PUBLIC LAW BOARD N0. 2206
AWARD N0. 41
CASE N0. 18
PARTIES TO THE DISPUTE:
Brotherhood of Maintenance of Way Employes
and
Burlington Northern, Inc.
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when having Burro Crane
B.N. 975060 repaired by other than Roadway Equipment Repair
Shop Sub-Departments (Traveling Maintainers, Maintainer
Mechanics, and Welders), without benefits of notice, consultation or mutual agreement with General Chairman Funk.
(System File P-P-360C)
(2) That Claimants C.L. Lassiter'and J.W. McCrary now be allowed
equal proportionate shares at their straight time rates of
pay for the total number of man hours expended by Shop Craft
employes in performing the work of repairing the BN 975060
referred to in:Part (1) of this claim.
OPINION OF BOARD:
Claimants were regularly assigned employes in Carrier's Roadway
Equipment Repair Shop. at Vancouver, Washington, a point on the former
Spokane, Portland and Seattle Railway Company (SP&S) territory, represented
by the Brotherhood of Maintenance of Way Employes (BMWE). Each of the
Claimants held seniority in classifications of Mechanic (Traveling
Maintainer), Welder and Helper. The referenced job titles are listed in
Rule 55, Classification of Work, with particular emphasis in this case upon
Rule 55-M, reading as follows:
1
' Awd. 41 - 2206 2 '.~
M. Traveling Maintainer and Maintainer.Mechanic
An employe skilled in and assigned to building (if not
purchased) repairing, dismantling or adjusting roadway
machine equipment and machinery, and on former SP&S
certain repairs to automotive equipment. (Emphasis
added.)
On or about September 19, 1977, one of Carrier's large work cranes,
(Burro Crane No. 975060) was severely damaged when the boom struck some
overhead wires and crashed onto the cab of the crane. The site of the
damage was Mile Post 279.9, on former SP&S territory, between Kahlotus and
Sperry, Washington, a point approximately 270 miles northeast of Vancouver
and 117 miles south of Spokane. Carrier's local officers elected to have
the damaged crane transported to Hillyard Work Equipment Shop, near Spokane,
for repairs rather than to the Vancouver Repair Shop. At Hillyard, the
damaged boom and cab were repaired by shopcraft employes using welding and
metal cutting equipment. The employes who made these repairs are members
of the Boilermakers craft represented by the International Brotherhood of
Boilermakers, Iron Shipbuilders, Blacksmiths, Forgers and Helpers
(IBB).
Apparently it is not contested that the shopcraft employes at Hillyard;
including the Boilermakers, worked on the crane from September 19, 1977
until October 14, 1977 when it was returned to service. Thereafter, the
BMWE filed the present claim in a letter of October 26, 1977, reading in
pertinent part as follows:
Burlington Northern,Inc.,hereinafter referred to as Company,
violated the Effective Agreement on
or
about September 19;
1977 when it failed to have Burro Crane B.N. 975060 repaired
at equipment repair shop in Vancouver, Washington and instead proceeded to effect repairs at Hilliard, Washington
using shop craft employes for this service.
Rules including but not limited to lA,1B,1C,2A,5H,55M, Note
to Rule.55, and Rule 69C are by referral made par t, of this
letter.
' s· Awd. 41 - 2206
PriDPto merger, work of repairing equipment which failed in
service or needed repairs while working on S.P. & S. track
was done by equipment maintainers at Vancouver equipment repair shop. This work is retained for these employes in
accordance with Riles 1C and 69C and contracting of this
work is prohibited except as provided under Note to Rule 55.
Burro Crane B.N. 975060 was damaged while working on former
S.P:.& S. territory between Pasco and Spokane on the B.N.
Seventeenth Sub-Division and therefore should have been repaired by Maintenance of Way employes at Vancouver.
Due
to this violation we request that Claimants C. L. Lassiter
and J..W. McCrary be allowed in addition to any other compensation they may have received, the amount paid to shop craft
employes while working on this piece of equipment from September 19th to October 14, 1977 or when work is completed.
