Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40328
Docket No. MW-40526
10-3-NRAB-00003-080360

The Third Division consisted of the regular members and in addition Referee Sherwood Malamud when award was rendered

(Brotherhood of Maintenance of Way Employes Division - ( IBT Rail Conference PARTIES TO DISPUTE: (Union Pacific Railroad Company (former Chicago ( and North Western Transportation Company)

STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.
Form 1 Award No. 40328
Page 2 Docket No. MW-40526
10-3-NRAB-00003-080360

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




On Saturday, January 27, 2007 the Carrier called Welder J. M. Davis to repair a frog at Mile Post 410.3 near Tindall, Missouri, on the Trenton Subdivision. Because Davis had been bumped by a more senior Welder on the previous day, he was unassigned on January 27.


Claimant Machine Operator E. Taff, as well as Davis, worked Monday through Friday January 22 - 26 on Gang 2918. Taff does not hold Welding seniority, nor does he have the skills to perform electric arc welding. The Organization argues that the Claimant should have been called as the regular employee, under Rule 23L, and as the senior employee on Gang 2918 on January 27, under Rule 31.


The Organization asserts that the frog was changed. It contends that no welding was performed. Significantly, the Organization's on-property handling of this claim does not include any statement from the Claimant as to the work performed on the frog on January 27. In spite of the fact that the Vice Chairman requested the Claimant to submit a statement, the Claimant provided no additional evidence that the frog was changed.


On the other hand, the Carrier presented a statement from Manager of Track Maintenance L. Lager who assigned a Welding gang to repair the frog. He wanted a Welder. J. M. Davis maintains seniority in the Welder classification. Furthermore, he has the skills to perform electric arc welding. The Claimant does not.


The record is devoid of any evidence whether any welding was actually performed or whether the frog was changed, because it was beyond repair. However, it is the Organization that bears the burden of proof in cases such as this. It must present sufficient evidence on the property to establish the basis for the claim presented. Here, the Carrier contends that an employee with welding qualifications was needed to perform the work on the frog. The Organization

Form 1 Award No. 40328
Page 3 Docket No. MW-40526
10-3-NRAB-000013-080360

claims the frog was changed and no welding was performed while changing the frog. However, there is no evidence as to work that was performed. There is an irreconcilable factual dispute as to whether welding was needed for this work assignment. Third Division Award 37204 sets out the action and reasoning of the Board when confronted with a case in which there is an irreconcilable conflict in the facts presented by the Organization and the Carrier, as follows:









This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.



                      By Order of Third Division


Dated at Chicago, Illinois, this 1st day of March 2010.