The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
The claim is for work performed by a contractor (Caylor and Gentz Construction) on November 20, 2007. The work at issue, removal, renewal and installation of track panels, frogs and the associated work of grading digging and clearing, the Organization asserts is reserved work. The Carrier asserts the existence of a "mixed practice" on this property; it may use its own or contractor forces and equipment to perform this work. The Carrier contends it provided notice of its intent to contract this work on the North Platte Service Unit on January 10, 2007. In addition to challenging the sufficiency of the notice, the Organization presented evidence in the form of a letter dated January 31, 2007 that on January 16, 2007 it requested a conference concerning the notice. The Carrier ignored this request.
During the on-property processing of this claim, the Carrier disputed the occurrence of the claimed contracting. It put the Organization to its proof. In response, the Organization submitted a statement from B. Nienhueser. Although there are lines on the form used by the employee for his signature and date, the document is unsigned and undated. In addition, the statement does not refer specifically to the events of November 20, 2007, the date of the claim. Instead, the Claimant refers to work referenced in the claim by claim number. Claimant Nienhueser adds:
The claim sets out the date of the work. However, the statement covers more than one day. It is not clear from the statement whether it covers November 20, 2007. The absence of a signature and date are not explained. The evidence in the dispute decided in Third Division Award 40965, which involves the same notice and contractor as in this case, differs in one important respect. In Award 40965, the Organization submitted on the property a handwritten statement specifically setting forth the dates of the work involved in the claim. It established that the claimed work occurred.
The Organization bears the burden of proof to establish each element of its claim. (Third Division Award 31930.) Without evidence that the work in question occurred, there can be no claim of a violation. The Organization failed to meet its burden of proof to establish that the contracting complained of occurred as claimed. With this finding, the Board does not reach the notice and conference issues raised by the Organization.
This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.