SPECIAL BOARD OF ADJUSTMENT NO. 605
PARTIES ) Brotherhood of Railroad Signalmen
TO THE )
DISPUTE ) and
Union Pacific Railroad Company
QUESTION AT ISSUE: .
Is Carrier's use of non-covered employees to perform work covered by the
Signalmen's Agreement considered a "transfer of work" as that term is used in Article
III, Section 1 of the February 7, 1965 Agreement?
OPINION OF
THE BOARD: On May 2, 1991, the Carrier tendered the Organization with written notice of
its intent to transfer work consisting of the wiring of six signal equipment
Houses from the Signal Shop at Pocatello, Idaho. to the Sedalia, Missouri Signal Shop. The Carrier
sited Article III. Section 2 of the February 7. 1965 Job Stabilization Agreement in its notice. The
Carrier explained that Signal employees at the Pocatello Shop were burdened with an excess
-.workload while the Sedalia Shop had unused capacity. Thus, the Carrier sought to equalize the
-.workload between the two shops so that it could more quickly accomplish the wiring work.
The Pocatello Shop is located on the original Union Pacific while the Sedalia Shop is located
:n the former Missouri Pacific Railroad territory. The Organization represents employees at both
:hops although employees on the Missouri Pacific are covered by a schedule agreement separate
mom Signal employees on the Union Pacific.
[Note to JBL: Harlier I have to add that the wiring work was performed by Sedalia -Shop
mployees from August 5 through August 8,
1
991.1
AWARD NO. 503-B
CASE N0. SG-45-W
Contending that the Carrier violated the applicable scope rule. the Organization initiated and
progressed a claim to the National Railroad .-adjustment Board (NRAB) Third Division.' .fit the
NRAB, the Carrier argued that this Disputes Committee had exclusive jurisdiction to adjudicate the
claim. In
NRAB Third Division Award No. 30-2 2 (Wesman),
the NRAB deferred any ruling on the
claim until this Disputes Committee could first ascertain whether it had primary and exclusive
jurisdiction over the dispute. In
Award No. 307 22,
the Board wrote:
The instant claim involves invocation by Carrier of the February 7,
1965 Mediation Agreement between the Parties. It is not a case of
first impression. Similar claims were presented in Awards 52 and 56
A, B, & C. on Public Law Board No. 4716, involving these same
parties. Nothing in this case distinguishes it from the prior cases. In
Award 52 the Board held:
While prompt resolution of disputes before Public
Law Boards is the ultimate goal, such resolution may
not be made at the expense of adherence to proper
procedural and jurisdictional considerations.
Accordingly, the Board finds that, until the ancillary
dispute over the Parties' interpretation of the February
7, 1965 Agreement is resolved, we must defer to the
procedures described in `Article VII - Disputes
Committee' of that Agreement. Should this matter
return to the Board once the Disputes Committee's
decision has been rendered, the Board will . . .
.proceed with a determination of the merits of the case
under the current Agreement between the Parties.
This Board has exclusive jurisdiction to adjudicate the dispute if the Carrier's transfer of the
-airing work constituted or was associated .-Oth an operational, technological or organizational
~:hange as specified in Article III, Section 1 of the February 7, 1965 Agreement. The first sentence
'
It is difficult to conceptualize the existence of any scope rule violation when the work in dispute was performed
by covered employees represented by the Organization.
AWARD NO. 503-B
CASE NO. SG-45-W
of Article III, Section 1 clearly ties the Carrier's right to transfer work to a technological, operational
or organizational change. Sections 1 and 2 of .Article III of the February 7, 1965 Agreement read:
Section I
The organizations recognize the right of the carriers to make
technological, operational and organizational changes, and in
consideration of the protective benefits provided by this Agreement
the carrier shall have the right to transfer work and/or transfer
employees throughout the system which do not require the crossing
of craft lines. The organizations signatory hereto shall enter into such
implementing agreements with the carrier as may be necessary to
provide for the transfer and use of employees and the allocation or
rearrangement of forces made necessary by the contemplated change.
