BEFO
RE PUBLIC LAW BOARD NO. 7386
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
DIVISION - HIT RAIL CONFERENCE
and
SOUTH KANSAS & OKLAHOMA RAILROAD
Case No.
I
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
1. The Carrier violated Article 3, Sections A, B, E and F, Article 11 and Article 13,
Section A and D of the Agreement on July 9, 10 and 11, 2009 when it released
Track Foreman J. Pierce, Boom Truck/Backhoe Operator B. Peck and Trackmen
M. Hempen and L. Thomison from duty and assigned outside forces (Lonestar
Railroad Contracting Services) to perform routine track maintenance work with
Carrier owned equipment (System File SK-4000-1).
2. As a consequence of the violation referred to in Part 1 above, Track Foreman J.
Pierce, Boom Truck/Backhoe Operator B. Peck and Trackmen M. Hempen and L.
Thomison shall each be compensated for a total of twenty-four (24) hours at their
respective time and one-half rated of pay."
The Organization filed a claim on the Claimants' behalf, alleging that the Carrier
violated the parties' Agreement when it assigned outside forces to perform routine track
maintenance work, using Carrier equipment, instead of assigning this work to the
Claimants. The Carrier denied the claim.
The Organization contends that the instant claim should be sustained in its entirety
because there is no dispute that the work in question is contractually reserved to Carrier
Maintenance of Way forces and cannot be contracted out unless the express exception
within Article 3F applies, because that exception under Article 3F did not apply to the
situation at issue despite the Carrier's arbitrary and improper "determination" that the
1
PLB NO. 73$6
' . AWARD l
Claimants were "unavailable" to continue performing the subject work during overtime
hours in an effort to circumvent the Agreement, because the Carrier's contentions
regarding a "full work week" and a "full schedule" are entirely disingenuous and without
merit, because the Claimants were available and willing to perform the subject work
beyond their standard forty-hour work week, because the Carrier's defenses are entirely
without merit, and because the requested remedy is warranted. The Carrier contends that
the instant claim should be denied in its entirety because the Claimants were unavailable
to perform the subject work in that they were assigned to and working full schedules on
the dates in questions, because the Agreement does not provide that employees will work
overtime in lieu of contractors being on the property or that the Carrier is prohibited from
taking the action that it took in assigning the subject work to the contractor during the
Claimants' off time, because there was no requirement that the Carrier authorize
overtime, and because the Organization failed to meet its burden of proof.
The parties being unable to resolve their dispute, this matter came before this
Board.
This Board has reviewed the record in this case, and we find that the Organization
has met its burden of proof that the Carrier violated the Agreement when it failed to allow
the Maintenance of Way Team Members the opportunity to continue performing the
work that they had been performing repairing the damage from the train derailment on
July 9, 2009. The Organization has correctly pointed out that the Carrier violated Article
3 when it subcontracted Organization team work in violation of the Agreement.
Article 3, Section E, states the following:
2
PLB NO. 7386
AWARD 1
MW Team Members included within the scope of this Agreement
perform work in connection with the construction, maintenance,
repair, and dismantling of track, road beds, structure facilities,
and appurtenances related thereto, located on the right of way and/or
used in the operation of the Carrier in the performance of the
common Carrier service, and other duties as assigned.
Consequently, the work at issue was clearly Maintenance of Way work. As a
matter of fact, the Claimants performed the work until approximately 2 p.m. on July 9,
2009, using Carrier tools and equipment to perform the work, when the Assistant
Roadmaster told them they would no longer be performing that work and sent them home
for the balance of the week.
Article 3, Paragraph F, states the following:
The Carrier may subcontract the performance of maintenance,
repair, and construction work or services if beyond the skill
and capabilities of available MW Team Members, or if
necessary personnel, machinery, equipment, tools, or
material are not available. For purposes of this Article,
personnel are not available when all MW Team Members are
assigned and working a full schedule. No MW Team Member's
position will be cut off or duties performed by someone not
subject to this Agreement, except as otherwise provided.
The key language here is that the personnel were available because MW Team
Members were not assigned and working a full schedule. The Carrier argues that they
had worked their full schedule because a full schedule is forty hours. That may be true,
and that need not be decided here. The problem is they have to be assigned and working
a full schedule. In this case, the Claimants were not assigned because they had been sent
home. Consequently, even if they had worked a full schedule, they were not "assigned."
The contract language requires that they be
both assigned and working a full schedule to
3
PLB NO. 7386
. AWARD l
be considered personnel that are not available. Since the personnel at issue did not meet
the requirement of being "assigned," the Carrier was prohibited from subcontracting the
work on this particular job when the Claimants were available to perform that work.
The Organization has met its burden of proof that the Carrier violated the
Agreement when it took the work away from the MW Team Members and subcontracted
it to an outside firm. Therefore, this claim must be sustained.
AWARD:
The claim is sustained.
TER R. MEY S
utral er
CA R M BER O GAN ZATION MEMBER
DATED:
2Z,~i
041,
DATED:
4