FINDINGS: '
Essentially, the background,;arguments and the dispute at issue are not unlike that advanced to this Board in Case No. 2,. except the claim here involves five carmen at DeCoursey Yard who were furloughed on September 15, 1983.
Although the date of furlough is admittedly closer to the date of the June 18, 1984 coordination of Mechanical Department facilities and forces in the Greater Cincinnati Terminal, we find no reason to hold that the furloughs were in anticipation of such coordination or to be of other than the opinion we set forth in denying the claims covered by Case No. 2. AWARD:

Claim denied.

J. ;T. .Will.iams, Carrier Member

i

Jacksonville, FL
,lay 29, 1985



0 owicz, mployee hcnaber