The claim was denied at all levels of handling, up to and including Carrier's
Chief Appeals Officer, who made final denial in a letter dated December 8,
1978, reading in pertinent part as
follows:
tin. F. H. Funk, Vice President
motherhood of Maintenance of
Vay
Pnnloyees
715 Vorthwestern Federal Rldg.
t-'inneapolis, Minnesota 55403
Dear Hr. Funk:
December 8, 197&
File MW-84(t12) 11/21/77
This refers to conference held October 12, 1978 and your
letter dated May 16, 1978, file N-F-360C, regarding claim on
behalf of. C. L. Lassiter and J. 1-:. McCrary.
You have furnished no proof or evidence to support your contention that Claimant Lassiter is a certified welcer. Upon
checking into your statement, fir. Roger Creswell, former
Shon Foreman, at Vancouver, contacted Clair,ant Lassiter in
thls regard and was inforrred by him that he had taken a
weldint- course in a vocational school, but hae never taken a
certification test or been certified as a welder.
Nor is Claimant ?-acCrary a certified welder qualified to perform the work on which claim is based. fir. McCrary has only
been assigned a welder for a short time from January 31,
1977 until displaced on flay 9, 1977. This short period of
tire hardly makes him a qualified welder on all types of
welding.
Awd. 41 - 2206 4
r
In your letter dated 1'ay Ifs,
197ti
you make reference to rena ire rmace to a boom on Burro Crane
X-37
in 1950. We leers
working on boom of
X-37
at that tire are unknown and as to
supervision at the shop 3t that time is also unknown.
In any event, the material. used in the construction of boo s
ir. different now then in the past. As to struts and crow
rernhers on a boors, true struts are replaced with new ones
race of a special steel and are not of common ancle iron as
us>pd in the Past, but have to be welded in this instance to
boor, base with proper weloinE- rod so no improper stress or
oxidation occurs in this section. Proper amount of weloing
application and length of head is critical as, to not causing.
future cracks or breaking of riaterial.
This "achine was damaged at ?'F 279.9 ea=t
of
Pasco on the
17th Subdivision, which is 116.9 riles from Hillyard Shop
whereas Vancouver Shop, even if' it had beer. equipped ape had
the skills recuired to n:alee the repairs, was 270.9 miles
acaav. There was no necessity to ship this machine to Vancouver when it could be repaired at lfillyard where the
enuipment and the skills are.
As previously stated, claim you have appealed completely
disregards the clear provisions of the tine limit on claims
rule as it lacks the essential specifics required to constitute a valid claim. -Other then stating that an alleged violation occurred "on or about'Septerbart9, 1917," you have
not identified who cerforocd the worst, on w"nt dates and
actual hours,alleZedly consumed in the performance of the
work. The burden of proof rests on you as the petitioner to
furnish the required supporting
data
for each and every date
and any effort on your part to advance the claim on a continuing basis is categorically rsjecteo. There
is no
obli~ati.on on the Carrier to develop unknoc;n circumstances or, or
about September 19, i977 or whether tile e=rcurnstances on any
subsequent unnamed date3 were tae saire. Third Division
A!*ard :Ac. 12$118 is but one of many awards tr:at have held.
such defects fatal:
"~incc this elair fails to set forth the nature
and extent of the performance of the disputed.
wort: or when or by who;: it :gas Derfor«ned, the
clairsi is lacking
in the specificity required by
Section
3,
First (i) of the itailway Labor
Act..."
Awd. 41 - 2206
In view of the forecoing, declination of your appeal is respectfully reaffirred.
Sincerely,
L. r.. t~al~/
Asst. to Vice President
EJK/dfd, 6
Thereafter. the claim was appealed to this Board for final and binding disposition.
It should be noted that the Boilermakers organization has a demonstrated.
third-party interest in the present case. In handling on the.property, the
IBB responded on December 17, 1978 to notification from Carrier of the BMWE '
claim, as follows:
This refers to your letter of December 5, 1978 which serves to advise of
a claim appealed to your office by the Maintenance of Way Organization
it
connection with certain repairs to Burro Crane B.N. 975060, performed by
boilermakers at Hillyard Shop, Spokane, Washington.
