Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 41476
Docket No. MW-41135
12-3-NRAB-00003-090500

The Third Division consisted of the regular members and in addition Referee Patrick Halter when award was rendered.

(Brotherhood of Maintenance of Way Employes Division - ( IBT Rail Conference PARTIES TO DISPUTE: (CP Rail System/Delaware and Hudson ( Railway Company

STATEMENT OF CLAIM:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
Form 1 Award No. 41476
Page 2 Docket No. MW-41135
12-3-NRAB-00003-090500

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21,1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




On November 29, 2007, a semi-trailer transporting a crane struck and severely damaged the Pangburn Road overpass at Mile Post 490.83 on the Freight Main Subdivision. Upon notification of this situation, the Carrier placed crews in Oneonta and Binghampton on standby while it assessed the damage. An inspection revealed that there was extensive damage to the bridge span and girders, which rendered the track impassable. The mainline was closed during the time that outside contractor forces repaired the bridge and overpass.


On December 10, 2007, the Organization filed a claim asserting that BMWErepresented employees were ready, willing and able to perform the claimed work, but the Carrier violated Rules 1, 3, 4, 11, 28 and Appendix H when it "sent home their B&B Employees and opted to have a contractor perform their work."





Form 1 Award No. 41476
Page 3 Docket No. MW-41135
12-3-NRAB-00003-090500
The B&B Crew were notified of the incident and placed on hold until
the situation could be assessed and a determination made as to
whether the available manpower was sufficient to complete the work
within the tight timeline given the emergency situation.
At 3:30 PM the crew was released after it was determined that they
could not complete the emergency work in the time required.
To further clarify, we did not place our employees on standby until
notifying a contractor to perform the work. Rather, we placed our
employees on standby until the emergency situation could be assessed
and a determination made as to whether the available manpower was
sufficient to complete the work in the tight timeline . . . . [E]mployees
were released from hold and allowed to go home after completing
their regular work day. The employees were not released from duty,
nor placed on furlough[.]"

On March 11, 2008, the Organization appealed the claim denial. Therein it observed "that this incidence was an emergency . . . which we have conceded," but BMWE "does not accept nor condone the Carrier's actions surrounding the matter . . . . Regardless of the circumstances and need for a specialized crane notwithstanding, the Carrier's force" has historically performed this work. The only reason the Carrier placed force employees on standby, the Organization asserts, was not to assess the damage, but rather to determine if contractor forces could be obtained to perform the claimed work.


The Carrier denied the appeal on May 7, 2008 and this matter was discussed during a conference held on August 22, 2008. Having been handled in the usual and customary manner on the property, including up to and including the Carrier's highest designated officer, the claim is now before the Board for final adjudication.


Notwithstanding the finding that the claimed work is scope-covered, there is no dispute that the incident constituted an "emergency" as that word is used in Rule 1. When an "emergency" exists, a Carrier is accorded flexibility in its response because

Form 1 Award No. 41476
Page 4 Docket No. MW-41135


time is of the essence. For example, notice and conference requirements are effectively suspended.

Given these findings, the Organization has not established a violation of any Rules as alleged.

Therefore, the Board will deny the claim in accordance with the precedent established in on-property Third Division Award 37288 wherein an "emergency" existed and allegations of Rules violations were set aside.







This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Third Division


Dated at Chicago, Illinois, this 13th day of December 2012.