Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40411
Docket No. MW-39486
10-3-NRAB-00003-060278
(06-3-278)
The Third Division consisted of the regular members and in addition Referee
Brian Clauss when award was rendered.
(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE:
(Union Pacific Railroad Company (former Chicago and
( North Western Transportation Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Iowa Bridge Company) to perform Maintenance of
Way and Structures Department work (construct concrete box
culverts under existing bridges) at Mile Post 281.42 on the
Boone Subdivision near Denison, Iowa beginning on March 28,
2005 and continuing instead of Seniority District B-4 employes
L. Fisher, J. Miller, K. Brink, W. Kress, R. Schoon, B.
Wickham, D. Broich and G. Mathies (System File 4RM9658T/1425551 CNW).
(2) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with a proper written notice of
its intent to contract out the above-referenced work or make a
good-faith attempt to reach an understanding concerning such
contracting as required by Rule 1(b).
(3) As a consequence of the violation referred to in Parts (1) and/or
(2) above, Claimants L. Fisher, J. Miller, K. Brink, W. Kress,
R. Schoon, B. Wickham, D. Broich and G. Mathies shall now
each be compensated at their applicable rates of pay for an
equal and proportionate share of the total straight time and
Form 1
Page 2
FINDINGS:
Award No. 40411
Docket No. MW-39486
10-3-NRAB-00003-060278
(06-3-278)
overtime man-hours expended by the outside forces in the
performance of the aforesaid work beginning March 28, 2005
and continuing."
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
This matter involves a contractor's construction of concrete box culverts
under existing bridges at MP 281.42 that began on March 28, 2005 on the Boone
Subdivision where the Claimants hold seniority on Seniority District B-4.
On February 14, 2005, the Carrier served notice of its intent to subcontract at
the location of "Bridge 281.42 on the Boone Subdivision near Dennison, IA"
identifying the work as Service Order No. 30944. The specific work was identified
as "furnishing all supplies, materials, (except Railroad supplied material),
equipment, labor, and supervision to construct concrete box culverts." The notice
continued that: "Serving of this `notice' is not to be construed as an indication that
the work described above necessarily falls within the `scope' of your agreement, nor
that the work is necessarily reserved, as a matter of practice, to those employees
represented by the BMWE."
Organization replied on the same day and requested an immediate
conference. The Organization pointed out that the Carrier's notice of intent to
subcontract is inadequate under Rule 1(b) because it fails to specify the five
enumerated exceptions for subcontracting which are identified in Rule 1(b). A
Form 1
Page 3
conference was h
an understanding.
Award No. 40411
Docket No. MW-39486
10-3-NRAB-00003-060278
(06-3-278)
el
~d on February 16, 2005, and the parties were unable to come to
The Organization followed up with a letter dated February 18, 2005 that
provided, in pertinent part:
"In conference, the Organization cited Carrier forces are
experienced and capable of performing the contemplated work. The
work proposed is work that is covered under the Scope of the
Agreement. Carrier possesses the required expertise and equipment
needed to perform this work. No agreement was reached during this
conference."
The Carrier responded in a March 8, 2005 letter that the work ". . . required
specialized skills that the Carrier employees do not possess and equipment that the
Carrier does not own and that Carrier forces do not have the skills to operate.
Under the circumstances, Carrier use of a contractor to perform this work is not a
violation of that agreement . . . ."
The Carrier advised that it would contract the work.
The Organization's response of May 16 indicated that work had begun on
March 25, 2005 and was continuing. The Organization listed the equipment and
tools being used by the contractor, "all of which are common tools and equipment in
the immediate inventory of Claimant's crews. Claimants have historically
performed
very same work as part of their regular bridge and culvert
maintenance." The Organization continued "The Claimants and other B&B
employees built a similar box culvert at MP 282 on the Boone Subdivision and have
removed other bridge structures in the past."
The Carrier responded in a July 5, 2005 letter asserting that the notice was
proper and further stating:
"Notwithstanding, and with the notice in mind, you are also aware
the contractor employees working are fully qualified to perform the
work. Further, the Carrier has customarily and traditionally
utilized contractor's forces to perform the type of work covered in
Form 1 Award No. 40411
Page 4 Docket No. MW-39486
10-3-NRAB-00003-060278
(06-3-278)
the dispute. Your contention that such work is reserved to
employees covered by the BMWE Agreement is simply without
substance. Since the work in the instant case does not fall under the
scope of your Agreement, your argument with regard to the lack of
notice is obviously irrelevant in this case. Moreover, even if such
were reserved to employees of your craft, the fact remains that the
Claimants involved in this case do not possess sufficient fitness and
ability to safely and efficiently perform the duties or operate the
equipment in question."
