Award No. 15
Docket No. 31
BMWE File TOL-1613
Carrier File 2-MG-1552
Parties Brotherhood of Maintenance of Way Employees
to and
Dispute The Baltimore and Ohio Railroad Company
Statement Claim filed on behalf of Trackman Cardell Bowling and
of Vernus Bowling for one and one-half (1 1/2) hours' pay
Claim on account of only being allowed six and one-half (6 1/2)
hours' pay on January 16, 1976 when they were on duty
eight (8) hours on said date.
Findings The Board, after hearing upon the whole record and all
evidence, finds that the parties herein are Carrier and
Employee within the meaning of the Railway Labor Act, as
amended, that this Board is duly constituted by Agreement
dated October 27, 1976, that it has jurisdiction of the
parties-and the subject matter, and that the parties were
given due notice of the hearing held.
Claimant Trackman, on January 16, 1976, reported with their
truck to Syanid behind the Fisher Body Plant, their assigned
work location for that day, to work with other Maintenance
of Way Forces.
The Employees assert that Claimants and their Foreman re
. mained in their truck because of the heavy rain until
about 10:00 AM, when it let up after which Claimants












                    (c). When less then eight (8) hours of work for the convenience of employees only actual hours

' worked or held on duty will be paid for."

                  ' PL G

                                            ~85a


      Award No. 15 Page 3 The Employees assert that because the Welders had been paid eight hours and that Claimantswere only paid for six and one-half hours that they were discriminated against, that Claimants are entitled to eight hours pay under Rule 16, the same as was paid to the Welders.


      The record reflects that it was not denied that the Welder and the Welder Helper had already been working and had left another location in a separate truck to join Claimants and that said Welders were unable to perform any work until Claimant Trackmen, who were sitting in the truck and had refused to go out in the "light" rain,had gone

      / to work. Said Welders were, in effect, ready, willing and able to work. Therefore they were paid. Claimants, on the other hand, had in effect, refused to work for about one and,one-half hours.


      The facts herein appear similar, if not identical, to those in Case No. 11 of PLB No. 1210, on this property. There, a claim was made for two hours for the Trackmen involved, and six hours each for those Claimants other then Trackmen account not working because of inclement weather. There, Machine Operators refused to work due to the weather and consequently, the Trackmen could not

\ work because, as pointed out in Award 11, "without the
      machines this unit is unable to perform the installation

            ' /p L i3 1850


                                Award No. 15

                                Page 4

of ties as scheduled". It was also held therein that:

        "The inference is clear that if the Machine Operators had been willing to work the whole unit would have been working, weather notwithstanding. The record also shows that the Assistant Division Engineer requested that the machines be started and the Operators refused to do so."

The Board in its Award No. 11 sustained the claim of the
Trackmen but denied the claim of the Operators.

                    .r


This Board finds in the instant case that on the facts of this record Claimant Trackmen refused to work, after being so requested by their Foreman, and that the Welder and Welder Helper were totally dependent on the performance of their work after the Trackmen had commenced working. Thus, the only reason Claimants failed to receive eight (8) hours, compensation was the result of their voluntary refusal to commence work at the work site. Foreman Mullen's opinion that the conditions existing on January 16, 1976 did not prevent the necessary track work from being performed was not previously disputed. Hence, as Third Division Award No. 16746 (Friedman) held:

        " ...Claimants have not justified their refusal to perform the assigned work. Under the circumstances Carrier had no obligation to assign the men elsewhere. Their failure to work was the result of a voluntary choice and the loss of time which resulted therefrom requires no recompense under any rule in the Agreement."


                                    '

-r

        · PLO i85o


                                                Award No. 15

                                                Page 5


                  Consequently, the instant claim will be denied.


      Award Claim denied.


        re urpe ,- r., oy m er o s ey, tier em er

                      n


                                  L

                              an art, Chairman and Neutral Member


                      Issued at Salem, New Jersey, April 15, 1980.