Arbitration Committee established by Section 11(a) of the New York Dock Conditions.' They agreed that the undersigned neutral would act as the sole member of the Arbitration Committee. At the neutral member's request, the patties waived the 45-day time limitation for issuing this decision as set forth in Section 11 (c) of the New York Dock Conditions.
Following the merger, the Organization and the Carrier entered into several important merger implementing agreements predicated on dividing much of the UP into a hub and spoke operating system. Two of these hubs were at St. Louis, Missouri and North Little Rock, Arkansas. The North
Little Rock/Pine Bluff Hub Merger Implementing Agreement went into effect on February 1, 1998. The St. Louis Hub Merger Implementing Agreement went into effect on November I, 1998.
Both of these merger implementing agreements had a savings clause defining the relationship between the merger implementing agreements and the applicable schedule agreements. Article VIII(A) of the St. Louis Hub Merger Implementing Agreement reads:
Identical language appears in Article VIII(A) of the North Little Rock/Pine Bluff Hub Merger Implementing Agreement.
This dispute concerns to what extent a side letter attached to the St. Louis Hub Merger Implementing Agreement modifies or supersedes the Missouri Pacific-Upper Lines Schedule Agreement which is the working agreement at another hub. The Laying Off and Leave of Absence Rule on the Missouri Pacific-Upper Lines, which was originally adopted on or about October 22, 1952, provides employees with a 30-day buffer period (except in cases of illness or injury) before employees are required to obtain a formal leave of absence or forfeit their seniority. More specifically, Section I of the Laying Off and Leave of Absence Rule in the Schedule Agreement provides:
Side Letter No. 24 of the St. Louis Hub Merger Implementing Agreement, which is dated April 15. 1998, states: BLE v. UPRR Page 3
Hub Merger Implementing Agreement. If Side Letter No. 24 changed the Schedule Agreement everywhere, there would be no reason for the parties to insert a non-referable clause in the side letter.
The BLE Committee membership who are subject to the terms of the St. Louis Hub Merger Implementing Agreement ratified the Agreement by an 84.1 percent vote. However, only those engineers working at points encompassed by the St. Louis Hub Merger Implementing Agreement voted in the ratification canvass. Conversely, those employees at other locations on the Missouri Pacific-Upper Lines did not vote on the terms and conditions in the St. Louis Hub Merger Implementing Agreement. The constitution and bylaws of the International Organization provide that a change in a schedule rule is not effective unless ratified by employees who are subject to the rule. More specifically, Sections 43 (a) and 43(b) of the International Constitution and Bylaws bar the Organization's officers from entering into an agreement that changes a rule governing the wages and working conditions of engineers without ratification by the affected membership.' Since the Organization Committee members at the North Little Rock/Pine Bluff Hub did not vote on the St. Louis Hub Merger Implementing Agreement, the laying off and leave absence rule remains unchanged at North Little Rock. Division 48, International Brotherhood of Locomotive Engineers v. Windham, Civ. Action 86-2313-C-2 (E.D. MO 1986).
Assuming arguendo, that Side Letter No. 24 is unclear or ambiguous, the negotiating history supports the Organization's interpretation. The former General Chairman iterated in his affidavit that the Organization only agreed to reduce the 30-day limitation period to 15 days in the Schedule Rule to short circuit the Carrier's very real threat of applying an inferior Schedule Agreement to the
' Section 33(x)(1) of the Constitution and Bylaws of the International Organization provide a similar mandatory ratification process for merger agreements. BLE v. UPRR Page 7
entire St. Louis Hub territory. However, that inferior agreement could not have been selected by the Carrier in any other Hub touching on the Missouri Pacific-Upper Lines territory. Therefore, it is illogical that the General Chairman and the Organization would agree to modify the Schedule Rule beyond the St. Louis Hub inasmuch as the Chicago & Eastem Illinois Schedule Agreement could not be adopted beyond that Hub.
Furthermore, each merger implementing agreement was negotiated separately and became effective at different times. The parties clearly intended that the terms and conditions of each merger implementing agreement would only apply to the territory expressly covered by the particular implementing agreement.
Article VIII(A) of the St. Louis Hub Merger Implementing Agreement and identical clauses in the other implementing agreements, including Article VIII(A)of the North Little Rock/Pine Bluff Hub Merger Implementing Agreement, demonstrate that the schedule rules are saved unless expressly modified by the Merger Implementing Agreement. Nothing in Side LetterNo. 24 suggests that the parties were modifying the laying off and leave of absence rule for the entire property covered by the Schedule Agreement. The savings clause in the North Little Rock/Pine Bluff Hub Merger Implementing Agreement limits the application of Side Letter No. 24 to the territories within the scope of the St. Louis Hub Merger Implementing Agreement.
Side Letter No. 24 amended the laying off and leave of absence schedule rule across the Missouri Pacific-Upper Lines. Stated differently, the amended rule is expansive. 1t pertains to more
BLE v. UPRR . Page 8 NYD § I1 Arb. Committee
territory thanjust the St. Louis Hub. The schedule rule was modified wherever the Missouri PacificUpper Lines schedule agreement is the applicable working agreement.
