PUBLIC LAW BOARD N0. 1760
Award No. 58
Case No. 58
Docket No. MW-DEC-80-37
Parties Brotherhood of Maintenance of Way Employees
to and
Dispute Norfolk and Western Railway Company
(Former Wabash)
Statement
of Claim: 1. Carrier violated the effective agreement
when Foreman W. A. Craft was unjustly assessed
ten (10) da s deferred suspension that activated a
fifteen (15~ day deferred suspension as of
December 14, 1982, which case is also before this
Board as Case No. 57.
2. Claimant Craft shall not be paid in the amount
that he lost due to the assessed 15 days deferred
suspension which was activated starting July 25,
1983 and extending through August 3, 1983 and that
this investigation be stricken from his record.
Findings: The Board, after hearing upon the whole record and all evidence,
finds that the parties herein are Carrier and Employee within the meaning
of the Railway Labor Act, as amended, that this Board is duly constituted
by Agreement dated February 2, 1976, that it has jurisdiction of the
parties and the subject matter, and that the parties were given due notice
of the hearing held.
Claimant was notified, under date of June 20, 1983, to attend a
formal investigation on July 14, 1983 on the charge:
" ..to determine your responsibility
in connection with your being in violation
of Norfolk and Western Railway Company
Standard Plan 333 concerning temporary
slow order sign showing the yellow approach
board being attached to a standard galvanized
post, in connection with your attaching a
yellow caution board to signal located at
mile post 341.3, west of Tolono on June 15,
1983 in lieu of attaching it to the post as
required by Standard Plan 333."
p~c3 /~1~a
-2- Award No. 58
Claimant, on June 15, 1983, was assigned as track patroller at
Bement, Illinois. He was instructed to put up temporary slow order
boards west of Tolono, Illinois account the track gang would be working
on the track, raising the switch at west end of Tolono. Claimant
placed one of the temporary slow order boards on the signal located
at MP 341.3 instead of on the prescribed galvanized post.
There is no question of guilt in this case. Claimant so admitted
(Q/A 99 - P. 9). The question raised concerns the determination of the
degree of discipline assessed and its ramification. The failure here
arose because Claimant improperly hung the yellow board (slow order
board) on the signal located at MP 341.3 instead of on prescribed
galvanized post. He failed to alert the dispatcher. After quitting
time Claimant did find a pole and hung the yellow signal properly.
As a result of the investigation Carrier concluded Claimant to be
guilty as charged. He was given ten (10) days deferred suspension as
discipline therefor. However, said ten days discipline activated the
fifteen (15) days deferred suspension previously assessed to Claimant,
on December 14, 1982. Thus, under the discipline system in effect Claimant
was therefore required to serve the pending fifteen (15) days discipline.
It is obvious that Claimant, in any event, would have been disciplined.
Hence, no matter what that discipline was the discipline system mandated
that it would serve to activate the previous pending discipline. In the
circumstances, the discipline here is found to be reasonable. This claim
will be denied.
Award: Claim denied.
t
c
M.~. e~e~e~- S. C. -Lyons, Carries ber
<Wa~y
5A, ~
Issued December 14, 1984.