(Brotherhood of Maintenance of Way Employes PARTIES TO THE DISPUTE: (and ( (Union Pacific Railroad Company

STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:








Page 2 PLB 7101
Case No. 12

FINDINGS:

The Board, upon consideration of the entire record and all of the evidence, rinds that the parties are Carrier and Employee within the meaning of the Railway Labor Act, as amended; that this Board is duly constituted by Agreement; this Board has jurisdiction over the dispute involved herein; and that the parties were given due notice of the Hearing held.

Claimant J. P. Coolican has established and holds seniority in the Maintenance of Way and Structures Department in the Track Subdepartment on Seniority District T-2 as a foreman. Claimants M. C. Kath, D. L. Bohn and R. L. Buol have established and hold seniority in the Maintenance of Way and Structures Department in the Track Subdepartment on Seniority District T-2 as machine operators (M. O. Common). Claimants were assigned and working their respective positions on the dates involved in this dispute.

Beginning on September 7, 2004 and continuing, the Carrier allegedly assigned Peterson Contractors, Inc. (PCI) to perform alleged basic fundamental Maintenance of Way and Structures Department work in the yard at Mason City, Iowa on the Fairmont Subdivision near Mile Post (1.6. Specifically, the work entailed fencing, grading, sub-ballast placement and other incidental work in connection with the construction of additional yard tracks. The Contractor assigned one Foreman and three Machine Operators to this project, allegedly working 12 hours per day Monday through Thursday, and 8 hours on Friday. The employees were using a Track Hoe, 1-2 dozers and 1-2 trucks as needed. The operators used various pieces of equipment.

The Organization contends that the Agreement was violated when the Carrier assigned PCI the work of fencing, grading, sub-ballast placement and other incidental work in connection with the construction of additional yard tracks at Mason City, Iowa on the Fairmont Subdivision near Mile Post 0.6. The Organization claims that it was improper for the Carrier to contract out the abovementioned work, which is work that is properly reserved to the Organization.

According to the Organization, the Carrier had customarily assigned work of this nature to the Carrier's Maintenance of Way Employees. The Organization further claims that the work in question is consistent with the Scope Rule. According to the Organization, the Carrier's Maintenance of Way Employees were fully qualified and capable of performing the designated work. The work performed by PCI falls within the jurisdiction of the Organization and therefore Claimants should have performed said work. The Organization argues that because Claimants were denied the opportunity to perform the relevant work, Claimants should be compensated for the lost work opportunities.
Page 3 PLB 7101
Case No. 12

Conversely, the Carrier takes the position that the Organization cannot meet its burden of proof in this matter. The Carrier contends that the work contracted out was that of fencing, grading, sub-ballast placement and other incidental work in connection with the construction of additional yard tracks, which the Carrier claims does not belong to the Carrier's BM,WE represented Employees under either the express language of the Scope Rule or any binding past practice. In addition, the Carrier argues that the Organization incorrectly asserted the instant Claim under the CNW BMWE Agreement whereas it should have been asserted under the UP BMWE Agreement. Because it was improperly asserted, the Carrier claims that the instant Claim should be voided.

We first note that at the Arbitration Hearing, the parties stipulated that the Notice issue was not in question. Therefore, we find that we need not reach that issue.

Next, we reach the question of whether the work in question has been traditionally and customarily performed by the Organization. In Special Board of Adjustment No. 1016, Award 150, the Board framed the scope issue as follows:



In the instant case, we have carefully reviewed all evidence regarding the question of whether the Organization has proven that the work involved belongs to the Organization. First, we note that the work of fencing, grading, sub-ballast placement and other incidental work in connection with the construction of additional yard tracks is not specifically identifed in the Scope Rule.

We next turn to whether there is sufficient evidence for the Organization to have proven that it has customarily, traditionally and historically performed the disputed work. In the instant case, while the Organization has presented some evidence to show that the work in question belongs to the Organization, that evidence is insufficient for the Organization to meet its burden of proof. See Public Law Board No. 6537 above. See Also Third Division Award 37365 (Goldstein),
Page 4 PLB 7101
Case No. 12

Public Law Board No. 4402, Award No. 20, Case No. 20, Award No. 28, Case No. 28; Public Law Board 6537, Award No. 1.

Based on the evidence in this matter as well as the above-cited precedent, we cannot find that the work of fencing, grading, sub-ballast placement and other incidental work in connection with the construction of additional yard tracks is definitively encompassed within the plain language of the Scope Rule or that the Organization has been able to prove that this work has historically and traditionally been performed by members of the Organization.

Thus, having determined that the Notice was proper and that the work was not within.the scope of the Organization, we find that the Organization has not met its burden of proof and the Claim is therefore denied.


Page 5 PLB7101
Case No. 12







t OUMtiWr!/Arbltf110f-WdNM. j .reuV..rwu~cna-y1
d- :o1aos.u1me-a arar

Steven M. Bierig
Chairperson and Neutral Member

Doming Ring Roy binson
Carrier Member Organ' anon Member

Dated at Chicago, Illinois this 14 t" day of June ZQ10.