The Organization responded on July 21, 2005, reminding the Carrier that
serving notice and having a conference does not give the Carrier a unilateral right to
contract the work under Rule 1(b) and further reminding the Carrier that the
conference included a discussion of how this type of work has been done by Carrier
B&B forces for many years and that the forces ". . . are experienced and capable of
performing the work" and that in the conference ". . . Carrier failed to even allege
that one of the contracting out criteria listed in Scope Rule 1 of the Agreement exists
in the instant case."
The Carrier points out in the letter of September 9, 2005 that the notice
required the contractor to furnish all supplies material, labor, and supervision for
the project. The letter also stated:
"It was also explained in conference that the work in question also
required special skills and equipment, not possessed by the Carrier
and its employees. Additionally, the Carrier does not have the
qualified personnel to complete this work with the other
commitments of the B&B department.
1C
'1C
Rule 1. Scope (b) does allow for work to be contracted when `time
requirements must be met which are beyond the capabilities of
Company forces.' Seeing as your Claimants were fully employed, it
must be determined that the Company forces were not available to
perform the work. According to the information presented by
Manager of Bridge Maintenance . . . he stated that the project was
Form 1
Page 5
Award No. 40411
Docket No. MW-39486
10-3-NRAB-00003-060278
(06-3-278)
under time sensitive restraints in which the Carrier did not have
available qualified forces to perform the work in the allotted time
frame."
The information supplied by the Manager of Bridge Maintenance was a four
line email dated June 1, 2005, which stated:
"(1) This project is time sensitive and the carrier does not have
adequate and qualified work force to perform this work in
required time frame.
not have.
specialized project requires equipment the carrier does
(3) The union was notified by labor relations.
(4) Broich and Wickham are working on both projects as
flagmen."
In the Organization letter of November 21, 2005, the following pertinent
points were addressed:
"(5) The Carrier has failed to show any evidence of specialized
equipment needed to perform this work.
(7) The Organization has provided copies of pictures of box
culverts that members have previously constructed.
(8) The Organization provided statements from members that
show B&B forces are capable and experienced at just about
any kind of bridge work."
The Organization provided statements describing past work, time lines,
copies of equipment leases, available equipment in company inventory, and
photographs of similar work.
Form 1 Award No. 40411
Page 6 Docket No. MW-39486
10-3-NRAB-00003-060278
The Organization maintains that the work at issue is scope covered work
pursuant to Rule 1(b) of the Agreement. It continues that the notice was defective
because where it did not mention the specific enumerated exceptions for
subcontracting. Further, even if the notice was not defective, the cited exceptions
that were proffered by the Carrier during handling were refuted as nothing more
than a mere statement without support in the record.
The Carrier counters that a timely proper advance notice of its intent to
contract out the work was provided to the Organization. It contends that the work
at issue is not scope covered, that there were not enough qualified employees to
complete the project because of other commitments of the B&B Department, and
that the full employment of the Claimants caused the employees no loss of wages or
work opportunity.
The Board carefully reviewed the record and concludes that it supports the
finding that the Carrier filed a notice of intent to subcontract and held a conference
with the Organization in the instant matter. However, that does not end the
inquiry. Our review also indicates that the work at issue is box culvert work to a
bridge on the Boone Subdivision. According to the Organization, such work is
covered by Rule 1(b) which provides:
"Employees included with the scope of this Agreement in the
Maintenance of Way and Structures Department shall perform all
work in connection with the construction, maintenance, repair and
dismantling of tracks, structures and other facilities used in the
operation of the Company in the performance of common carrier
service on the operating property. This paragraph does not pertain
to the abandonment of lines authorized by the Interstate Commerce
Commission.
By agreement between the Company and the General Chairman,
work as described in the preceding paragraph which is customarily
performed by employees described herein, may be let to contractors
and be performed by contractor's forces. However, such work may
only be contracted provided that special skills not possessed by the
Company's employees, special equipment not owned by the
Company, or special material available only when applied or
Form 1 Award No. 40411
Page 7 Docket No. MW-39486
10-3-NRAB-00003-060278
(06-3-278)
installed through supplier, are required or unless work is such that
the Company is not adequately equipped to handle the work, or time
requirements must be met which are beyond the capabilities of
The Organization provided the above-discussed photographs, statements,
timelines, and leases to underscore that the work has been performed by BMWErepresented employees in the past on this subdivision. This evidence serves to
underscore the plain meaning of Rule 1(b) that this work is scope covered.
