NATIONAL MEDIATION BOARD, ADMINISTRATOR
SPECIAL BOARD OF ADJUSTMENT NO. 1087
In the Matter of the Arbitration
-between-
Brotherhood of Maintenance of OPINION AND AWARD
Way Employes Case No. 14
-and
National Carriers' Conference
Committee
In accordance with the October 25, 1996 Agreement in effect
between the above-named parties, the Undersigned was designated
as the Chairman and Neutral Member of the referenced Board to
hear and decide a dispute concerning these parties.
A hearing was held in Miami, Florida on February 4, 2002 at
which time the representatives of the parties appeared. All
concerned were afforded a full opportunity to offer evidence and
argument and to examine and cross-examine witnesses consistent
with the Agreement that created the Board. The Arbitrator's Oath
was waived.
THE QUESTION AT ISSUE
The parties failed to stipulate an issue to be resolved by
the Board. The parties authorized the Board to formulate an
appropriate issue. The organization proposed the following
issue:
Was the rate increase applicable to the
classification of Foreman made pursuant to
the new CSXT System Agreement (Attachment A
of the Strongsville Agreement, dated May 23,
1
.' S8ANo.lo87
QWO
I~
1999), a subsequent wage increase applicable
to claimant M. J. Cronin's "protected rate"
under Article IV, Section 1 of the Agreement
in Mediation Case No. A-7128, dated February
7, 1965, as amended by Article XII of the
Agreement in Mediation Case No. A-12718 (SubNos. 1-8), dated September 26, 1996 ("the
JSA").
The Carriers proposed the following issue:
Is Claimant M. J. Cronin's, ID 518869,
February 7, 1965 Job Stabilization protective
rate of $17.82 per hour (rate as of December
1, 2000) the correct protective rate of pay?
On the basis of the arguments of the parties and a careful
review of the entire record, the Board deems a fair statement of
the issue to be:
Did the Carrier, CSX Transportation, Inc.,
violate Article IV, Section 1 of the
Agreement in Mediation Case No. A-7128, dated
February 7, 1965, as amended by Article XII
of the Agreement in Mediation Case No. A12718 (Sub-Nos. 1-8), dated September 26,
1996 by calculating Claimant M. J. Cronin's
February 7, 1965 Job Stabilization protective
rate to be $17.82 per hour (as of December 1,
2000) based on the carrier's decision not to
treat the rate increase applicable to the
classification of Foreman made pursuant to
the new CSXT System Agreement (Attachment A
of the Strongsville Agreement, dated May 23,
1999), as a subsequent wage increase under
Article IV, Section 1 of the Agreement in
Mediation Case No. A-7128, dated February 7,
1965, as amended by Article XII of the
Agreement in Mediation Case No. A-12718 (SubNos. 1-8), dated September 26, 1996 ("the
JSA")?
BACKGROUND
The Claimant filed claims for benefits pursuant to the
February 7, 1965 agreement for the months of November 2000,
December 2000, January 2001, and February 2001. In a letter
2
SBA ANa,io8'? ,a
dated February 12, 2001, the Carrier explained the Carrier's
decision to deny the claim for the month of December 2000:
Records reflect that your earnings were
equal to and/or exceed your Feb 7 guarantee
for the month of December 2000. Therefore,
you are not entitled to a guarantee payment
for December 2000.
As information, your Feb 7 guarantee is
$17.81 [sic] per hour.
(Organization Exhibit 3 and Carrier Exhibit C.)
In a letter dated April 5, 2001, the organization clarified
the pending claims on behalf of the Claimant:
Claimant Cronin submitted Feb 7 claims
beginning January, 2001 for the Month of
December, 2000 and each month thereafter
through February 2001. February 15, 2001
Claimant Cronin received a letter from J. D.
Brinkworth, dated February 12, 2001. This
letter informed Claimant Cronin that he did
not qualify in the month of December for Feb.