First, we must point out that Hillyard Shop is formerly a G.N. facility.
(not SP & S) and that boilermakers therein have historically performed
the work as described. in your above referred to letter. We direct your
attention to Rule 57 in the Great Northern Agreement Schedule which
grants to the boilermakers this contractual right and reads as follows
it
pertinent part:
Rule 57.
Boilermakers' work shall consist of building,
repairing, removing and applying steel cabs and running
boards the laying out and fitting up any sheet-
iron or sheet steel work made of 16 guage or heavier ....
..... boilermakers' work in connection with building and
fairing of steam shovels, derricks,booms, housings,
circles and coal buggies, I-beams, channel iron, angle
iron, and T-iron work .......
(underscoring added)
Awd. 41 - 2206 6
The foregoing rule is identical in language to the present rule (Rule 57)
of the controlling agreement. Since builermakers are regularly assigned
and do daily perform the work in question at Hillyard, and doing so in
accordance with contract, custom and tradition of long standing, we
consider the contentions and claim of the Maintenance of Way Organizatior
as an attempt to-capture work properly performed by the Boilermaker Craft
Without receding from our position in any way, we. are unaware of any
instance when Maintenance of Way employees have performed this work
on former S.P. & S. property and we are advised that Blacksmiths are
assigned to this work in Vancouver.
We trust that you will protect the interests of this Organizacion in
this matter.
Yours trulBrian T nson
General Chairman
Prior to hearing of this case by our Board, the Chairman provided the IBB with
notice and opportunity to be heard. The IBB appeared at the Board hearing
and presented a written submission which has been duly considered, together
with the submissions, evidence and arguments advanced by the Carrier and BMWE.'
In addition to Rule 55-M of the present BN/BMWE Agreement supra, other
contract provisions cited and/or relied upon by the three parties herein
include Article I and Rules 40 and 41 of the former SP&S/BMWE Agreement;
Rules 1(c) and 69(c) and Note to Rule 55 in the present BN/BMWE Agreement;
and Rule 57 from the former Great Northern (GN)/IBB Agreement, which is
identical with the present Rule 57 of the BN/IBB
Agreement. -The
referenced.
rules read as follows:
"Article 1 - SCOPE
These rules govern the hours of service and working
conditions of all employes in the Maintenance of Way
and Structures Department, including derrick and
steamshovel operators, pile driver operators, and
water service foremen; not including supervisory
forces above the rank of track inspector, and not including the signal, telegraph and telephone maintenance departments, and clerks."
Awd. 41 - 2206 7
"RULE 40.
All work on Operating property, as classified in
this Agreement, shall be performed by employes
covered by this Agreement, unless by mutual agreement between the General Chairman and designated
Representative of Management, it is agreed that
certain jobs may be contracted to outside parties
account inability of the railroad due to lack of
equipment, qualified forces or other reasons to
perform such work with.its own force's. It is recognized that where train service is made inoperative due to conditions such as, but not limited to,
washouts or fires, individuals or contractors may
be employed pending discussion with respect to such
mutual agreement."
"RULE 41. (Revised 12-4-59)
Roadway Equipment Repair and Operation Department
Forces will be composed of the following classes of
employees as the nature of the work requires:
First--Mechanic. An employee skilled in and assigned
to building, repairing, dismantling or adjusting roadway machine equipment and machinery,
automotive equipment, and responsible for
sucn worx.
"RULE 1. SCOPE
C. This Agreement does not apply to employes in the
Signal, Telegraph and Telephone Maintenance Department,
nor to clerks. The sole purpose of including employes
and sub-departments listed herein is to preserve pre
existing rights accruing to employes covered by agree
ments as they existed under similar rules in effect on
the CB&Q, NP, GN and SP&S railway companies prior to
date of merger; and shall not operate to extend juris=
diction or Scope Rule coverage to agreements between
another organization and one or more of the merging
companies which were in effect prior to the date of
merger."
