Form I NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 41159
Docket No. MW-41502
11-3-NRAB-00003-110085

The Third Division consisted of the regular members and in addition Referee Patrick Halter when award was rendered.

(Brotherhood of Maintenance of Way Employes Division -
( HIT Rail Conference
PARES TO DISPUTE:
(National Railroad Passenger Corporation (Amtrak)

STATEMENT OF CLAIM:





Form 1 Award No. 41159
Page 2 Docket No. MW-41502


FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The claim, dated November 3, 2009, involves the Carrier's decision to use outside forces to remove and replace fencing at the Wayne Street compound in Niles, Michigan, commencing September 11, 2009 and continuing until the project was completed.


According to the Organization, such work has been ordinarily and customarily performed by BMWE-represented employees since 1975 and the Claimants were available to perform the work. By not assigning the work to the Claimants, the Carrier violated the Scope Rule. Furthermore, the Carrier violated Rule 24 when it did not provide advance notice of its intention to contract out the work.


In response the Carrier asserts that BMWE forces on this property never have performed work of this magnitude and complexity - installing 1,590 feet of seven foot security fencing and ten fence gates including removal of existing fencing - on either an exclusive or ordinary basis. The Carrier asserts it provided notice of its intent to contract out and met with BMWE so it complied with Rule 24.


The progression of the claim on the property shows it was processed in the usual and customary manner, including placement before the highest officer of the Carrier designated to handle it. Following a conference discussion on May 21, 2010 the claim is now properly before the Board for adjudication.


Regarding Rule 24 and whether there is a notice violation, in a letter dated July 6, 2009 the Carrier notified the Organization of its intent to contract out the work

Form 1 Award No. 41159
Page 3 Docket No. MW-41502



because maintenance forces were fully engaged in performing their regular duties. Although forces would be assigned inspection and protection of contractors as needed, they could not complete this project within a reasonable amount of time. Finally, the contract work would not result in the furlough of forces.


On July 27, 2009 the Carrier met with the Organization in conference, but the parties were unable to reach agreement. Following this conference, the Carrier notified the Organization that it would proceed with the project using outside forces.


Based on the above-cited letters and conference, the record contains substantial evidence showing that the Carrier complied with Rule 24, so there is no violation.


The principle is well-established that the burden of proof is on the Organization to establish that the disputed work is scope covered. The Carrier contends that the Organization must prove that BMWE forces exclusively perform this type of work. The Board disagrees. Rather, "exclusivity" applies to jurisdictional disputes between classes and crafts of the Carrier's employees and not to contracting out.


For this situation (contracting out) the Organization must establish that its members have customarily and ordinarily performed the work (fence installation) falling within the scope of the Agreement. The Carrier acknowledges that its employees perform maintenance, repair and replacement work, but it asserts that they have not performed fence installation work - especially installation of this magnitude and complexity.


Although Engineering Daily Activity Reports confirm that Maintenance of Way forces customarily and ordinarily repair and replace existing fencing, they do not support a finding that BMWE forces install new fencing and/or security gates. The Engineering Daily Activity Reports also do not establish that BMWE-represented employees have ordinarily and customarily performed work of this magnitude and complexity - length of new security fence (1,590 feet) height of new fence (seven feet) installation of ten security gates.


Although the Organization asserts that BMWE-represented forces installed the existing fence in 1975, there are no corroborating statements or documents to support this assertion in the record. There is, however, the Carrier's letter issued in 1996 to the Organization stating that the Carrier had no record of fence installation being performed by its forces on the Michigan District.

Form 1 Award No. 41159
Page 4 Docket No. MW-41502
11-3-NRAB-00003-110085

The burden of proof rests with the Organization to establish that BMVVErepresented forces ordinarily and customarily handle the installation of new fencing and security gates. The lack of support for its assertion about installing the existing fence in 19'15, the Carrier's 1996 letter concerning the record of fence installation by Carrier forces on the Michigan District and the absence of corroborative new-fence work in Engineering Daily Activity Reports or a document similar thereto, compels the Board to conclude that the Organization failed to establish that new fence and gate installation is work ordinarily and customarily performed by BMNE-represented employees.


In short, the Organization did not establish by substantial evidence that forces on the Michigan District customarily and ordinarily perform the work of installing new fence and security gates. In the absence of substantial evidence to support its position, this claim must be denied.


Claim denied.

This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.


                    NATIONAL RAILROAD ADJUSTMENT BOARD

                    By Order of Third Division


Dated at Chicago, Illinois, this 21st day of November 2011.