7 benefits and Mr. Brinkworth further advised
that Claimant Cronin's guarantee rate was
$17.81 [sic] per hour, not the Foreman rate
of $18.63 as claimed by Claimant Cronin.
September 26, 1996 Claimant Cronin was
working a Yard Foreman position at State
Street Yard, Indianapolis, IN and his
guarantee rate should reflect the current
Basic Foreman Rate, currently $18.75 and July
1, 2000 $18.63.
The February 7, 1965 Agreement clearly
requires that Section 1 employees not be put
in a worse position with respect to
compensation and benefits. Had Claimant not
been furloughed, he would have worked
December 1, 2000 and would have been paid
$18.63 for no less than 8 hours straight
time.
As a result of this Agreement violation
please advise when Claimant Cronin will be
paid 8 hours straight time at $18.63 for
December 1, 2000 plus the current Foreman
3
SBA ~so.log7
ago
I~(
rate ($18.75) for the months of January and
February, 2001. This claim is made
continuous until such time as Claimant
Cronin's guarantee rate is adjusted to
reflect the current Basic Foreman Rate of
pay.
(Organization Exhibit 3 and carrier Exhibit G.)
In a letter dated June 27, 2001, the Carrier declined the
claim for the following reasons:
You are taking exception to the Feb 7th
protected rate of Mr. Cronin, contending that
his protected rate should be $18.63 (for the
month of December 2000), based upon his
holding a yard foreman position at State
Street Yard, Indianapolis, IN, on September
26, 1996. The Carrier's records reflect that
claimant held Position 5KA1-639, Foreman,
with a rate of $15.07 per hour on September
26, 1996. With the subsequent general wage
increases and cost-of-living adjustments, his
protected rate for the month of December
2001, is $17.82, and $17.94 beginning in
January 2001.
In view of the above, Mr. Cronin's Feb 7th
protection claim for the month of December
2000, was properly calculated and claimant
was not entitled to a guarantee payment this
month. His claims for January and February
2001, were properly calculated at the
appropriate rates referenced above, and he
was paid guarantee in the amounts of
$3,048.10 and $896.50, respectively.
(Organization Exhibit 3 and Carrier Exhibit J.)
The parties failed to resolve the matter during the
grievance procedure. The dispute proceeded to arbitration for a
final and binding determination.
4
5$R
ND. to$l Awp
PERTINENT PROVISIONS
MEDIATION AGREEMENT
FEBRUARY 7, 1965
ARTICLE I - PROTECTED EMPLOYEES
Section 1 -
All employees, other than seasonal employees, who were in
active service as of October 1, 1964, or who after October 1,
1964, and prior to the date of this Agreement have been restored
to active service, and who had two years or more of employment
relationship as of October 1, 1964, and had fifteen or more days
of compensated service during 1964, will be retained in service
subject to compensation as hereinafter provided unless or until
retired, discharged for cause, or otherwise removed by natural
attrition. Any such employees who are on furloughs of the date
of this Agreement will be returned to active service before March
1, 1965, in accordance with the normal procedures provided for in
existing agreements, and will thereafter be retained in
compensated service as set out above, provided that no back pay
will be due to such employees by reason of this Agreement. For
the purpose of this Agreement, the term "active service" is
defined to include all employees working, or holding an
assignment, or in the process of transferring from one assignment
to another (whether or not October 1, 1964 was a work day), all
extra employees on extra lists pursuant to agreements or practice
who are working or are available for calls for service and are
expected to respond when called, and where extra boards are not
maintained, furloughed employees who respond to extra work when
called, and have averaged at least 7 days work for each month
furloughed during the year 1964.
ARTICLE IV - COMPENSATION DUE PROTECTED EMPLOYEES
Section 1 -
Subject to the provisions of Section 3 of this Article
IV, protected employees entitled to preservation of employment
who hold regularly assigned positions on October 1, 1964, shall
not be placed in a worse position with respect to compensation
than the normal rate of compensation for said regularly assigned
position on October 1, 1964; provided, however, that in addition
thereto such compensation shall be adjusted to include subsequent
general wage increases.
