Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 43764 Docket No. MW-42529 19-3-NRAB-00003-140168
The Third Division consisted of the regular members and in addition Referee Andria S. Knapp when award was rendered.
(Brotherhood of Maintenance of Way Employes Division (IBT Rail Conference
PARTIES TO DISPUTE: (
(Union Pacific Railroad Company (former Chicago
and North Western Transportation Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside forces (Snelton) to perform Maintenance of Way and Structures Department work (remove/replace switches and related work) at the south end of yard 9 in the Proviso Rail Yard in Northlake, IL on December 4, 5 and 6, 2012 (System File B-1301C-107/1579275 CNW).
(2) The Agreement was violated when the Carrier assigned outside forces (Snelton) to perform Maintenance of Way and Structures Department work (remove/replace switches 45 through 50 and related work) at the Proviso Rail Yard in Northlake, IL, at approximately Mile Post 14.5 to Mile Post 15 on December 8, 10 and 11, 2012 (System File B-1301C-108/1579947).
(3) The Agreement was violated when the Carrier assigned outside forces (Snelton) to perform Maintenance of Way and Structures Department work (remove/replace switchesalong 53-66 switching lead and related work) at the Proviso Rail Yard in Northlake, IL, at approximately Mile Post 14 on December 17, 2012 (System File
B-1301C-109/1579948).
(4) The Agreement was further violated when the Carrier failed to furnish the General Chairman with advance written notice of its intent to contract out the above-referenced work or make a good faith attempt to reach an understanding concerning such contracting as required by Rule 1B and Appendix '15.'
(5)As a consequence of the violations referred to in Parts (1) and/or
(4) above, Claimants B. Mendiza, S. Duda, T. Noakes and S. Hugger shall now '… each be compensated for and [sic] equal share of all hours, reportedly ninety-six (96) man/hours at the appropriate rate, that the contractor's forces spent performing their work, at the applicable rate of pay.' (Emphasis in original.)
(6)As a consequence of the violations referred to in Parts (2) and/or
(4) above, Claimants C. Rapier, B. Mendiza, S. Duda, T. Noakes and S. Hugger shall now '… each be compensated for and [sic] equal share of all hours, reportedly one hundred and sixty-five (165) man/hours at the appropriate rate, that the contractor's forces spent performing their work, at the applicable rate of pay.' (Emphasis in original.)
(7)As a consequence of the violations referred to in Parts (3) and/or
(4) above, Claimants C. Rapier, B. Mendiza, S. Duda, T. Noakes and S. Hugger shall now '… each be compensated for and [sic] equal share of all hours, reportedly sixty (60) man/hours at the appropriate rate, that the contractor's forces spent performing their work, at the applicable rate of pay.' (Emphasis in original.)"
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute were given due notice of hearing thereon.
The parties have combined three claims for presentation to the Board in this one case, due to the claims presenting the same issues and nearly the same fact patterns, occurring in the same time frame and in roughly the same location.
In all three claims, the Organization alleges that the Carrier violated Rule 1B of the parties' Agreement when it assigned an outside contractor, Snelton, to assist its Maintenance of Way forces in replacing and/or repairing switches at various locations in the Proviso Yard (the south end of yard 9, switches 45-50, and along 53-66 switching lead), near Northlake, Illinois, in December 2012. Track maintenance, including repairing and replacing switches, is work that has historically, customarily and traditionally been performed by MoW forces, which brings it within the Scope Rule. Contracting may occur pursuant to the terms agreed in Rule 1B of the Agreement, which requires notice in advance and an opportunity to meet to discuss ways to reduce theamountofcontractingbeforeScope-coveredworkmaybeassignedtooutsideforces. Rule 1B also establishes the circumstances under which work may be contracted: special skills, special equipment, or special material; work such that the Carrier is not adequately equipped to handle it; time requirements that are "beyond the capabilities of Company forces to meet"; and emergencies. The Carrier did not provide adequate notice or an opportunity to conference as required by Rule 1B of the Agreement, nor did it offer a basis for contracting out scope-covered work. The December 27, 2011, "notice" that the Carrier provided was not proper advance notification, because it was generic in nature and failed to identify any specific contracting out transactions. Finally, the Carrier failed to establish that the work contracted fell within any of the exceptions set forth in Rule 1B that would permit contracting of scope-covered work. The Carrier owns the same equipment that was used by the contractor, and its own MoW forces have repaired and replaced switches throughout the Carrier's system for years. MoW Forces were available, willing and qualified to perform the work if it had been assigned to them.