Awd. 41 - 2206 8
"RULE 69. EFFECTIVE DATE AND CHANGES
C. It is the intent of this Aqreement to preserve
pre-existing rights accruing to employes covered by
the Agreements as they existed under similar rules
in effect on the CB&Q, NP, GN and SP&S Railroads
prior to the date of merger; and shall not operate
to extend jurisdiction or Scope Rule coverage to
agreements between another organization and one or
more of the merging Companies which were in effect
prior to the date of merger."
"NOTE to Rule 55: The following is agreed to with respect
to the contracting of construction, maintenance or repair
work, or dismantling work customarily performed by employes in the Maintenance of Way and Structures Department.
Employes included within the Scope of this Agreement -
in the Maintenance of Way and Structures Department, including employes in former GN and SP&S Roadway Equipment
Repair Shops and welding employes - perform work in connection with the construction and maintenance or repairs
of and in connection with the dismantling of tracks, structures or facilities located on the right of way and used in
the operation of the Company in the performance of common
carrier service, and work performed by employes of named
Repair Shops.
By agreement between the Company and the General Chairman,
work as described in the preceding paragraph which is
customarily performed by employes described herein, may
be let to contractors and be performed by contractors'
forces. However, such work may only be contracted provided that special skills not possessed by the Company's
employes, special equipment not owned by the Company, or
special material available only when applied or installed
through supplier, are required; or when work is such that
the Company is not adequately equipped to handle the work,
or when emergency time requirements exist which present.
undertakings not contemplated by the Agreement and beyond the capacity of the Company's forces. In the event
the Company plans to contract out work because of one of
the criteria described herein, it shall notify the General
Chairman of the organization in writing as far in advance
of the date of the contracting transaction as is practicable and in any event not less than fifteen (15) days
Awd. 41 - 2206
9
prior thereto, except in 'emergency time requirements,
cases. If the General Chairman, or his representative,
requests a meeting to discuss matters relating to the
said contracting transaction, the designated representative shall make a good faith attempt to reach an understanding concerning said contracting, but if no understanding is reached the Company may nevertheless. proceed
with said contracting and the Organization may file and
progress claims in connection therewith."
BOILERMAKERS' SPECIAL RULES
Rule 57. CLASSIFICATION OF WORK
Boilermakers' work shall consist of laying out, cutting
apart, building or repairing boilers, car tanks and drums,
inspecting, patching, riveting, chipping, caulking, flanging
and all flue work; building, repairing, rcntoving and applying
steel cabs anti running boards, metal headlight boards. n'ind
sltects, ctiginc tender tanks, steel tender frames (except such
parts of steel tender frames as are necessary to be broueltt to
car shops for repairs), pressed steel tender truck frames,
building and repairing metal pilots, the rcrnoving and applying of nictal pilots to nictal pilot beams; the laying out and
littitig up any slicct-iron or sltect-steel work tttaile of 16
~_augc or heavier, including fronts and doors, grates and grate
rigging.
aslt pans, front -end netting and diaphra_;tt work,
removing and applying all stay bulls, radials, flexible cabs,
sl;cves, crown bolts, stay rods, and braces in !oilers. tanks
ana drums; appl%ing anti removing arch tubes. r·; era!ing
punches and sltcars for shaping anti forming. plwumatic Staybolt breakers, air rams and hannmrs; bull, jatn and coke
rivetcrs; boilermakers' work in connection with the building
.ii :d
repairing of steam sluwels, derricks, booms. hou'ing,
circles, ant coal bue-ics. I-beam, cltann·:1 iron. ;:nae iron,
and ·!'-iron work, all-drillitif_, cutting and tapping and op ~rating rolls in connection with boilcrntakcrs' work; o:<%ncctyIcnc, tlt:rmit and electric welding oft work g·:ncraliy reco~-
nizcd as boilermakers' work, and all outer work Senemllv
rccognizcd as boilertnakcrs' work.