5
S6R
No.
1DB7
AWo 1`(
MEDIATION AGREEMENT
SEPTEMBER 26, 1996
ARTICLE XII - WORKFORCE STABILIZATION
Part A
Section 1 - The February 7, 1965 Agreement
Entitlement to certain elements of job security, currently
available under the February 7, 1965 Agreement (Agreement), shall
be upgraded, so that employees who have at least ten continuous
years of service will be entitled to the protection.
Section 2
(a) Article I, Section 1 of the Agreement shall be amended
to read as follows:
Section 1 - All employees, other than seasonal employees,
who are in active service and who have or attain ten (10) or more
years' of employment relationship will be retained in service
subject to compensation as herein provided unless or until
retired, discharged for cause, or otherwise removed by natural
attrition. For the purpose of this Agreement, the term "active
service" is defined to include all employees working, or holding
an assignment, or in the process of transferring from one
assignment to another (whether or not the date on which such ten
or more years of employment relationship is acquired was a work
day). An employee who is not regularly assigned on the date the
employee is otherwise eligible to achieve protected status under
this Section will be deemed to be protected on the first day
assigned to a regular position in accordance with existing rules
of the BMWE Agreement.
(c) Article IV, Section 1, of the Agreement shall be amended
to read as follows:
"Section 1 - Subject to the provisions of Section 3 of this
Article IV, protected employees who hold regularly assigned
positions shall not be placed in a worse position with
respect to compensation than the normal rate of compensation
for said regularly assigned position as of the date they
become protected; provided, however, that in addition
thereto such compensation shall be adjusted to include
subsequent wage increases."
6
sBAc ~3o. L03-' A,_00!
Agreement
Between
CSX Transportation, Inc.
And
Its Maintenance of Way Employees
Represented by the
Brotherhood of Maintenance
of Way Employes
Effective June 1, 1999
RULE 28 - RATES OF PAY
Rates of pay in Appendix "P" shall be considered negotiated
rates.
APPENDIX "P"
CSX Transportation, Inc.
(except former Clinchfield Railroad)
Rate Schedule
Effective June 1, 1999
Rates per hour Positions
$17.69 Production Foreman
Scale Inspector
Welding Foreman
$17.42 Welder - Track and Structural
$17.37 Foreman-Bridge and Facilities
$17.11 Plumber
Basic Track Foreman
$17.09 Machine Operator "A"
$17.01 Bridge Inspector
Track Inspector
$16.83 Assistant Production Foreman
$16.65 Assistant Bridge & Facilities Foreman
$16.60 Machine Operator "B"
$16.30 Assistant Track Foreman
$16.18 Assistant Track Inspector
$16.01 Bridge Operator/Tender
Welder Helper
$15.56 Lubricator/"Blue Hat"
$15.27 Production Trackman
$14.89 Basic Trackman
$14.66 Crossing watchman
POSITION OF THE ORGANIZATION
In the context of Article IV, Section 1, the organization
asserts that the CSXT System Agreement contained a subsequent
wage increase for the basic Track-Foreman pursuant to Rule 28 and
7
58A
NO. 1o1~,? AWp iq
Appendix P of the Agreement. The organization maintains that the
disputed amount should be included in the claimant's protected
rate. The organization reasons that the Claimant obtained
protection on September 26, 1996 as a Yard Foreman and
established a protective rate. It is the position of the
Organization that the CSXT System Agreement eliminated the Yard
Foreman position and replaced the Yard Foreman position with the
Track Foreman position.
The Organization insists that the elimination and
replacement of the positions caused a wage increase of $.78 per
hour to occur. As a subsequent wage increase occurred within the
meaning of Article IV, Section 1, the organization specifies that
the Claimant's protected rate should have included the $.78 per
hour. The Organization emphasizes that the rate for the Basic
Track Foreman became the new rate for such positions because of
the elimination of the position of Yard Foreman. As a result,
the organization stresses that the Basic Track Foreman rate
became the Claimant's protected rate.