One
of
the purposes of such implementing agreements shall be to
provide a force adequate to meet the carrier's requirements.
Section I
Except as provided in Section 3 hereof, the carrier shall give at least
60 days' (90 days in cases that will require a change of an employee's
residence) written notice to the organization involved of any intended
change or changes referred to in Section 1 of this Article whenever
such intended change or changes are of such a nature as to require an
implementing agreement as provided in said Section 1. Such notice
shall contain a full and adequate statment [sic] of the proposed
change or changes, including an estimate of the number of employees
that will be affected by the intended change or changes. Any change
covered by such notice which is not made within a reasonable time
followine the service of the notice, when all of the relevant
circumstances are considered, shall not be made by the carrier except
after again complying with the requirements of this Section 2.
Upon careful consideration, this Board finds that the transfer of wiring work involving just
:ix signal equipment houses from one signal shop to another signal shop on the same merged system
goes not constitute an operational or organizational change within the meaning of Article III, Section
of the February 7, 1965 Agreement. Instead. the subject matter of this case is more properly
AWARD NO. 503-B
CASE NO. SG-.l·5-W
characterized as a possible scope rule violation governed by the provisions in the applicable working
agreements.
While the parties to the February 7, 1965 Agreement did not precisely define the meaning
of an operational change (or for that matter, a technological or organizational change), a change in
operation inherently connotes an alteration more integral to how work is performed than the transfer
of a modicum of work from one signal shop to another. In this case, the manner of performing the
wiring work did not change and there was no change in how either shop operated. Moreover. the
record indicates that the Carrier simple reassigned certain work based upon the unused productive
capacity at the Sedalia Shop. All of these circumstances strongly suggest that the Carrier's activity
was not predicated on an operational or an organizational change.
This Board stresses that it need not definitively define what activity constitutes technological,
organizational or operational changes. We narrowly hold that evidence or any such change is not
contained within this particular record.
Therefore, this Board lacks jurisdiction to adjudicate the claim.
AWARD
The Answer to the Question at Issue is No.
Dated: September 24, 1996
John B. LaRocco
Neutral Member
-1-
AWARD NO. 503-B
CASE NO. SG-d5-W
SPECIAL BOARD OF ADJUSTMENT NO. 605
PARTIES ) Brotherhood of Railroad Signalmen
TO THE )
DISPUTE ) and
Union Pacific Railroad Company
QUESTION AT ISSUE:
Is Carrier's use of non-covered employees to perform work covered by the
Signalmen's Agreement considered a "transfer of work" as that term is used in Article
III, Section 1 of the February 7, 1965 Agreement?
OPINION OF
THE BOARD: On May 2, 1991, the Carrier tendered the Organization with written notice of
its intent to transfer work consisting of the wiring of six signal equipment
Houses from the Signal Shop at Pocatello, Idaho. to the Sedalia, Missouri Signal Shop. The Carrier
cited Article III. Section ? of the February 7, 1965 Job Stabilization Agreement in its notice. The
Carrier explained that Signal employees at the Pocatello Shop were burdened with an excess
Workload while the Sedalia Shop had unused capacity. Thus, the Carrier sought to equalize the
workload between the two shops so that it could more quickly accomplish the wiring work.
The Pocatello Shop is located on the original Union Pacific while the Sedalia Shop is located
in the former Missouri Pacific Railroad territory. The Organization represents employees at both
:hops although employees on the Missouri Pacific are covered by a schedule agreement separate
mom Signal employees on the Union Pacific.
[Note to JBL: Earlier I have to add that the wiring work was performed by Sedalia Shop
mployees from August 5 through August 8, : 991.]
