PUBLIC
LAW
BOARD No. 1210 -AWARD No. 11
PARTIES TO DISPUTE: Baltimore and Ohio Railroad Company
and
' Brotherhood of Maintenance of Way Employees
STATEMENT OF
CLAIM:
"Claim for two hours each for the Traclomen listed below
and six hours each for those other than Trackmen listed
below account the Force not working on April 21, 1972
because of inclement weather."
(Those employees listed included
7
Trackmen, 1 Assistant
Foreman,
7
Machine Operators)
OPINION OF BOARD: On the date in question the fifteen employees referred to
in the claim reported to their work location at
7:00
AM.
It was raining. At 9:00 AM the Assistant Division Engineer
arrived at the job site and found that none of the men were
working. The record shows that the Machine Operators had
f.
refused to work due to weather and therefore the Trackmen
could not work because "Without the machines this unit is
unable to perform the installation of ties a's scheduled."
The inference is clear that if the Machine Operators had _
been willing to work the whole unit would have been working,
weather notwithstanding. The record also shows that the
Assistant Division Engineer requested that the machines be
started and the Operators refused to do so. There is no
dispute between the parties as to the above set of circum
stances.
When advised that the Operators refused to start their
_- PL
Board Nor, ~~0 (2) , . AWARD No. - 11
machines the Assistant Division Engineer told the men to go
to work or he would allow them only two (2) hours' pay for
· the day.
Petitioner, in support of the claim,, has cited Rules 16(a),
16(b) and 17(a) of the Agreement.
These Rules state, in pertinent part,. as follows:
16 (a) - "Regularly established daily working hours
will not be reduced below eight
(8)
for five
(5)
days per week to avoid making force
' reductions, . . ."
· 16 (b) - "Trackmen and extra gang men required to
report at usual. starting time and place
for the day's work will be allowed a minimum
of four
(4)
hours when conditions prevent
work being performed.
17 (a) - "There is hereby established for all employees
covered by this agreement, subject to the
exceptions contained hereafter in this rule and
Rule 60 (b-2). a work week of 1?0 hours, consisting
of five days of eight hours each, . . ."
Petitioner alleges that., under the circumstances in the
. instant case, the Carrier official unilaterally reduced the z
Claimants' work day on the day in question when he told them
to either go to work or they would be paid for only the two
hours they had been at the work site,
which was
in violation
of Rule 16(a). We do not agree. The fact of the matter is -
that the Operators refused to go to work, were told by proper
authority to go to work and still refused, and were therefore
told to leave the property. Their,opportunity to work a
normal eight
(8)
hour day, which they were requested to do
· when they were told to go to work., was restricted by their
own inaction - it was the refusal to work that put in motion
.gL Board No. 1210
6
(3)
. AWARD No. 11
the events that followed. Obviously, an employee who
refuses to go to work when directed to do so by. proper authority exposes himself to possible penalty - in this instance
"no work, no pay.",
However, insofar as the Trackmen are concerned, we do agree
that Rule 16(b) entitles them to a payment of four (4)
hours minimum when conditions prevent work being performed
after they have.reported for work at the usual starting time
as alleged `by Petitioner. The condition that prevented them
' from working, in this case, was not the inclement weather
but the refusal of the Operators to work. As the Carrier
stated, "Without the machines this unit is unable to perform
the installation of ties as scheduled."
We do not find that Rule 17 (a) has any application to the
factual situation presented to us. This Rule, in essence,
merely defines that the 40-hour week will consist of five
eight-hour days instead of some other combination of days
and hours within a week., the total of which would equal
forty. ,
Petitioner., in his submission to this Board, made much of
the conditions of weather on the claim date and inferred, at
least., that employees had the option of determining whether
the weather on a particular day was suitable for work. We
will dispose of this portion of the. argument by drawing
attention to Award No. 18012 which stated, in part,
' "It is a managerial prerogative to determine when
work is to be performed, as exemplified in many of
our awards."
The subject requires no further discussion.
.--rL'Board ITO. 1210
~,
(4)
., AWARD P1o.'.11
AWARD: Claim sustained insofar as the Trackmen are concerned, i.e.,
· two (2).additional hours' pay at their straight time hourly
1
rate
Remainder of the claim is Denied.
ORCER: The Carrier shall comply with this Award within thirty (30)
days of the date of this Award.
C. Robert Roacriey., Neutral
A. J °'unningham, .ogee i·:amber L. W. Burks, Carrier
:ember
Baltimore, Maryland
March 11,
1974 -