The Organization notes that a failure to include the
disputed amount creates inequities by causing former Conrail
employees, who became employees of the Carrier on June 1, 1999,
to have higher protected rates than the Claimant, who had
obtained protected status with the Carrier on September 26, 1996,
and by possibly enabling some CSX Foremen, whose prior agreements
paid more than the Claimant's Agreement, to have higher
protective rates than the Claimant. The organization contends
8
S0A No.loB-l 01-1
that such an absurd result, which enables employees who were not
subject to the Job Stabilization Agreement while working for the
acquired carrier to have higher protected rates than the
Claimant, lacks validity under a proper interpretation of the Job
Stabilization Agreement.
The organization points out that the 1999 Systemwide restructuring agreement, which dovetailed the foreman
classifications to establish a rate of pay for Basic Track
Foremen, generated a "subsequent wage increase" for the Claimant
within the meaning of Article IV, Section 1. The Organization
argues that the Claimant's protected rate should reflect the
disputed increase.
The organization highlights that the Carrier's position
relies on a misreading of Article IV, Section 1 by using the 1965
"subsequent general wage increase" standard rather than the any
"subsequent wage increase" standard contained in the 1996
amendment to Article IV, Section 1. As the disputed amount meets
the requirements of Article IV, Section 1, as amended, the
organization declares that the Carrier's effort to prove that the
disputed amount was not a "general" wage increase lacks
persuasiveness.
The Organization observes that the disputed amount would
constitute a general wage increase even under the 1965 version of
Article IV, Section 1. The Organization cites certain precedent
from Special Board of Adjustment No. 605 to support this
analysis. The organization comments that Special Board of
9
S OA
lub, (DR-?
14
Adjustment No. 605 found that "a general wage increase need not
be uniform to be `general'." (Award No. 147 (1969) (Friedman,
Neutral) (Organization Exhibit 6).) The Organization explains
that all of the positions in the foreman classification received
increases as a result of the re-structuring and the System
Agreement. The Organization elaborates that the lack of
uniformity does not mean that the increases did not constitute
general wage increases. The organization acknowledges that
Special Board of Adjustment No. 605 did not find payments to
selected positions to eliminate inequities to be the equivalent
of a general wage increase under Article IV, Section 1. (Award
No. 163 (1969) (Rohman, Neutral); Award No. 196 (1970) (Rohman,
Neutral); Award No. 361 (1973) (Rohman, Neutral); and Award No.
371 (1973) (Rohman, Neutral) (Organization Exhibits 8 and 9.)
The organization reiterates that the entire group of foremen
received various increases to obtain the new rate of Basic Track
Foremen and therefore the disputed amount constitutes a general
wage increase.
The organization summarizes that Article IV, Section 1
provides that all subsequent wage increases become part of an
employee's protected rate. The Organization underscores that the
CSXT System Agreement increased the wage rate for the position
that afforded the Claimant protected status. The Organization
urges that the Claim be sustained.
POSITION OF THE CARRIER
The Carrier asserts that the Claimant had a protected rate
10
S8~ nsa. lo9't f
of $17.82 per hour, rather than $18.63 per hour, as of December
1, 2000 because the Claimant became protected on September 26,
1996. The Carrier emphasizes that the current rate of a Basic
Track Foreman does not constitute the Claimant's protected rate.
Instead, the Carrier explains that the claimant's protected rate
evolved from the Claimant's protected rate as of September 26,
1996 and subsequent general wage increases.
The Carrier clarifies that the Organization mistakenly
included the rate rationalization amount for the foreman position
in the June 1, 1999 System Agreement pursuant to Rule 28. The
Carrier views the negotiated rates to be voluntary adjustments
that constituted a rate rationalization rather than a general
wage increase. The carrier describes that some rates of pay
increased, some rates of pay remained unchanged, and a few rates
of pay decreased. The Carrier stresses that the significant
structural changes consolidated approximately 400 rates of pay
into 16 rates of pay. The Carrier rejects the treatment of the
rate rationalization adjustment as a subsequent wage increase to
calculate the Claimant's protected rate. The Carrier indicates
that a general wage increase occurs when all employees receive a
cost of living adjustment or an increase in salary. The Carrier
recounts that the development of a uniform rate and
classification system lacks the status of a general wage increase
as contemplated by the parties or as provided by the Job
Stabilization Agreement.
