NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION

Award No. 41888   Award No. 41889   Award No. 41890
Docket No. MW-40697   Docket No. MW-40701   Docket No. MW-41016
14-3-080527   14-3-080532   14-3-090271
Award No. 41891   Award No. 41892   Award No. 41893
Docket No. MW-41090   Docket No. MW-41147   Docket No. MW-41148
14-3-090375   14-3-090510   14-3-090515
Award No. 41894   Award No. 41895   Award No. 41896
Docket No. MW-41187   Docket No. MW-41276   Docket No. MW-41660
14-3-090458   14-3-100116   14-3-110141
Award No. 41897   Award No. 41898   Award No. 41899
Docket No. MW-41679   Docket No. MW-41682   Docket No. MW-41686
14-3-110261   14-3-110275   14-3-110304
Award No. 41900   Award No. 41901   Award No. 41902
Docket No. MW-41698   Docket No. MW-41731   Docket No. MW-41732
14-3-110349   14-3-110169   14-3-110184
Award No. 41903
Docket No. MW-41857
14-3-120142
 
(Brotherhood of Maintenance of Way Employes Division -
  ( IBT Rail Conference
PARTIES TO DISPUTE: (
  (BNSF Railway Company (former Burlington
  ( Northern Railroad Company)

STATEMENT OF CLAIM: As shown in the above mentioned Docket Nos. and not
repeated herein.

FINDINGS: The Third Division of the Adjustment Board finds:
  Page 2   Award No. 41888 et al
Docket No. 40697 et al
 
14-3-NRAB-00003-080527 et al
 
  That the disputes were certified to the Third Division of the Adjustment Board ex parte by the petitioning party; and
 
  Under date of May 21, 2014, the petitioning party addressed a formal communication to the Arbitration Assistant requesting withdrawal of these cases from further consideration by the Division which request is hereby granted.
 

AWARD
  Claims withdrawn.
 

NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division

Dated at Chicago, Illinois, this 16th day of June 2014.