According to the Carrier, the Organization has failed to meet its burden of proof. TheCarriergavetheOrganizationadequatenoticeonDecember27,2011,ofitspossible intent to utilize contractors to assist its own forces in "removing, replacing, loading and unloading switches and track panels…," and when the parties met in conference on the notice, they discussed the reasons why the Carrier needed to contract out the work. The Carrier is permitted to contract out work "that the Company is not adequately equipped to handle." The statement from Manager Nudera established that the Carrier did not have adequate personnel or equipment in the area to complete the work in a timely fashion without the use of supplemental forces. The work was properly contracted out under the "not adequately equipped" exception.
In contracting claims, the Organization must first establish that the work occurred as alleged and that it is Scope-covered work under the Agreement. The next issue is whether the notice was sufficient under Rule 1(B). If it was, the Carrier must establish that the proposed contracting falls under one of the exceptions established in Rule 1(B): special skills, equipment, or materials; the Carrier is not adequately equipped to handle the work; special time requirements "beyond the capabilities of the Company"; or emergency conditions.
The Board recognizes that the work of removing, repairing and replacing switcheshashistorically,traditionally andcustomarily beenperformedby theCarrier's Maintenance of Way forces and that it accordingly is covered by the Scope Rule in the Agreement.
The next step in the analysis is whether the notice was sufficient under Rule1B.TheCarriersenttheOrganizationa15-Day NoticeofIntenttoContract Work dated December 27, 2011:
"THIS IS TO ADVISE OF THE CARRIER'S INTENT TO CONTRACT THE FOLLOWING WORK:
PLACE: Proviso Yard on the Chicago Service Unit.
SPECIFIC WORK: Providing fully fueled, operated and maintained track excavators (track hoes) to assist Railroad with removing, replacing, loading and unloading switches, and track panels, excavating ditches, drains and installing culvers commencing January 1, 2012 thru December 31, 2012."
Whether a notice is sufficient under Rule 1B is a perennial topic for the Board, and there are innumerable Awards on the subject. One problem is that the complexity of the Carrier's operational requirements is such that there is no single template or checklist to use when it comes to what a notice must contain. Ultimately, the measure of adequacy for a notice under Rule 1B is whether it provides sufficient information for the Organization: (1) to be able to determine whether it wants to meet in conference with the Carrier to discuss the proposed contracting out and (2) to be able to engage in meaningful discussion in conference if it does. This does not mean that the Carrier must specify every detail of the who, what, when, where, how and why of a proposed contracting transaction; one purpose of meeting in conference is for the Organization and Carrier to be able to discuss the proposal more fully and for the Organization to be able to ask any questions it might have about the proposal. Conversely, the Board has found notices that are overbroad to be inadequate. Frequently, the Board is tasked with balancing the Organization's need for sufficient information with the Carrier's interest in maintaining as much flexibility as possible with respect to contracting out by issuing a notice that is as general as it can be while providing the information that the Organization is entitled to.
Consideringthe noticeat issue here, the Board concludesthatitwassufficientfor purposes of Rule 1B. It is specific as to the location of the proposed contracting out: the Proviso Yard in the Chicago Service Unit. It is also specific as to the equipment and the nature of the work to be contracted out: "track excavators (track hoes) to assist Railroad with removing, replacing, loading and unloading switches and track panels." The Board has been critical in the past of notices that cover too much time, butgiventhespecificity ofthelocationandthenatureofthework,theone-yearduration set forth in the December 27, 2011, notice is acceptable. The Organization contends that the notice fails to set forth the basis for the proposed contracting. The notice does not contain the specific language "the basis for the contracting out is [fill in the blank]," but the Carrier's statement that it is proposing to contract specifically "to assist Railroad [forces]" (emphasis added) with removing and replacing switches is strongly indicative that the Carrier is not adequately equipped to handle the work with the equipment and forces that it has. The basis for the contracting is another topic that the parties can discuss in conference. The notice could have been more specific, but it met minimum standards for adequacy under Rule 1B.
