD
Claims withdrawn.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 15th day of Jane 2010.