Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40665
Docket No. MW-40106
10-3-NRAB-00003-070300
(07-3-300)

The Third Division consisted of the regular members and in addition Referee Michael D. Gordon when award was rendered.


(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE:
(BNSF Railway Company (former Burlington
( Northern Railroad Company)

STATEMENT OF CLAIM:





Form 1 Award No. 40665
Page 2 Docket No. Docket No. MW-40106
10-3-NRAB-00003-070300
(07-3-300)
FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




Following a March 1, 2004, inspection, the Carrier determined bridge 44.8 LS2 near Waverly, Nebraska, needed repair, including concrete restoration. Based on the conclusion of its inspection Structural Engineer that repair required epoxy injection and polymer repair, the Carrier wrote the Organization on March 29:






IThe 2003 letter stated that concrete work would be subcontracted system wide because the Carrier lacked necessary special equipment and materials and its employees lacked necessary expertise. The Organization objected, contending the notice was not specific and concrete work is within the scope of its regular and routine work. The parties met and discussed their differences on February 11, 2004, but were unable to agree. The current status of the disagreement is unclear in this record.

Form 1 Award No. 40665
Page 3 Docket No. Docket No. MW-40106
10-3-NRAB-00003-070300
(07-3-300)
all the necessary skills to perform this work. Work is scheduled to
begin approximately May 3, 2004 and be complete in two weeks.
This letter is intended to inform you of our maintenance programs,
and keep you and your membership abreast of our plans to
accomplish this work, in the spirit of open dialogue between BNSF
and the BMWE.
Should you desire to discuss this matter, Mr. Ron Michelbook can be
available for a conference call at his office in Kansas City at 10:00
AM Central Daylight Time on Friday, April 16, 2004 . . . ."

On April 13, the Organization stated (1) its schedule did not permit participation in a proposed April 16 meeting or conference call (2) the matter appeared the same as one discussed on February 11 (3) a mutual meeting could be arranged if there were differences, but (4) otherwise, the positions expressed on February 11 should be repeated in this claim. No meeting was held.


E-80 Plus Constructors, an outside contractor, performed the concrete restoration repair work between April 19 and 23, 2004. At some point, apparently after the contractor began its work and as part of its assessment responsibility, it was decided that epoxy was not needed. Polymer was used for the repair. Epoxy repairs have been subcontracted by the Carrier since at least 1976. Polymer uses different equipment, material, and skill and is less difficult to perform. It has been done by BMWE-represented employees in the past.


The Organization grieved, citing Rules 1, 2, 5, 55, the Note to Rule 55 and Appendix Y It submits no proper advance notice and meeting required by the Note to Rule 55 occurred because the notice listed polymer and epoxy, whereas only polymer was used.


The Organization claims polymer repairs are contractually reserved as its work. It contends the Carrier's defenses lack merit. At the same time, the Organization tacitly acknowledges the Third Division, as well as on-property Public Law Boards have held that epoxy and polymer work can be performed by outsiders

Form 1 Award No. 40665
Page 4 Docket No. Docket No. MW-40106
10-3-NRAB-00003-070300


under the special work exception in the Note to Rule 55. However, it argues that those cases all involve some epoxy work and are inapplicable to repairs, like the present dispute, where only polymer is used.


The Carrier essentially argues (1) it has the right to subcontract bridge reconstruction using epoxy injection and polymer concrete and it properly did so (2) the Organization did not prove a violation and (3) no damages to the Claimants were proven. More specifically, it asserts (1) polymer alone involves similar specialized skills as when both epoxy and polymer are used together (2) it is not required to piecemeal functions performed by E-80 and (3) although BMWE-represented employees have done some, but not exclusive, concrete restoration with polymers only, the results have not always been successful. The Carrier cites one Third Division decision involving the Union Pacific Railroad and three on-property Public Law Board decisions holding that epoxy/polymer work may be subcontracted. See Third Division Award 31170; Public Law Board No. 4768, Award 10; Public Law Board No. 4768, Award 29 and Public Law Board No. 4402, Award 36.


The Organization's complaint about lack of proper notice is without merit. The March 29 letter was correct when written. The Carrier believed its notice remained true when it contracted with E-80 and when E-80 began the disputed work. Only after the contracted work started was the repair method modified from epoxy/polymer to polymer alone. Nothing indicates the Carrier engaged in subterfuge or acted in bad faith, without due diligence or for any other improper reason regarding the notice.


The same considerations apply to the work itself. Appendix Y provides the Carrier will attempt to reduce subcontracting in good faith "to the extent practicable." On these facts, it would not be practicable to negate the E-80 contract during a fiveday project to begin the job again with Carrier forces. Moreover, the on-property Public Law Board Awards cited by the Carrier involve epoxy/polymer bridge repairs, and, therefore, strongly bolster its position. The Organization provides no arbitral decisions directly requiring assignment of polymer only bridge repairs to its members.


Indeed, seen in its best light, the Organization's evidence regarding bridge repairs reflects a mixed practice. Moreover, acceptance of its position would require that E-80's function be piecemealed in mid-performance and at a stage when the

Form 1 Award No. 40665
Page 5 Docket No. Docket No. MW-40106
10-3-NRAB-00003-070300
(07-3-300)

disputed portion (polymer repair) followed E-80's unchallenged duty to analyze the proper material it would use. Either mixed practice or piecemealing are sufficient to allow this particular subcontract.









This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this Ist day of November 2010.