Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 41054
Docket No. MW-41160
11-3-NRA1-00003-090521
The Third Division consisted of the regular members and in addition Referee
William R. Miller when award was rendered.
(Brotherhood of Maintenance of Way Employes Division -
( HIT Rall Conference
(Union Pacific Railroad Company
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (Cayior and Gentz) to perform Maintenance of Way work
(transport Maintenance of Way equipment) from Mile Post 97
and Mile Post 88 to Mile Post 86.50 on the South Morrill
Subdivision of the Nebraska Division on July 28, 2008 (System
File J-0852U-268/1508969).
(2) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with a proper advance notice of its
intent to contract out said work and when it failed to make a
good-faith effort to reduce the Incidence of contracting out scope
covered work and increase the use of its Maintenance of Way
forces as required by Rule 52 and the national December 11, 1981
Letter of Agreement.
(3) As a consequence of the violations referred to in Parts (1) and/or
(2) above, Claimants H. Emmons and T. Benda shall now each be
compensated for eight (8) hours at their respective straight time
rates of pay."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
Form I Award No. 41054
Page 2 Docket No. MW-41160
11-3-NRAB-0000.3-090521
The carrier or carriers and the employee or employees involved in this dispute are
respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute were given due notice of hearing thereon.
This case is a companion to Third Division Award 41052, which dealt with a
nearly identical dispute. The arguments presented by the parties in that case are
exactly the same as those set forth in the instant dispute. The only differences between
that case and the instant case involve the names of the Claimants, Mlle Post location,
and claim dates.
For the sake of brevity, the Board will not reiterate the positions of the parties or
its reasoning and logic, but instead refers the parties to the prior Award. The Board
finds and holds on behalf of the Organization. The Claimants shall be compensated as
requested in Part (3) of the claim because there was a showing of lost work
opportunities.
AWARD
Claim sustained.
This Board, after consideration of the dispute identified above, hereby orders that
an award favorable to the Claimant(s) be made. The Carrier is ordered to make the
Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 23rd day of August 2011.