The Organization next contends that the Carrier failed to establish a legitimate basis under Rule 1B for contracting the work. Specifically, it stated that the Carrier owns the same equipment that was used by the contractor, which Carrier forces could have operated, so that "not adequately equipped" did not apply. However, the record
includes statements from managers that contradict that assertion. Regarding the first of the three claims (Claim #1579275), Manager James Nudera wrote:
"We didn't start working at the south end of yard 9 until the 5th of dec. and we used sneltons [sic] equipment to assist our gang plus we used our American crane. Our other equipment was being utilized by our men installing switches at the east end of the bowl track 45 - 50. all men mentioned in this claimed [sic] were working at the time, at both locations." (Emphasis added.)
This is sufficient to establish that the Carrier was not adequately equipped to complete thework using its existing forces and equipment. There are similar statements regarding the other two claims. With respect to the second claim (Claim #1579948) and the third claim (Claim #1579947), Manager of Track Maintenance Chase Nichols submitted the same statement:
"15 day notice was given. Employees in claim were working same hours that day. Carrier did not have enough equipment or manpower to finish workasjobsthatwereupforbidkeptgoingwithoutanybidders."(Emphasis added.)
Again, management's statement confirms that the Carrier was not adequately equipped to complete the work, in terms of either equipment or manpower. The employee statements in the record confirm that contractor forces were used in conjunction with Carrier forces, not instead of them. They also confirm management's assertion that there was a shortage of manpower, which management attributed to bid jobs "going without bidders."
On the basis of the record before it, the Board concludes that the work in dispute in these claims met the "not adequately equipped" exception to Rule 1B, and that the Carrier did not violate the Agreement when it contracted the work out.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division
Dated at Chicago, Illinois, this 16th day of July 2019.
LABOR MEMBER'S DISSENT
TO
AWARD 43764, DOCKET MW-42529, AWARD 43765, DOCKET MW-42538 (Referee Andria S. Knapp)
The Majority erred in its findings in these cases. Specifically, the Majority erred in accepting the Carrier's notices and in its findings related to the exceptions under Rule 1B.
Under Rule 1B and Appendix "15", any contracting notice must include, amongst other things, the work to be contracted and the "reasons therefor". These requirements have been enforced by recent arbitrations under this Agreement. See Third Division Awards 41044, 42419, 42423, 42435 and 42438 from Arbitrators Malamud and Larney. Also see, Third Division Awards 43577, 43578, 43582, 43589 and 43592, which were adopted on March 27, 2019. The Majority failed to distinguish this precedent or even acknowledge it existed. Accordingly, for this reason, these awards should be given no precedential value.
In addition, prior to contractingout reserved work, the Carrier has an obligation to establish a Rule 1B exception. See Award 40409. The Carrier also has an obligation to attempt to procure rental equipment and schedule the work to utilize its own forces to perform scope covered work. See Awards 42423, 42427, 42429 and Award 153 of Public Law Board No. 2960. Notwithstanding, in this case, the Majority found the Carrier was able to establish a Rule 1B exception based on a manager's statement that equipment and men were all being utilized elsewhere. However, the notification relied on by the Carrier was dated December 27, 2011, but the claimed work did not occur until December 2012. Accordingly, the Carrier had nearly a year to plan to make its men and equipment available for performing the claimed work. This Board has previouslyaddressed a similar fact pattern. See on-propertyThird Division Awards 42423, 42435, 42437 and 42438. Specifically, the Majority in Award 42435 held:
"*** Certainly the most implausible exception asserted by Carrier is that it was not adequately equipped to handle the work, that is, maintenance of way employees were unavailable as they were assigned to work on other projects. The Board concurs in the Organization's position that the lead time of five and a half months that elapsed from the time Carrier issued the subject 15-dayNotice of Intent to subcontract the re-roofing work, was more than sufficient for Carrier to find a total of fourdays within that span of time that would not conflict with otherprojects, therebyfreeingseven maintenance of wayemployees to perform the disputed scope covered work. In not finding such a period to utilize its own forces to perform the disputed work strongly indicates to us that poor scheduling of work on the part of Carrier was responsible for Carrier having to subcontract the work. We hold this same reasoning applicable to Carrier's asserted exception that time requirements were such that it was beyond the capabilities of its own forces to complete the work.
Labor Member's Dissent Awards 43764 and 43765 Page Two
"All that was required of Carrier was to find four consecutive days within the five and a half month time period that would permit assigning seven maintenance of way employees to perform the scope covered work thereby assuring its completion consonant with the time requirements."
Accordingly, the Majority erred when it failed to follow or even distinguish the recent onproperty precedent and these awards should be given no precedential value.
Respectfully submitted,
Zachary C. Voegel
Zachary C. Voegel Labor Member