Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 41473
Docket No. MW-40939
12-3-NRAB-00003-090238

The Third Division consisted of the regular members and in addition Referee Patrick Halter when award was rendered.

(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE:
(CP Rail SystemJDelaware and Hudson
( Railway Company

STATEMENT OF CLAIM:





Form 1 Award No. 41473
Page 2 Docket No. MW-40939
12-3-NRAB-00003-090238
and applicable rates of pay for all straight time and overtime hours
expended by the outside forces in the performance of the aforesaid
work beginning October 15, 2007 and continuing and Claimants T.
Vanderpool, K. Chilson and A. Kovaleski shall now each be
compensated at their respective and applicable rates of pay for all
straight time and overtime hours expended by the outside forces in
the performance of the aforesaid work beginning September 6,
2007 and continuing."

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




This claim involves the Carrier's use of outside forces to install steel arches, pour concrete foundations and perform related crown repair work beginning on September 5, 2007 at the Nicholson Tunnel in Factoryville, Pennsylvania.







Form 1 Award No. 41473
Page 3 Docket No. MW-40939
12-3-NRAB-00003-090238
mileage 656.0 on Canadian Pacific Railway's Freight Main
Subdivision. This work must be undertaken for the safety of railway
employees working in the tunnel as well as for a safe fluidity of the
trains passing through the tunnel. Due to the specialized equipment
and personnel required for the drilling and grouting portions of this
work, CPR will be contracting this project.
The work will be executed in two phases located in the area 1 of the
tunnel:







This claim, as well as the issues and arguments set forth therein, are acknowledged by the Organization as a continuation of its claim which was decided by the Board in Third Division Award 41419. In other words, the instant claim is materially similar, if not identical, to the claim adjudicated by the Board in Award 41419, wherein the Board sustained the claim for the front-end loader, but did not sustain the claim for the crown repair work performed at Nicholson Tunnel.


Unlike Award 41419 wherein the claim identified outside forces operating a front-end loader, there is no allegation identified in the instant claim regarding outside forces operating equipment not identified in the notice.


For the reasons set forth in detail in Award 41419, which is incorporated herein by reference, the claim in this proceeding is denied for the crown repair work, including steel arches and concrete foundations at Nicholson Tunnel.

Form 1 Award No. 41473
Page 4 Docket No. MW-40939
12-3-NRAB-00003-090238

As noted by the Board in Award 41419, "[A]pparent from this record are the diverse and divergent views held by the parties about Rule 1 and Appendix H. Discussions occurred in good faith notwithstanding these differing views and the absence of any understandings between the parties about contracting out."








This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.



                      By Order of Third Division


Dated at Chicago, Illinois, this 13th day of December 2012.