Accordingly, we find that constructing box culverts clearly falls within the scope of
Organization work as described in Rule 1(b). See e.g., Third Division Award 37647
and Awards cited therein.
When the record supports a finding that the Organization has made a rp ima
facie showing of a Rule 1(b) violation, as it did in the instant matter, Third Division
Award 37376 informs that ". . . the burden then shifts to the Carrier to show that
one of the five exceptions in Rule 1(b) applies."
With the finding that the work is scope covered pursuant to Rule 1(b) it is
necessary to examine whether the Carrier can avail itself to one of the enumerated
exceptions that were proffered during handling of the claim.
The Carrier did not list any of the exceptions in the notice of subcontracting.
The exceptions were addressed during the handling of the claim. The conference
and subsequent discussion between the parties that occurred prior to the actual
work began being performed on March 25, 2005, revealed that the Carrier
contended that an exception applied because the work ". . . required specialized
skills that the Carrier employees do not possess and equipment that the Carrier
does not own and that Carrier forces do not have the skills to operate."
The Organization refuted this defense with the above-discussed photographs,
statements, timelines, and leases to underscore that the work has been performed by
BMWE-represented employees in the past on this subdivision and that the tools and
equipment were common Carrier equipment. Despite requests by the Organization
for an explanation of the "specialized skills" and equipment necessary, the
responses were not forthcoming. There is no evidence in the record that establishes
Form 1
Page 8
Award No. 40411
Docket No. MW-39486
10-3-NRAB-00003-060278
what skills and equipment were necessary for the project. Accordingly, the
affirmative defense has not been shown.
From this record, the other asserted defense of "time requirements" that the
Carrier argued in its Submission was not the defense proffered at the time the
contracting notice was discussed and the work contracted out. See Third Division
Award 37376. Further, even if the defense were considered, the Carrier would not
prevail in the defense. The Carrier argues that Rule 1(b) specifically states that it
can contract out when ". . . time requirements must be met which are beyond the
capabilities of Company forces to meet . . ." and that the Carrier did not have the
necessary capabilities. In support, the Carrier includes 16 separate notices of intent
to contract on the Boone Subdivision in its Submission that were served on the
Carrier in 2004 and 2005. The Carrier cites these notice letters as support for the
Manager of Bridge Maintenance's statement that the instant project was time
sensitive and that the Carrier did not have adequate and qualified forces to perform
the work.
However, the Board carefully reviewed the record. Our review of the record
indicates that the 16 notices were not supplied during handling of the instant claim
on the property. There are numerous Awards that stand for the proposition that ex
parte submissions are not the proper venue for introducing new evidence. The
citations need not be recited here. Accordingly, the 16 notices cannot be considered
by the Board. What is left to consider is the one line in the Manager of Bridge
Maintenance's email, i.e., "This project is time sensitive and the Carrier does not
have adequate qualified work force to perform this work in required time frame."
That statement, absent more, would be insufficient to establish the defense.
A careful reading of the record convinces the Board that the Carrier has not
satisfied its burden of proof relative to its asserted affirmative defenses. Having
established that the work was reserved to BMWE-represented employees pursuant
to Rule 1(b) the inquiry moves to remedy. There is nothing in the record to show
why the Carrier chose to perform this work when it did. Even if the Board were to
consider the 16 notices of intent to subcontract discussed above, all those notices
would show is that work on the Boone Subdivision had been contemplated for a
substantial period of time. As stated above, those notices have not been considered.
Nonetheless, the record contains no showing that the work could not have been
scheduled in a manner so as to include the Claimants. The Claimants were assigned
Form 1 Award No. 40411
Page 9 Docket No. MW-39486
10-3-NRAB-00003-060278
to the Boone Subdivision at the time of the contracting of the box culvert work. We
conclude that the Organization established a loss of work opportunity.
The Organization claims that the Claimants should be compensated for all
hours worked by the contractor. The Carrier counters that full employment of the
Claimants precludes any entitlement to compensation. The Carrier's argument has
been previously rejected. See Third Division Award 37647 and citations therein.
Therefore, in light of the above findings, the Claimants shall be made whole for all
monetary losses.
AWARD
Claim sustained in accordance with the Findings.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an award favorable to the Claimant(s) be made. The Carrier is ordered to make
the Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 14th day of May 2010.