Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40625
Docket No. SG-38876
10-3-NRAB-00003-050311
(05-3-311)

The Third Division consisted of the regular members and in addition Referee Marty E. Zusman when award was rendered.


(Brotherhood of Railroad Signalmen PARTIES TO DISPUTE:


STATEMENT OF CLAIM:



FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



Form 1 Page 2

Award No. 40625
Docket No. SG-38876
10-3-NRAB-00003-050311
(OS-3-311)

This is companion to Third Division Awards 40622, 40623 and 40624. In each claim, there is no dispute that the members of Electronic Technician Gang K-092, of which Claimant J. G. Apostoli, Jr., was a member, were senior in seniority and had not worked at the overtime rate on November 29, 2003. Instead, junior employees of CSC Construction Gang R-961 were given the work at the Carrier's 30th Street Station.


The Organization alleges that the Carrier violated Appendix B-3 (a) and (b) by calling out junior employees.


The Organization has the burden of proof to establish a prima facie case that the Claimant should have been assigned the work. It argues on the property that the Carrier violated Appendix B-3, Sections (a) and (b) which read, in pertinent part, as follows:




(not part of their regular assignment) or continuous with





In this instance, the work was planned on an overtime basis to relocate communication cables for Shoemaker Construction Company at Penn Coach Yard.


The Organization argues that the work accrued to the Claimant because he had the seniority and was previously utilized to support contractors working at the 30th Street Station. The Claimant was qualified and should have been offered the work based on seniority.


The Board finds that there is a prima facie case. Certainly, this was work that was previously assigned. The Board also takes careful note that the work involved relocating communications cables, i.e., work that was never denied on

Form 1 Page 3

Award No. 40625
Docket No. SG-38876
10-3-NRAB-00003-050311
(05-3-311)

property, which could have been performed by the Claimant. In fact, there is no denial to the Organization's background statement that:



The Carrier's position on the property is that the rerouting of existing communication cables was assigned to Construction Gang R-961 in full compliance with the Agreement, supra, because the gang had originally installed the cables and was familiar with the installation, connection and location of the cables to be relocated. The Carrier argues that the work is neither reserved for the Technician class, nor does it accrue to them.


The Board does not agree. There is no showing on the property that the Technician Gang should not have performed the work. The work was given to the Construction Gang due to the fact that "members of gang 8961 had performed work prior to the overtime and made the additional work assignment in accordance with the agreement."


The fact that Gang R-961 had originally installed the cables does not give its members a demand right to relocate the cables at a later date. The Carrier's defense is that the Construction Gang had originally installed the cables and further that the work accrued to those ". . . who were actually performing the work prior to the overtime." The Board finds no proof in the record to support this assertion. The Division Engineer's rebuttal and all others reiterate that the Construction Gang did the initial work and, therefore, it accrued to the junior Construction Gang members because they "were actually performing the work prior to the overtime."


The record indicates that both gangs have and could have performed the work. Appendix B-3 (a) and (b) support the Carrier if proof is provided that the junior employees were, in fact, working on the project immediately prior to the overtime assignment or "continuous with the current tour of duty." No proof was provided to support this affirmative defense. If they were not working on this

Form 1 Award No. 40625
Page 4 Docket No. SG-38876
10-3-NRA8-00003-050311


project, the fact that they initially installed the cables is not supported by any language in the Appendix. What is negotiated is language that, absent the first condition, gives preference to seniority for the overtime.


The Board finds that the Carrier violated the Agreement. The Carrier argues that the claim for the time and one-half rate of pay is improper and excessive, because there is no provision for awarding punitive rate payments for work not performed. While the Board has disagreed with the Carrier's position numerous times and for various reasons when, as here, the Carrier states, "It is well established that the proper penalty on this property for loss of work opportunity is payment at the straight time rate" and no rebuttal is forthcoming from the Organization, it must stand as fact. The claim is sustained at the straight time rate of pay.




      Claim sustained in accordance with the Findings.


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 27th day of August 2010.