PARTIES TO THE DISPUTE:
PUBLIC LAW BOA N0. 1844
Brotherhood of Maintenance of Way Employees
and
Chicago and North
Western
Transporation Company
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1)
OPINION OF BOARD:
The Agreement was violated
when
outside forces were used to pick up
and load rail and track scrap on the Illinois Division (System File
81-1-219).
(2) The Agreement was further violated when the Carrier did not give the.
General Chairman
prior notification of its
plans
to assign said work
to outside forces.
Because of the aforesaid violations, Messrs. D. E. Harriss and
K. L. Bushman each be allowed pay at their respective rates for an
equal proportionate share of the total number of hours expended by
outside forces beginning sixty (60) days retroactive from January 28,
1975."
In this case the Organization alleges a violation of the Scope Rule, Rule 1
of the Agreement. The background facts are not disputed. During the claim
period Carrier was engaged in main line rail renewal, replacing old rail with
new and heavier continuous welded (ribbon) rail. Several work stages of dismantling, removal of old material and construction of tracks were involved in
the project. Specifically the old rail was taken out including tie plates,
angle bars,
and turnouts; the old
rail and
materials were picked up
and transported
to a rail welding plant; and new ribbon rail together with tie plates, angle
bars, turnouts, etc. were laid. M of W forces were used to perform all of this
work but Carrier contracted part of the pickup and loading of the released rail
and track scrap work to outside forces. Specifically, Carrier contracted with
Stahl Construction Company for the use of two cranes and operators. This rented
equipment was used to pick up the old rail and related material and machine
operators supplied by the outside contractor ran the cranes in the performance
of this work. The record shows that no prior notice or consultation was provided
the General Chairman by the Carrier before entering into this disputed transaction,
Nor is it contested that both of the Claimants herein, D. E. Harriss and K. L.
Bushman, were working respectively as crane operator and foreman on the replacement~phase of the rail renewal project at all times when the contractor's
employees were operating the rental cranes on the rail removal phase of that
project.
We do not find persuasive the Carrier's 'contention that the contracting out
provisions of Rule 1 are inapplicable in this case. Carrier would have us find
that its rental of equipment together with outside employees to run such equipment does not constitute a letting of work to contractors to be performed by
contractor's forces. Such semantic distinctions however would permit parceling
out of work protected by the Scope Rule piecemeal by such rental agreement in a
fashion which would render Rule 1 meaningless. It is apparent to us that such
was not the intent of the parties in drafting that Agreement language and we
have no doubt that we deal here with a "contracting transaction" as that term is
used in Rule 1 (b), Paragraph 3.
k.
3
Apparently there is no real dispute that the work involved is work embraced
within the scope of the applicable Agreement as described in the first paragraph
of Section (b) of Rule 1. Therefore, even assuming arguendo that one or more of
the criteria for subcontracting established by Paragraph 2 of Section (b) was
applicable, it was incumbent upon Carrier to comply with the provisions of
Paragraph 3 before contracting out the scope covered work to outside forces.
We are guided in construing and interpreting the notice and consultation
provisions of Rule 1 (b) by antecedent Awards involving Article IV of the May 17,
1968 National Agreement upon which the instant contract language obviously is
based. Carrier herein failed to give any notice before contracting out the work
to Stahl Construction Company and beyond doubt it has violated Rule 1 by this
failure. We concur with the reasoning of some of the earlier Article IV awards
to the effect that failure to comply with the notice provisions makes irrelevant
Carrier's further contentions regarding inadequate or unavailable equipment to
handle the work. These are matters which the parties might have discussed under
the procedures provided in Paragraph 3 of Rule 1 (b), but they have no bearing
on whether the notice should have been given in the first place. See Awards
19399 and 19657.
The only remaining question is whether monetary damages should lie in
this case for the proven violation of Rule 1. This Referee has stated on prior
occasions in similar cases that he is most reluctant to treat a proven rule
violation with a mere reprimand. The notice and consultation requirements of
Rule I are not precatory but mandatory and Carrier officials disregard them
at their peril. But here, as in other cases, we do not write on a clean slate.
A substantial body of precedent has developed regarding these Article IV type
cases which we may not lightly disre ;ard nor find palpably erroneous. A
consistent principle flowing through all of those awards faith respect to damn ;es
,.<
is that monetary compensation is not awarded in the absence of a proven loss
of earnings or work opportunity by Claimants. See Awards 19305, 19399, 19657,
20071, and 20275. Claimants in this case have not demonstrated such loss since
the record shows that they were working and under pay at all times when the
outside forces operated the rental cranes. Based upon the foregoing precedents
we shall not award the monetary damages sought in the claim.
FINDINGS:
Public Law Board No. 1$44, upon the whole record and all of the evidence,
finds and holds as follows:
1. That the Carrier and Employee involved in this dispute are, respectively,
Carrier and Employee within the meaning of the Railway Labor Act;
2. that the Board has jurisdiction over the dispute involved herein;
and
3. that the Agreement was violated.
5
AWARD
Claim sustained to the extent indicated in
the Opinion.
Dana E. Eische , ,air
~-
0. M. Berge, Empl ee Member R. W. Schmiege, Caier Member