The underlying basis for this claim is the BM14E contention that the
repair work on the Burro Crane damaged on former SP&S territory would have
gone to the BMWE employes at the Vancouver Repair Shop under the former
SP&S/BMNE Agreement and, therefore, those employes were entitled to the
work under Rules 1(c) and 69 (c) of the present Agreement BN/BMWE Agreement.
B144E alleges additionally and alternatively that Carrier also failed to
comply with the consultation requirements of Rule 40 of the former SP&S/BMWE
Agreement and Note to Rule 55 of the BN/BMWE Agreement. Rule 55-M of the
BN/BMWE Agreement also is relevant because it contains the following express
reference: "...on former SP&S certain repairs to automotive equipment".
Therefore, the bottom line allegation of the BMWE is that Carrier violated
Rules 1(c), 55 and 69(c) of the present BN/BMWE Agreement, incorporating
by reference Rules 1, 40 and 41 of the former SP&S/BMWE Agreement.
Carrier answers that the BMWE had no "exclusive" right under the former
SP&S/BMWE Agreement to perform the work of repairing machinery like the
Burro Crane and, therefore, cannot claim such work under the present
"general" BN/BMWE Scope Rule. Arguendo, Carrier asserts that even if there
was a violation in the facts of the present case damages should not be awarded
since Claimants were "fully employed and under pay" during the time the shopcraft employes did the repair work on the train. The IBB avers that since
the work was performed at Hillyard, a former GN point, it belongs "exclusively"
to their craft pursuant to the express provisions of Rule 57 of both the
former GN/Shopcraft and BN/Shopcraft Agreements.
We have decided claims somewhat similar to the instant dispute in our
earlier Awards No. 8 and 20, construing and applying Rules 1(c) and 69(c),
and Awards No. 34 and 35 interpreting Rule 55 and the Note to Rule 55.
Awd. 41 - 2206 I1
The same general,principles which required dismissal of the claims in
Awards No. 8, 20, 34 and 35 mandate a sustaining Award in the factual context of the present case.
As we held in Awards No. 8 and 20, Rules 1(c) and 69(c) have the
intent and effect of preserving pre-existing Scope Rule rights of Maintenance
of Way Employes on the merged BN, as they existed on the respective premerged carriers. In other words, such rights are "frozen" in time as they
existed on the effective date of May 1, 1971. We frequently have pointed
out that the rights thus preserved by Rules 1(c) and 69 (c) on the merged
Carrier are coextensive with, and consequently neither lesser nor greater
than, the work reservation rights enjoyed by the employes under their
respective previous agreements between B14WE and the former CB&Q, NP, GN
and SP&S railway companies. Thus, the proper focus of inquiry in the
present case is to determine whether Claimants would have been entitled
under the former SP&S/BMWE Agreement to perform the work in contention
herein. If so, then that "pre-existing right" was carried forward and
preserved by Rules 1(c) and 69(c) which would be violated by Carrier's
unilateral assignment of the work to the Boilermakers at Hillyard. If the
work would not have "belonged" to the Claimants under the former SP&S/BMWE
Agreement then the claimed violation of Rules'1(c) and 69 (c) of the present
BN/BMWE Agreement would be without foundation.
Much of the controversy in the earlier scope rule cases we have
decided has resolved around the "general" versus "specific" dichotomy.
Thus, in Awards No. 8 and 20 we pointed out that where the "pre-existing
right" arose under a general scope rule which was silent or ambiguous in
its express language regarding work reservation, then the organization
alleging a violation of present Rules 1(c) and 69(c) has to show reservation
' Awd. 41 - 2206 12 ':
of the work on the former property by custom, practice and tradition of
performance to the practical exclusion of others. The corollary applies
equally and consistently, however, i.e., if the Scope and/or Classification
Rules on the former territory were "specific" in the express reservation of
the disputed work for Maintenance of Way Employes, then the organization
does not have the evidentiary burden of proving "exclusivity" and does not
have to prove reservation-by custom, practice and tradition in order to make
out a violation of present Rules 1(c) and 69(c)..