The Carrier pinpoints that the employees did not receive an
11
SSA No. ttoln Awo 114
equal increase or a percentage increase. The Carrier argues that
the inclusion of the term "negotiated rates" in Rule 28 of the
Agreement and the absence of the term "general wage increase" in
the rate rationalization provision reflects that the skilled
negotiators did not intend to treat the rate rationalization
amounts as a general wage increase. The Carrier refers to
certain arbitral precedent from Special Board of Adjustment No.
605 (Award No. 163 (1969) (Rohman, Neutral); Award No. 196 (1970)
(Rohman, Neutral); Award No. 361 (1973) (Rohman, Neutral); and
Award No. 371 (1973) (Rohman, Neutral)) to highlight the
requirements for finding that a general wage increase exists.
The Carrier verifies that the Claimant received the proper
protected rate that included actual subsequent general wage
increases and cost of living adjustments. The Carrier reiterates
that the rate rationalization did not constitute a general wage
increase. The Carrier requests that the Claimants rate of
$17.82 per hour be upheld. The Carrier therefore urges that the
claim should be denied.
OPINION
I. Introduction
This case involves language interpretation. The parties
stipulated that the Organization--as the moving party--has the
burden to prove its case by a fair preponderance of the credible
evidence.
In analyzing the record, the Special Board of Adjustment
underscores that Section II(A) of the October 25, 1996 agreement
12
SBA Nb. 1pT)
p,.so v4
between the parties that led to the creation of this Special
Board of Adjustment indicates that:
The Board shall not have the authority to add
contractual terms or to change existing
agreements governing rates of pay, rules and
working conditions.
The following analysis reflects these limitations on the
authority of the Board.
II. The Nature of the Dispute
Article IV, Section 1 of the February 7, 1965 Agreement, as
amended, provides certain safeguards to adjust the rate of
compensation for protected employees. As a threshold matter, the
parties disagree about the proper interpretation and application
of the September 16, 1996 amendment to Article IV, Section 1 of
the February 7, 1965 Agreement. Specifically, the 1996 amendment
contains the phrase "subsequent wage increases" instead of
"subsequent general wage increases," the formulation set forth in
the original version of that provision.
The Carrier contends that a clerical error occurred when
Presidential Emergency Board No. 229 inadvertently failed to
include the word "general" in the recommended amendment to
Article IV, Section 1 of the February 7, 1965 Agreement and that
the parties fully intended that this Article should continue to
be interpreted and applied in the manner as it has since its
inception. The Organizations presentation to PEB 229 clearly
sought no change to the language "subsequent general wage
increases" nor, in addressing the organizations presentation,
did the members of PEB 229 indicate that they considered this
13
SeA Wo. 19-7
P1,
w
D
1'~
phrase to be a matter of dispute before them. In fact, the
testimony, both written and oral, leads to the opposite
conclusion.
