Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD

THIRD DIVISION

Award No. 43831 Docket No. MW-44701 19-3-NRAB-00003-180177

The Third Division consisted of the regular members and in addition Referee Andria S. Knapp when the award was rendered.

(Brotherhood of Maintenance of Way Employes Division - (IBT Rail Conference

PARTIES TO DISPUTE: (

(Kansas City Southern Railway Company

Former SouthRail Corp

STATEMENT OF CLAIM:

"Claim of the System Committee of the Brotherhood that:

(1) The Agreement was violated when, from July 13, 2016 to July 22, 2016, the Carrier assigned or otherwise allowed outside forces to perform Maintenance of Way work (tie installation) inbetween/or at Mile Post 288 to Mile Post 286 and Mile Post 283 to Mile Post 281 on the Artesia Sub [System File C 16 07 13 (050)/K0416-6898 SRL].

(2) The Agreement was further violated when the Carrier failed to notify the General Chairman, in writing, as far in advance of the date of the contracting transaction as is practicable and in any event not less than fifteen (15) days prior thereto regarding the aforesaid work and when it failed to assert good-faith efforts to reduce the incidence of subcontracting and increase the use of Maintenance of Way forces as required by the Side Letter of Agreement dated February 25, 1988 and the December 11, 1981 National Letter of Agreement.

(3)As a consequence of the violations referred to in Parts (1) and/or

(2) above, Claimants J. Comer, P. Wright, B. Seale, A. Young, J. Dempsey, L. Baldridge, R. Conner, II, D. Johnson, B. Wheeler,

D. Waldon and J. Horton shall now each '... be compensated eight (8) hours regular rate of pay for ten (10) day(s) which

totals $2144.80 for the Laborers plus late payment penalties based on a daily periodic rate of .0271% (Annual Percentage Rate of 9.9%) calculated by multiplying the balance of the claim by the daily periodic rate and then by the corresponding number of days over sixty (60) that this claim remains unpaid.' (Emphasis in original)."

FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.

Parties to said dispute were given due notice of hearing thereon.

The Carrier and the Organization operate on the Carrier's properties under three separate collective bargaining agreements. This case arises under the South Rail Agreement (SLR).

This Claim arose when the Carrier assigned an outside contractor, Trak-Time, to perform tie installation work on July 13 through 22, 2016, at or near Mile Post 288 to Mile Post 286 and Mile Post 283 to Mile Post 281 on the Artesia Subdivision. According to the Organization, eleven contractor employees worked eight hours a day for ten days, installing ties at the Saltillo siding from MP 288 to 286 near Saltillo, Mississippi, and at the Glen siding from MP 283 and MP 281 near Tupelo, Mississippi. The original claim was accompanied by a handwritten Initial Questionnaire/ Information Form for Claims or Grievances, to which was attached an additional sheet with handwritten statements from two of the Claimants, attesting to the fact that they had witnessed the contractors performing the work in dispute. According to the Carrier's records, Trak-Time only worked at the mileposts in the claim on only two dates, July 13 and 14, 2016.

According to the Organization, installing ties is work historically, traditionally and customarily assigned to the Carrier's Maintenance of Way forces and protected by the Scope Rule in the parties' Agreement. The parties entered into a side Letter of Agreement dated February 25, 1988, that sets forth the circumstances under which the Carrier may contract out bargaining unit work, none of which apply here. Moreover, the Letter of Agreement requires the Carrier to provide advance written notice of any proposed contracting out and to meet and discuss the matter with the Organization. The Carrier did not provide adequate notice, which the Board has recognized in prior cases is sufficient to warrant sustaining the claim.

