Form 1
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 40959
Docket No. MW-41302
11-3-NRAB-00003-100147
The Third Division consisted of the regular members and in addition Referee
Edwin H. Benn when award was rendered.
STATEMENT OF CL.
(Brotherhood of Maintenance of Way Employes Division -
( HIT Rail Conference
(Union Pacific Railroad Company
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Dondlinger and Sons Construction) to perform
Maintenance of Way work (replace pillar blocks and related
work) on the piers at BR 277.63 on the Sharon Springs
Subdivision beginning on October 20, 2008 and continuing
through November 19, 2008 (System File D-0852U-23111513700).
(2) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with a proper advance written
notice of its intention to contract out said work and failed to
make a good-faith attempt to reach an understanding
concerning said contracting as required by Rule 52 and the
December 11, 1981 Letter of Understanding.
As a consequence of the violations referred to in Parts (1)
and/or (2) above, Claimants D. Bejan, M. Goin, K. Manley, M.
Schooler and K. Weber shall now each be compensated for two
hundred thirty (230) hours at their respective Group 3 rates of
pay-11
Form 1
Page 2
FINDINGS:
Award No. 40959
Docket No. MW-41302
11-3-NRAB-00003-100147
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
By letter dated September 29, 2008, the Carrier advised the Organization as
follows:
"This is a 15-day notice of our intent to contract the following work:
Location: Bridge 277.63 Sharon Springs Subdivision - near Hays,
Kansas and Bridge 225.15 near Ellsworth, Kansas.
Specific Work: This request is to cover the repairs for two bridges
on the Sharon Springs Subdivision Bridges 277.63 and 225.15.
Furnish all labor, supplies, materials, equipment and supervision to
replace bridge pier tops, install new anchor bolts, level spans, place
dowels and reinforcement bars to face abutments and wing walls
with a minimum of 8" of concrete. (Full scope to be discussed at
showing)"
Conference was held under Rule 52 on October 9, 2008, without resolution.
According to the Organization, the contracted work commenced on October 20,
2008.
Carrier's notice was adequate under Rule 52. See Third Division Award
31170 (". . . the notice given was sufficient to inform the Organization of what work
Form 1 Award No. 40959
Page 3 Docket No. MW-41302
11-3-NRAB-00003-100147
was being contemplated for contracting."). The Carrier's September 29, 2008,
notice meets that test.
The Carrier contracted out bridge repair work in the past and claims
protesting such action under Rule 52 have been denied. See Award 31170, supra,
finding that ". . . the Carrier's evidence is sufficient to establish a past practice of
contracting out concrete bridge repair work . . . ." There is no reason to deviate
from that precedent established between the parties permitting the Carrier to
contract out the work in dispute. The prior precedent is not palpably in error and,
for purposes of stability, must be followed.
The Organization's general arguments seeking to avoid many years of
Awards involving contracting out disputes between the parties concerning many
areas of scope-covered work cannot cause a different outcome. No matter how wellframed the Organization's arguments may be - arguments which address its
positions that the work in dispute has customarily, historically and traditionally
been assigned to and performed by and is reserved to B&B Sub-department
employees as scope-covered work; that the Carrier's actions are not in conformity
with the December ll, 1981, Berge-Hopkins letter; and that the Rule 52 criteria for
contracting out have not been met - putting aside that these kinds of arguments
have been advanced by the Organization in the past, the fact remains that between
these parties (and provided the Carrier follows the notice and conference
requirements in Rule 52) the Carrier has the ability to contract out scope-covered
work if there is a practice showing that the Carrier has contracted out that work in
the past. See Third Division Award 40861:
"The Carrier is correct that in what it refers to as "mixed practice"
cases, the Board has found that contracting of scope-covered work is
permissible under Rule 52 where the Carrier has contracted that
work in the past. See e.g., the Board's recent decisions in Third
Division Awards 40755 (fence construction work) and 40756
(vegetation control). With respect to the type of work performed in
this case [loading ballast], prior Awards have upheld the Carrier's
ability to contract out similar work. See Third Division Awards
33645 and 37644."
Form 1 Award No. 40959
Page 4 Docket No. MW-41302
11-3-NRAB-00003-4 00147
The Board is not blindly following prior Awards and ignoring the
Organization's arguments. Instead, the Board is following the long-held doctrine
that for purposes of stability, prior Awards must be followed unless they are
palpably erroneous. See Third Division Award 34204:
". . . [F[or
purposes of stability, we cannot decide this case de novo,
but we are required to defer to that prior Award. To do otherwise
would be an invitation to chaos and would result in encouraging
parties after receiving an adverse decision to attempt to place a
similar future dispute before another referee in the hope of
obtaining a different result."
The prior Awards between the parties allowing the Carrier to contract out
scope-covered work if a practice exists showing the Carrier has done so in the past
are not palpably in error. Stability requires that we follow that doctrine. If this
Board did not follow that doctrine, chaos would result and the parties would then be
encouraged to engage in referee shopping seeking to find someone who might be
persuaded to simply disregard a long line of decisions.
The result the Organization seeks is a sword with two edges. The
Organization has routinely prevailed in contracting out cases with employees
receiving full make whole relief for lost work opportunities (even though they were
working) where the Carrier failed to follow the notice and conference requirements
in Rule 52. Those claims have been sustained even where the contracting out would
have been permissible under Rule 52 if only the Carrier met its notice and
conference obligations. See e.g., Third Division Award 40763 (although fencing
work could be contracted out because the Carrier had done so in the past, the claim
was sustained because the contracted work began less than 15 days after notice was
given in violation of Rule 52).
If the Board disregarded the long-established precedent between the parties
that allows the Carrier to contact out work where it has an established practice of
doing so in the past, then the Organization's precedent of prevailing in failure to
provide notice and meet conference obligations cases would be open to a similar fate
of being disregarded. If that occurred, then the structure of Rule 52 would be
rendered entirely useless. See Third Division Award 32862:
Form I Award No. 40959
Page 5 Docket No. MW-41302
11-3-NRAB-00003-100147
". . . [O]ur function is to enforce language negotiated by the parties.
In Article IV and as a result of negotiations, the parties set forth a
process of notification and conference in contracting disputes. The
Carrier's failure to follow that negotiated procedure renders that
negotiated language meaningless."
Here, the Carrier met its notice and conference obligations under Rule 52.
There is a practice of contracting out the disputed work in the past. Based on prior
precedent which is not palpably erroneous, the Carrier's actions do not violate Rule
52. The claim shall be denied.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 14th day of April 2011.