Under the foregoing governing principles of interpretation, initially
we must inquire whether Article I or Rules 40 and 41 on the former SP&S/BMWE
Agreement expressly and specifically reserved to Maintenance of Way Employes
the work of repairing machine equipment like' the damaged crane. A long
line of Third Division decisions has held that Rules 40 and 41 of the SP&S/BMWE
Agreement reserved expressly for Maintenance of Way Mechanics the repair of
damaged automotive equipment and roadway machine equipment on the former
SP&S. Awards 3-19684; 3-19898; 3-19909; 3-19924; 3-20042; 3-20338; 3-20412
and 3-20633. Several of the cited cases are virtually on all fours with the
central issue in this case and we find no basis to deviate from the line of
unbroken precedent. We have no hesitancy in following those decisions and
holding that had this claim arisen under the former SP&S/BMWE Agreement, the
BMWE Mechanics would have been entitled to perform the repair work on the
Burro Crane damaged on SP&S property. Since the Claimants would have been
entitled to the disputed work "but for" the merger, this pre-existing right
to the work is carried forward and preserved under Rules 1(c) and 69(c) of
the BN/BMWE Agreement. Additional impetus to support the claim is provided
by the express language of Rule 55-M, although we stop short of finding
- Awd. 41 - 2206
13
that Rule 55=M standing alone constitutes a reservation of the disputed
work to BMWE.,
Based upon the foregoing analysis, we are compelled to conclude that
Carrier did violate Rules 1(c) and 69 (c) of the BN/BMWE Agreement (and
implicitly Rules 40 and 41 of the SP&S/BMWE Agreement) by assigning the
repair work on the Burro Crane No. 975060 to Boilermakers at Hillyard
rather than to the BMWE employes at Vancouver Repair Shop. In so holding,
we do not derogate the language of Rule 57 of the BN/Shop craft Agreements.
However, we deem it critical to the outcome of this case.to note that
Carrier transported the crane from the point of damage on the former SP&S
territory to a repair facility on former GN territory to be repaired by
Boilermakers, rather than taking it to the former SP&S repair facility
at Vancouver where Claimants were employed. In the freeze-frame view and
retrospective analysis mandated by the "pre-existing right'.' clauses in
Rules 1(c) and 69(c), that action was the functional equivalent of taking
the work off of the property (SP&S) and giving to foreign contract employes
(GN) without prior discussion with the BMWE General Chairman. If, as Carrier
alleges, skills and facilities at Vancouver were insufficient to handle the
job then such were matters for discussion with the Organization under
Rules 40 of the SP&S/BMWE Agreement and the Note to Rule 55 of the BN/BMWE
Agreement, and not for unilateral transfer of the work by Carrier.
' Based upon all of the foregoing, we shall sustain Part (1) of the
claim. With respect to Part (2), Carrier's plea that no damages should
lie for the proven violation is rejected for reasons developed in Awards
3-19898; 3-20042; 3-21412; 3-20633; 3-21340 and 3-21808. However, the
Organization as moving party is under the obligation to provide for the
14 _ ' .
Awd. 41 - 2206 . . . .:
record sufficient evidence upon which this Board may calculate and award
compensatory damages if violations are proven. The present record is devoid
of any probative evidence concerning the number of man-hours spent during
the period September 19 through October 14, 1977 by the Boilermakers performing the welding and other repair work to the boom and cab of the damaged
crane. The lack of specific evidence on this critical point was raised by
Carrier in handling on the property but never adequately responded to by
the Organization. This evidentiary gap redounds to the detriment of the
Organization which has the burden of proving every material aspect of its
claim, including type and amount of damages. In,the face of the proven
violation of Rules 1(c) and 69(c) it would be a travesty to award no damages
at all. But in the absence of specific proof regarding the amount of lost.
work opportunity, we shall award only nominal damages of one (1) hour of
pay
at the straight-time rate for each Claimant for each regular working
day during the period September 19 through October 14, 1977..
AWARD
1. Part (1) of the claim is sustained.
2. Part (2) of the claim is sustained only to the extent indicated
in the Opinion..
7
vu
Carrier Member Employe Member
Dana Esche Chairm n
Date: 1
C)11.C
.~