The Carrier contends that the Organization did not meet its burden of proof. KCS did provide notice to the Organization, when it sent its Annual Notice of Intent to contract work for calendar year 2016 by letter dated December 15, 2015. It has provided this type of notice for many years; the notice lists the contractors the Carrier plans to use for its system/production/capital projects and general maintenance and support work, with a description of the type of work it plans to have each contractor complete. Track & Time was listed in the notice. The Annual Notice advises the Organization that the Carrier has neither the necessary equipment nor the manpower available to complete the referred to in the notice in a timely manner, because its own forces would be fully engaged on other projects, and that is sufficient to justify contracting out under Rule 39. The Carrier also issued a supplemental notice on May 13, 2016, that was directed specifically at the MSLLC Ties and Rail Relay project, which was projected to take seven weeks, starting June 27, 2016. The parties conferenced the Notices with no agreement being reached, and the Carrier proceeded to contract the work. Contracting has long been the history, practice and tradition on the property, with the result that there is a mixed practice that permits the Carrier to continue to contract the work. Finally, the Organization has not been able to establish that the work occurred as alleged; the Carrier's records establish that Trak-Time worked in the area claimed for two days, not ten.

The parties having been unable to resolve the dispute through the grievance process, the matter was appealed to the Board for a final and binding decision.

The Board notes first that there is an irreconcilable dispute in the facts regarding the dates and locations that Trak-Time worked. The Organization claimed that Trak-Time worked ten days in two locations, between Mile Post 288 and Mile Post 286 and between Mile Post 283 and Mile Post 281, from July 13 through July 22, 2016. Carrier records show, however, that Trak-Time worked in those locations on only two dates, July 13 and 14, 2016. The Board is unable to determine from the evidence in the record which of those two versions of the facts is correct. (1)Accordingly, it must dismiss the Claim as it relates to the eight disputed dates, and focus solely on the admitted dates, July 13-14.

The Carrier argues that the work claimed by the Organization is not Scopecovered work because the Organization cannot establish that it has been performed exclusively in the past by its Maintenance of Way forces. The Board has previously rejected that position in favor of a standard that looks to see if the work has historically, customarily and traditionally been assigned to MoW forces, and tie installation meets that standard.

The Carrier maintains that its history of contracting out work on the property has created a mixed practice, in which work is assigned both to its own forces and to contractors. If this is true, then the Carrier may continue its practice without violating the Agreement. But there is no real proof of a mixed practice. The record includes Annual Notices of Intent dating back to 2009, and there is no denying that the Carrier engages in a substantial amount of contracting. The Annual Notices, however, are too generic in nature for the Board to conclude that otherwise Scope-covered work has been regularly assigned to outside contractors to the point that it has lost its character as Scope-covered work. The parties agreed at the arbitration hearing that the docket of cases presented to the Board was the first one to include subcontracting claims in thirteen years. The fact that the parties have been able to work out their differences in the past does not mean that the Organization has given up its rights under the Agreement.

Although the work is Scope-covered, it may still be contracted out pursuant to the side Letter of Agreement entered into by the parties effective February 25, 1988. It provides, in relevant part:

"It is the intent of the Agreement for the SRC to utilize maintenance of way employees under rules of the Agreement to perform work included within the scope of the Agreement; however it is recognized that in certain specific instances the contracting out of such work may be necessary provided one or more of the following conditions are shown to exist:

1) Special skills necessary to perform the work are not possessed by Maintenance of Way Employees.

2) Special equipment necessary to perform the work is not owned by the Carrier or is not available to the Carrier for its use and operation thereof by its Maintenance of Way Employees.

3) Time requirements exist which present under-takings not contemplated by the Agreement that are beyond the capacity of its Maintenance of Way Employees.

In the event the SRC plans to contract out work because of one or more of the criteria described above, it shall notify the General Chairman in writing as far in advance of the date of the contracting transaction as is practicable and in any event, not less than fifteen (15) days prior thereto. Such notification shall clearly set forth a description of the work to be performed and the basis on which the SRC has determined it is necessary to contract out such work according to the criteria set forth above.

If the General Chairman, or his representative, requests a meeting to discuss matters relating to the said contracting transaction, the designated representative of SRC shall promptly meet with him for that purpose and the parties shall make a good faith effort to reach an agreement setting forth the manner in which the work will be performed. It is understood that when condition 3 is cited for contracting work, SRC, to the extent possible under the particular circumstances, shall engage its Maintenance of Way Employees to perform all maintenance work in the Maintenance of Way and Structures Department and construction work in the Track Subdepartment, with due consideration given to the contracting out of construction work in the Bridge and Building Subdepartment to the extent necessary. If no agreement is reached, SRC may nevertheless proceed with said contracting and the Organization may file and progress claims in connection therewith.