Contending that the Carrier violated the applicable scope rule. the Organization initiated and
progressed a claim to the National Railroad Adjustment Board (NRAB) Third Division.' At the
NRAB, the Carrier argued that this Disputes Committee had exclusive jurisdiction to adjudicate the
claim. In
NRAB Third Division Award No. 30-2 2 (Wesman),
the NRAB deferred any ruling on the
claim until this Disputes Committee could first ascertain whether it had primary and exclusive
jurisdiction over the dispute. In
Award No. 30:71,
the Board wrote:
The instant claim involves invocation by Carrier of the February 7,
1965 Mediation Agreement between the Parties. It is not a case of
first impression. Similar claims were presented in Awards 52 and 56
A, B, & C, on Public Law Board No. 4716, involving these same
parties. Nothing in this case distinguishes it from the prior cases. In
Award 52 the Board held:
While prompt resolution of disputes before Public
Law Boards is the ultimate goal, such resolution may
not be made at the expense of adherence to proper
procedural and jurisdictional considerations.
Accordingly, the Board finds that, until the ancillary
dispute over the Parties' interpretation of the February
7, 1965 Agreement is resolved, we must defer to the
procedures described in 'Article VII - Disputes
Committee' of that Agreement. Should this matter
return to the Board once the Disputes Committee's
decision has been rendered, the Board will . . .
.proceed with a determination of the merits of the case
under the current Agreement between the Parties.
This Board has exclusive jurisdiction to adjudicate the dispute if the Carrier's transfer of the
%iiring work constituted or was associated with an operational, technological or organizational
change as specified in Article III, Section 1 of the February 7, 1965 Agreement. The first sentence
'
it is ditrcult to conceptualize the existence of any scope rule violation when the work in dispute was performed
by covered employees represented by the Organization.
AWARD NO. 503-B
CASE NO. SG-.l5-W
of Article III, Section 1 clearly ties the Carrier's right to transfer work to a technological, operational
or organizational change. Sections I and 2 of .-article III of the February 7, 1965 Agreement read:
Section 1
The organizations recognize the right of the carriers to make
technological, operational and organizational changes, and in
consideration of the protective benefits provided by this Agreement
the carrier shall have the right to transfer work and/or transfer
employees throughout the system which do not require the crossing
of craft lines. The organizations signatory hereto shall enter into such
implementing agreements with the carrier as may be necessary to
provide for the transfer and use of employees and the allocation or
rearraneement of forces made necessary by the contemplated change.
One
of
the purposes of such implementing agreements shall be to
provide a force adequate to meet the carrier's requirements.
Section 1
Except as provided in Section 3 hereof, the carrier shall give at least
60 days' (90 days in cases that will require a change of an employee's
residence) written notice to the ore_anization involved of any intended
change or changes referred to in Section 1 of this Article whenever
such intended change or changes are of such a nature as to require an
implementing agreement as provided in said Section 1. Such notice
shall contain a full and adequate statment [sic] of the proposed
change or changes, including an estimate of the number of employees
that will be affected by the intended change or changes. Any change
covered by such notice which is not made within a reasonable time
following' the service of the notice, when all of the relevant
circumstances are considered, shall not be made by the carrier except
after again complying with the requirements of this Section 2.
Upon careful consideration, this Board finds that the transfer of wiring work involving just
six signal equipment houses from one signal shop to another signal shop on the same merged system
goes not constitute an operational or organizarional change within the m caning of Article III, Section
of the February 7, 1965 Agreement. Instead- the subject matter of this case is more properly
AWARD NO. 503-B
CASE NO. SG-45-W
characterized as a possible scope rule violation governed by the provisions in the applicable working
agreements.
While the parties to the February 7, 1965 Agreement did not precisely define the meaning
of an operational change (or for that matter, a technological or organizational change), a change in
operation inherently connotes an alteration more integral to how work is performed than the transfer
of a modicum of work from one signal shop to another. In this case, the manner of performing the
wiring work did not change and there was no change in how either shop operated. Moreover. the
record indicates that the Carrier simple reassigned certain work based upon the unused productive
capacity at the Sedalia Shop. All of these circumstances strongly suggest that the Carrier's activity
was not predicated on an operational or an organizational change.
This Board stresses that it need not definitively define what activity constitutes technological,
organizational or operational changes. We narrowly hold that evidence or any such change is not
contained within this particular record.
Therefore, this Board lacks jurisdiction to adjudicate the claim.
AWARD
The Answer to the Question at Issue is No.
Dated: September 24, 1996
John B.LaRocco
Neutral Member
-;-