Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 41476
Docket No. MW-41135
12-3-NRAB-00003-090500
The Third Division consisted of the regular members and in addition Referee
Patrick Halter when award was rendered.
(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE:
(CP Rail System/Delaware and Hudson
( Railway Company
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (New Century Construction Company) to perform
Maintenance of Way work (bridge repair and related work) on the
railroad bridge over Pangburn Road in Princeton, New York on
November 29, 2007 instead of B&B employes D. Welch, L. Martin,
T. Delameter, R. Holleran, E. Carr, B. Allmendinger, J. Perry and
J. Moelder (Carrier's File 8-00599 DHR).
(2) As a consequence of the violation referred to in Part (1) above,
Claimants D. Welch, L. Martin, T. Delameter, R. Holleran, E.
Carr, B. Allmendinger, J. Perry and J. Moelder shall now each be
compensated for ten and one-half (10.5) hours at their respective
time and one-half rates of pay."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
Form 1 Award No. 41476
Page 2 Docket No. MW-41135
12-3-NRAB-00003-090500
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21,1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute were given due notice of hearing thereon.
On November 29, 2007, a semi-trailer transporting a crane struck and severely
damaged the Pangburn Road overpass at Mile Post 490.83 on the Freight Main
Subdivision. Upon notification of this situation, the Carrier placed crews in Oneonta
and Binghampton on standby while it assessed the damage. An inspection revealed
that there was extensive damage to the bridge span and girders, which rendered the
track impassable. The mainline was closed during the time that outside contractor
forces repaired the bridge and overpass.
On December 10, 2007, the Organization filed a claim asserting that BMWErepresented employees were ready, willing and able to perform the claimed work, but
the Carrier violated Rules 1, 3, 4, 11, 28 and Appendix H when it "sent home their
B&B Employees and opted to have a contractor perform their work."
On January 11, 2008, the Carrier denied the claim as follows:
"An emergency situation occurred at approximately 1240/29 ET when
a semi-trailer transporting a crane struck the overhead railway bridge
at MP 490.83 of the Freight Main subdivision. Inspection discovered
extensive damage to the bridge span and girders. As a result, the
mainline was closed for approximately 20 hours.
Repairs were planned using bridge material from an abandoned
bridge near this location which was previously double track. These
repairs needed to be completed on a timely basis in order to open the
mainline.
Form 1 Award No. 41476
Page 3 Docket No. MW-41135
12-3-NRAB-00003-090500
The B&B Crew were notified of the incident and placed on hold until
the situation could be assessed and a determination made as to
whether the available manpower was sufficient to complete the work
within the tight timeline given the emergency situation.
At 3:30 PM the crew was released after it was determined that they
could not complete the emergency work in the time required.
To further clarify, we did not place our employees on standby until
notifying a contractor to perform the work. Rather, we placed our
employees on standby until the emergency situation could be assessed
and a determination made as to whether the available manpower was
sufficient to complete the work in the tight timeline . . . . [E]mployees
were released from hold and allowed to go home after completing
their regular work day. The employees were not released from duty,
nor placed on furlough[.]"
On March 11, 2008, the Organization appealed the claim denial. Therein it
observed "that this incidence was an emergency . . . which we have conceded," but
BMWE "does not accept nor condone the Carrier's actions surrounding the
matter . . . . Regardless of the circumstances and need for a specialized crane
notwithstanding, the Carrier's force" has historically performed this work. The only
reason the Carrier placed force employees on standby, the Organization asserts, was
not to assess the damage, but rather to determine if contractor forces could be
obtained to perform the claimed work.
The Carrier denied the appeal on May 7, 2008 and this matter was discussed
during a conference held on August 22, 2008. Having been handled in the usual and
customary manner on the property, including up to and including the Carrier's
highest designated officer, the claim is now before the Board for final adjudication.
Notwithstanding the finding that the claimed work is scope-covered, there is no
dispute that the incident constituted an "emergency" as that word is used in Rule 1.
When an "emergency" exists, a Carrier is accorded flexibility in its response because
Form 1 Award No. 41476
Page 4 Docket No. MW-41135
12-3-NRAB-00003-090500
time is of the essence. For example, notice and conference requirements are effectively
suspended.
Given these findings, the Organization has not established a violation of any
Rules as alleged.
Therefore, the Board will deny the claim in accordance with the precedent
established in on-property Third Division Award 37288 wherein an "emergency"
existed and allegations of Rules violations were set aside.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 13th day of December 2012.