Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 41576
Docket No. MW-41877
13-3-NRAB-00003-120171
The Third Division consisted of the regular members and in addition Referee
Dr. Lou Imundo when award was rendered.
(Brotherhood of Maintenance of Way Employes Division -
( IBT Rail Conference
PARTIES TO DISPUTE: (
(BNSF Railway Company (former Burlington
( Northern Railroad Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The discipline [Level S thirty (30) day record suspension and a
three (3) year review period] imposed upon Mr. R. Valencia by
letter dated November 15, 2010 for alleged violation of MOWOR
2.14.2 Before Reporting Clear of Authority Limits in connection
with charges of not informing the train dispatcher that all
employees and multiple work groups using the authority were
clear of track before reporting clear of authority limits at
approximately 0900 hours on September 7, 2010 at about Mile Post
35 on the Chicago Subdivision while assigned as track inspector
was arbitrary, capricious and in violation of the Agreement
(System File C-11D040-7/10-11-0108 BNR).
(2) As a consequence of the violation referred to in Part (1) above,
Claimant R. Valencia shall now receive the remedy prescribed by
the parties in Rule 40(G)."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
Form 1
Page 2
Award No. 41 576
Docket No. MW-41877
13-3-NRA]3-00003-120171
The carrier or carriers and the employee or employees involved in
dispute
are respectively carrier and employee within the meaning of the Railway Labor Act,
as approved June 21,1934.
involved herein.
Division of the Adjustment Board has jurisdiction over the dispute
Parties to said dispute were given due notice of hearing thereon.
The Claimant's rights were violated because he was not accorded a fair and
impartial Investigation.
Claim sustained.
AWARD
ORDER
This Board, after consideration of the dispute identified above, hereby orders
that an award favorable to the Claimants) be made. The Carrier is ordered to make
the Award effective on or before 30 days following the postmark date the Award is
transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 18th day of March 2013.