The Board further notes that the phrase "subsequent general
wage increases" is not unique to the February 7, 1965 Agreement,
but in fact appears in numerous protective agreements and in
protective conditions imposed by the ICC/STB, including the
Amtrak C-1 Conditions, New York Dock, Oregon Short Line, N&W,
Burlington, and Mendocino Coast Protective Conditions. The
phrase also continues to appear in the February 7, 1965 Agreement
as it applies to the other labor organizations who are signatory
to the agreement, including the Brotherhood of Railroad
Signalmen, who, like the BMWE, has similarly updated the February
7, 1965 Agreement in recent national agreements. The Board finds
that the phrase "subject to subsequent general wage increases" is
a term of art to labor relations practitioners in the railroad
industry and embodies the standard industry approach to
adjustment of protective rates. Thus, it is reasonable to assume
that PEB 229 would have specifically addressed such a significant
departure from established precedent if it had truly intended to
recommend such a significant change to that standard. The utter
silence of the record before us strongly supports the inference
that it had no such intention. Therefore, it is impossible for
this Board to conclude that PEB 229 purposely recommended a
material alteration to the manner in which protected rates of pay
were to be subsequently adjusted, or that the parties knowingly
14
4,6A SID - V4
agreed to such a change when the PEB's recommended language
amending the February 7, 1965 Agreement was incorporated in toto
in the 1996 national agreement. As indicated previously, this
Board is not empowered by the parties to add contractual terms or
to change existing agreements; its authority being limited to
interpreting and applying the February 7, 1965 Agreement, as
amended. It is therefore the conclusion of this Board that the
phrase "subsequent wage increases" should be interpreted and
applied as having the same meaning as the phrase "subsequent
general wage increases" based upon the absence of any evidence to
demonstrate that the parties knowingly agreed to eliminate the
word "general" and thereby materially alter the manner in which
protected rates of pay would be adjusted.
Having so concluded, the Board must now determine whether
the wage adjustment emanating from the May 23, 1999 Strongsville
Agreement, which resulted in Claimant M. J. Cronin's hourly rate
being changed from the hourly rate of compensation of Yard
Foreman (old rate) to the hourly rate of compensation for the
position of Track Foreman (new rate), resulted in an increase to
Claimant Cronin's protected rate of compensation pursuant to the
provisions of Article IV, Section 1, of the February 7, 1965
Agreement.
The adjustment to Claimant Cronin's rate of pay resulted
from a unique rate rationalization agreement which consolidated
approximately 400 rates of pay into 16 rates of pay. The only
question before the Board is whether the adjustment to Claimant
15
SEA, ND-
l0$'7 /~xu~
r4
Cronin's rate of pay was a subsequent general wage increase for
purposes of Article IV, Section 1. The Board concludes, based on
the relevant facts and circumstances, that it was. Accordingly,
Mr. Cronin's protected rate of compensation under the provisions
of Article IV, Section 1, should be that of Track Foreman (new
rate), subject to subsequent general wage increases. This Board
expresses no views on the appropriate disposition of claims which
may be filed or which may have been timely and properly filed by
other individuals, concerning wage adjustments, related to the
Strongsville Agreement.
III. Conclusion
Under the special circumstances here involved, the Award
shall indicate that the Claim is sustained and Claimant Cronin
shall be made whole in all respects consistent with this
determination by recognizing that his protected rate of pay under
Article IV, Section 1, of the February 7, 1965, Agreement should
be considered the rate of pay of the position of Track Foreman.
Accordingly, the Undersigned, duly designated as the
referenced Board and having heard the proofs and allegations of
the above-named parties, make the following AWARD:
The Carrier, CSX Transportation, Inc., did
violate Article IV, Section 1 of the
Agreement in Mediation Case No. A-7128, dated
February 7, 1965, as amended by Article XII
of the Agreement in Mediation Case No. A
12718, dated September 26, 1996 by
calculating Claimant M. J. Cronin's February
7, 1965 Job Stabilization protective rate to
be $17.82 per hour (as of December 1, 2000)
instead of $18.63 per hour. The Claimant
shall be made whole in accordance with the
16
46
A lib
. b97 ~-l.~ o l y
accompanying opinion.
Robert L. Dod4las
Chairman and Neutral Member
o x,
Donald F. Griffin A. K. Gradia
Ur Carrier Member
Concurrln Dissenting Concurring/Dissenting
R. ehrli ijo n F. Hennecke
U ' er rrier member
Concurring Dissenting Concurring/Dissenting
DATED: January 29, 2004
STATE of New York)ss:
COUNTY of Nassau
I, Robert L. Douglas, do hereby affirm upon my oath as
Arbitrator that I am the individual described in and who executed
this instrument, which is my opinion and Award.
17