Nothing herein contained shall be construed as restricting the right of SRC to have work customarily performed by employees included with the Scope of the Agreement from being performed by contract in emergencies that prevent the movement of traffic when additional force or equipment is required to clear up such emergency condition in the shortest time possible. . . ."

The Side Letter of Agreement identifies three circumstances under which the Carrier may contract out bargaining unit work: (1) special skills not possessed by MoW employees; (2) special equipment not owned by the Carrier or otherwise available for operation by its forces; and (3) time requirements such that the work cannot be completed on time using only the Carrier's forces.

The Side Letter also requires written notice be provided to the Organization in advance of the contracting transaction. The purpose of notice is to give the Organization a heads up that the Carrier plans to contract out what would otherwise be bargaining unit work in enough time for the Organization and the Carrier to meet and discuss ways to minimize contracting if the Organization has any questions or objections. To that end, the language of the Agreement states: "Such notification shall clearly set forth a description of the work to be performed and the basis on which the SRC has determined it is necessary to contract out such work according to the criteria set forth above." (Emphasis added.)

The question of what constitutes adequate notice is not a new one for the Board. The Board has held previously that the notice must include sufficient information for the Organization to make an informed decision about whether it wants to object and to be able to prepare to engage in meaningful discussions with the Carrier about alternatives to the proposed contracting. Without that, the parties would not be able to engage in the "good faith effort" envisioned in the Side Letter of Agreement.

In this case, the Carrier's December 15, 2015, Annual Notice of Intent to contract for the next calendar year was supplemented by a notice dated May 13, 2016, that focused on the "MSLLC Ties and Rail Relay" project. The notice set forth the type of work, the type of equipment, the length of the project, its projected start date, and its location--"MSLLC - Vicksburg and Meridian Subdivisions." The basis given for the proposed contracting was stated as "The Carrier does not have the equipment or available manpower to perform these projects in a timely manner." The Organization contends that the notice did not sufficiently identify the basis for the proposed contracting. The Board does not agree. The notice indicates that some 75 contractors were expected to work seven weeks on the project, 10 hours a day (on a 10 on/4 off schedule). The size of the project alone is sufficient for the Organization to understand that the Carrier probably does not have the manpower to complete the work in the time frame allotted. Given the number of contractors involved, it is likely that the Carrier does not own enough equipment either. The notice might not be as detailed as the Organization would like, but it is sufficient for the Organization to evaluate whether it wants to object to the proposed contracting and to participate in a meet and discuss session with the Carrier. The Board concludes that notice was adequate.

The final issue for the Board to decide is whether the contracting out was permissible under any of the standards set forth in the Agreement. As briefly noted above, the notice itself suggested that the project was a large one that could not be completed using only the Carrier's MoW forces and equipment. The nature of track maintenance work is such that carriers have to focus on implementing and completing large maintenance, renovation and construction projects during fair weather. This means that its staffing requirements will vary widely throughout the year, with more manpower needed in the spring, summer and fall and less in the wintertime. It is not economically feasible for a carrier to maintain year round a workforce large enough to perform all the work that needs to be done in peak production periods. Inevitably, outside contractors will be needed to supplement the Carrier's own forces. The same is true of equipment needs--they vary with staffing needs. The Board concludes that the basis given by the Carrier in the notice for the proposed contracting--that it did not have the manpower or the equipment to complete the projects in a timely fashion.

AWARD

Claim denied.

ORDER

This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant(s) not be made.

NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division

Dated at Chicago, Illinois, this 4th day of September 2019.

1. Although the Claim was accompanied by a page with two handwritten statements on it, the Board notes that the two statements were brief and did not provide any detail. The two statements, which were supposedly written by two different individuals, were word for word the same. Moreover, the handwriting, including signatures, on the two statements were identical. This significantly undermines their credibility.