Nowhere in Side Letter No. 24 is there any language restricting the change in the Laying Off and Leave of Absence Rule to the St. Louis Hub. The absence of such language is a direct contrast to the presence of limiting language on other side letters. For example, Side Letter No. 26 to the St. Louis Hub Merger Implementing Agreement, which amended Schedule Rule 26(D), expressly states that the revision applies only to the St. Louis Hub. Similarly, Side Letter No. 23 to the St. Louis Hub Merger Implementing Agreement contains verbiage restricting the breadth of the rule change so that the amended rule is effective only at certain locations. The language in these two side letters demonstrates that the parties knew how to write restrictive terms. If the parties did not intend for Side Letter No. 24 to completely and entirely modify the Schedule Rule they would have inserted limiting language in the side letter.
Next the express language of Side Letter No. 24 conclusively demonstrates that the change in the rule went beyond the St. Louis Hub. The third paragraph of Side Letter No. 24 states that the current rule will be amended but does not restrict the amendment to the St. Louis Hub. The second paragraph reveals that the Carrier requested modification to existing rules. It would be senseless for the Carrier to ask for a change to a rule and then agree to a bifurcated application of the amendment whereby employees within the St. Louis Hub are treated differently from employees outside the St. Louis Hub.
_ Lastly, the words in Side Letter No. 24 constitute specific language. It is axiomatic in theVM(A) savings clause in the St. Louis Hub Merger Implementing Agreement is a broad and general provision. Side Letter No. 24 is a very specific and detailed provision that supersedes Article VIB(A). Thus, the savings clause is irrelevant.
The parties bargained separately over the various hub merger implementing agreements and the Carrier implemented each merger implementing agreement at a different time. This bargaining process and environment strongly suggests that the parties contemplated that the provisions of each hub merger implementing agreement would pertain only to employees and property covered by the particular merger implementing agreement. Otherwise, the Carrier and Organization would have negotiated a master hub agreement, the terms of which would pierce the boundaries of each hub.
In this particular case, the North Little Rock/Pine Bluff Hub .Merger Implementing Agreement became effective many months before the Carrier implemented the St. Louis Hub Merger Implementing Agreement. The employees subject to the North Little Rock/Pine Bluff Hub Merger Implementing Agreement understood the changes in working conditions brought about by the terms of their hub merger implementing agreement. Of course, these employees were not privy to the terms and conditions of the separately negotiated merger agreement governing the St. Louis Hub. It is noteworthy that the North Little Rock/Pine Bluff Hub Agreement does not contain a side letter equivalent to Side Letter No. 24 of the St. Louis Hub Merger Implementing Agreement.
Therefore, the North Little Rock/Pine Bluff Hub employees were not subject to any terms of the St. Louis Hub Agreement or, put differently, that they were not suddenly subject to a modification of their working conditions when the St. Louis Hub Agreement became effective nine
BLE v. UPRR Page 10months later. It would be incongruous that, for a nine-month period, the North Little Rock/Pine Bluff Hub engineers would be subject to the 30-day limitation period in the Schedule Rule and then, on November I, 1998, the more stringent 15-day limitation period would suddenly be imposed on these engineers.
In sum, the context in which the Hub Agreements were negotiated strongly supports the Organization's construction of Side Letter No. 24.
In addition, the express language of Side LetterNo.24 buttresses the Organization's position. As the Organization persuasively argues, the second paragraph of Side Letter No. 24 refers to ". . . negotiations of this Hub . . ." which clearly announces that the parties were bargaining over terms and conditions applicable to the territory covered by the St. Louis Hub Merger Implementing Agreement. The language does not state during negotiations of "all Hubs" or, during negotiations of "Hubs attendant to the Missouri Pacific-Upper Lines." It logically follows that the outcome of those negotiations pertained exclusively to the St. Louis Hub.
Absent any language showing that the breadth of the change in the laying off and leave of absence rule extended beyond the demarcation of the St. Louis Hub, the clearlanguage of Side Letter No. 24 restricts the modification to employees subject to the terms and conditions of the St. Louis Hub Merger Implementing Agreement.
Inasmuch as the terms of Side Letter No. 24 of the St. Louis Hub Merger Implementing Agreement did not extend beyond the territory covered by the St. Louis Hub, Article VIII(A) of North Little Rock/Pine Bluff Hub Merger Implementing Agreement preserved (saved) the
BLE v. UPRR Page I 1Oreanization's Ouestion at Issue: Does Side Letter No. 24 of the St. Louis Hub Merger Implementing Agreement modify the MPUL Laying Off and Leave of Absence Schedule Rule beyond the geographical territory of the St. Louis Hub?
Carrier's Ouestion at Issue: Did the April 15, 1998 letter agreement amending the "Laying Off and Leave of Absence" rule dated October 22, 1952 and contained on Page 250 of the current Collective Bargaining Agreement apply only to the St. Louis Hub or does it apply to all of the MPUL committee?
Answer to Carrier's Ouestion at Issue: For the reasons more fully stated in this Opinion, Side Letter No. 24 applies only to employees and territory subject to the terms and conditions of the St. Louis Hub Merger Implementing Agreement.
Arbitrator
Neutral and Sole Committee Member