Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 43654 Docket No. MW-43490 19-3-NRAB-00003-160234
The Third Division consisted of the regular members and in addition Referee Gerald E. Wallin when award was rendered.
(Brotherhood of Maintenance of Way Employes Division (IBT Rail Conference
PARTIES TO DISPUTE: (
(CSX Transportation, Inc.
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The claim* as presented by General Chairman D. Albers on November26,2014toDivisionEngineerJ.Fortuneshallbeallowed presented because said claim was not disallowed by Director Labor Relations R. Miller in accordance with Rule 24(b) (System File I59711314/2014-179155 CSX).
*The initial letter of claim will be reproduced within our initial submission."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute were given due notice of hearing thereon. Form 1 Award No. 43654
Page 2 Docket No. MW-43490
19-3-NRAB-00003-160234
The Organization raised a procedural issue as a threshold matter that must be addressed before considering the merits of the dispute. According to the on-property record, the claim was conferenced on July 29, 2015. Thereafter, by letter dated November 5, 2015, the Organization asserted the Carrier was in default because the claim was never denied. The Carrier never refuted the Organization's contention.
Rule 24b of the parties' Agreement reads, in pertinent part, as follows:
"*** When a claim or grievance is not allowed, the carrier's Highest Designated Labor Relations Officer will so notify, in writing, whoever listed the claim or grievance (employee or his union representative) within sixty (60) days after the date the claim or grievance was discussed of the reason therefor. When not so notified, the claim will be allowed."
(Underscoring supplied)
Given the state of the record, the claim must be sustained as presented.
AWARD
Claim sustained.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division
Dated at Chicago, Illinois, this 17th day of May 2019.