~ e-
PUBLIC LAW BOARD N0. 1760
Award No. 135
Docket No. 135
Carrier File MW-DECR-91-02-LM-03
Parties Brotherhood of Maintenance of Way Employes
to and
Dispute Norfolk and Western Railroad Company
(former Wabash)
Statement
of Claim: Claim on behalf of R. V. Parker for pay for time lost,
reinstatement of operator rights, and the difference in pay
for all time worked at a lower rate as a result of his
dismissal as a Group #1 Prior Right Machine Operator and 30
day suspension resulting from the locomotive crane he was
operating striking an overhead highway bridge on January 8,
1991.
Findings: The Board has jurisdiction by reason of the parties
Agreement establishing this Board for that purpose.
Crane Operator, R. V. Parker, on January 8, 1991, was
operating a Carrier-owned locomotive crane over the rail
from the east end of the South Liberty siding toward Hardin,
a distance of approximately 33 miles. On this route, the
crane was required to pass under an overhead state highway
bridge at Milepost 325.43 near Henrietta, MO. As the crane
passed under the bridge at approximately 1:30 PM, the boom
of the crane hit the structure, bending several components
therein. The Claimant instructed another employee to
contact the State Highway Department and advise them of the
incident. He continued to move the crane onto Hardin where
about 3:00 PM, he contacted a Carrier officer and reported
the incident.
An investigation was held in connection therewith and
as a result thereof, Carrier concluded the Claimant to be
guilty of the charge placed against him. He was demoted or
dismissed as a Group #1 prior right Machine Operator and was
suspended from service for 30 days.
Claimant has been employed with Carrier for 26 years.
He has been a Crane Operator for 9 years.
The Carrier concluded that the Claimant had violated
Rule 1559. which requires that:
"Operators and/or pilots or boom-type cranes must be sure
that in the boom where there are overhead bridges or other
obstructions before attempting to pass beneath
obstructions."
0Ld /760
-2- Award No. 135
Also Rule N which, in part, reads:
0
"Every accident resulting in... damage to property must be
reported to the proper authority by the quickest
communication available, and a written report on the
prescribed form must be submitted promptly."
The Claimant was accorded the due process to which
entitled under Rule 30.
There was sufficient evidence adduced including
Claimant's statements and admissions against interest, to
support Carrier's conclusion of culpability as to the
violation of the rules cited above. Claimant's statement at
T-3, and confirmed at T-18, in part reads:
"Operator R. V. Parker stated reason for contact with crane
and overhead bridge was account of incorrect estimation 'of
the height of the boom and the height of the bridge
structure."
The Claimant has been employed for 26 years. He has
been a crane Operator for 9 years. The length of time that
the Claimant has been disqualified undoubtedly has, by now,
served its purpose. The Board herewith restores his Crane
Operator's seniority. The claim is otherwise denied.
Award: Claim disposed of as per findings.
Order: Carrier is directed to make this Award effective within
thirty (30) days of date of issuance shown below.
4
S7. . ammonfJ r., Employee ember L. . . Miller, Jr -,e~er Member
an art, airman ,-
and Neutral Member
Issued
January 21, 1993.