PUBLIC LAW BOARD N0. 2206
AWARD N0. 46
CASE N0. 28
PARTIES TO THE DISPUTE:
Brotherhood of Maintenance of Way Employees
and
Burlington Northern, Inc.
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when permitting outside
forces to construct 680feet of subgrade embankment on the
Lake Kapowsin Branch near Mile Post 7, January 9,10,11,12,
13,16,17,18,19 and 20, 1978. (S-P-163C System File).
(2) That Claimants J.R. Whitver and T.J. Bradshaw now be
allowed 80 hours each at Group 2 rate of pay January 9,10,
11,12,13,16,17,18,19 and 20,,1978.
OPINION OF BOARD:
In this case, the Organization alleges a violation of the Scope
Rule and the Note to Rule 55 when Carrier subcontracted for outside forces
and equipment to repair flood damage, without adequate notice and/or
agreement of the General Chairman. The work at issue was described in a
January 9, 1978 letter from Carrier to the General Chairman, reading as
follows:
1
Awd. 46 - 2206 2
Mr. F. H. Funk, General Chairman January 9, 1973
Brotherhood of Maintenance of
Way Employees File MW-84(c)-Track
500 Northwestern Federal Building
Minneapolis, Minnesota 55403
Dear Mr. Funk:
As a result- of the heavy rain and resulting flood conditions on the ?Jest Coast during the month of December 1977,
the track washed out at two locations near MP 7 on the
Lake Kapowsin Branch.
The washout east of MP 7 is 500 feet long and 8 feet deep
with the track gone. The second washout is 200 feet west
of the above washout and is 180 feet long and about
7
feet deep, with the track hanging. In order to construct
the embankment for the track now that the water level in
the stream has dropped, it will be necessary to work
dozers in the stream to push up gravel for an embankment.
With the number of washouts that have resulted frcm the
f'lood conditions, we do not have heavy equipment available to perform this work in order to restore traffic
on this line. For your information, dozers any: operators
from St. Regis mill will be utilized to construct the
embankment. After the emban.aent is constructed, Carr_er
forces will construct the track and protect it with heavy
rip rap.
Sincerely,
L. K. Hall
Asst. to Vice President
The General
Chairman promptly
requested a conference which was held on
January 19, 1978, but no agreement was reached between the parties. In the
meantime, Carrier had already contracted with the St. Regis Company to perform the reconstruction of the washed out bank. The outside forces completed
the embankment work in ten days between January 9-19, 1978, using three
D-8 Caterpillar bulldozers, one front-end loader and three ten-yard dump
trucks. Thereafter, Carrier's Maintenance of Way employes replaced the rail
and secured the embankment by placing some 1,300 cubic yards of riprap.
Awd. 46-- 2206
The present claim was initiated by the Vice General Chairman on
February 16, 1978, as follows:
February 16, 1978
Mr. i). H. Burns
Superintendent
30'3
South Jackson Street
Seattle, Washington 98104
Dear Mr. Burnst
I am herewith filing a Claim on behalf of J. R. Whitver, S.S.)) 536-50-2743,
and T. J. Bradshaw, S.S.# 516-56-8610, Group 2 Machine Operators on Seniority
District il 6, when the B. N. Inc. hereafter refered to as the Company, hired
2 D-8 Caterpillars from the St. Regis Mill to construct: 680 foot of embank
ment washed out by floods in December 1977.
The. Company ,had X71-WC659 a D-8H Cat available at Snohomish, Washington
which was setting idle during the time the St. Regis cats were in use, The
X71-0807 arD-8 Cat was abolished, X71-WC657 a D-7 Cat was abolished, and
X71-0728 a D-7 Cat has been abolished for I year for repairs. There were
D-7 Cats working at locations other then the washed out areas..
Mr. Whitver and Mr. Bradshaw had followed Group 2 roster positions until
November when their Seniority would riot allow them to continue , so they
had to displace Sectionmen to continue working for the Company. Had the
machines listed above been
bulletined and
assigned they would still be
working in Group 2.
The Company is in violation of the. i-tcluding, but riot limited to the.
following Rules, 1-13, 1-C, 2-A, 55-N and the Not.i to f;ule 55. The Company did not ask approval to contract until the day the work began by the
Contractor, which was January 9, 1979.
This Claim i, for 80 hours each at Croup 2 ratr of pay for the above .
named limployes(January 9-10-11-12-13-16-17-18-19-20, 1978)
Please advise if this Claim will be allowed as'presented. A conference is
requested and desired at an early date.
Yours Truly,
. ·Duane D. Tulberg
Vice General Chairman
Awd. 46 - 2206 4
After much discussion on the property, with-several conferences and crossfiling of conflicting allegations regarding the adequacy of Carrier's bull-
dozers and other equipment,. a final denial of the claim was made on -
February 13, 1979, as follows:
Mr. C. H. Lindsey, Gen. Chmn. February 13, 1979
Bro. of Maintenance of Way Employes
500 Northwestern Federal. Building File MW-84(c) 4/21/78
Minneapolis, Minnesota 55403
Dear Mr. Lindsey:
This refers to your file S-P-163C .of January 29, 1979, in
the claim of H. R. Whitver and T. J. Bradshaw for 80 hours
each at Group 2 rate, January 19-20, 1978, when a
contractor constructed 680 feet embankment washed out by
floods on the Lake Kapowsin Branch.
I do not concur in your views that the D-7 caterpillars
were as good as the D-8 used by the contractor. This was
an emergency and we have adequately demonstrated that fact
in view of which the claim is not valid and declination is,
therefore, respectfully reaffirmed.
Sine re y,
all
Asst. to Vice President
LKH:at33
We have reviewed all of the voluminous correspondence, cited arbitration
awards and other evidence submitted to us by the parties. It is plain that
the work at issue normally and customarily would have been performed by
machine operators, laborers and sectionmen represented by the Organization.
Nor can it be seriously contested that the January 9, 1978 letter advising
the General Chairman of a fait accompli was not adequate notice under the
fifteen-day minimum notice and consultation requirements of the Note to
Rule 55. Thus, the organization would have made out a prima facie violation - _
Awd. 46 - 2206
of the Note,~if that provision applied in the present fact situation.
The single exception to the notice and consultation requirements of
the Note is the "emergency time requirements cases" provided for in the
exculpatory language contained in the last paragraph of the Note to Rule
55, as follows:
Nothing herein contained shall.be construed as restricting the right of the Company to have work customarily
performed by employes included within the scope of this
Agreement performed by contract fn emergencies that
affect the movement of traffic when additional force
or equipment is required to clear up such emergency
condition in the shortest time possible.
Thus, all of the. argument and evidence regarding the conditions set forth
in the third paragraph of the Note to justify subcontracting after due
notice and consultation, but in the absence of agreement by the General
Chairman are irrelevant and serve only to cloud the issue presented in this
case. The only question properly before us in this case is whether the
emergency time requirement conditions supra obtained when Carrier let the
contract to St. Regis. , Thus, we must inquire: Did the .conditions near
M.P. 7 on the Lake Kapowsin Branch constitute an emergency that affected
the movement of traffic and which required additional forces or equipment
to clear up in the shortest time possible? In the context of the language
in the Note, the burden is upon Carrier to provide substantial probative
evidence on the record to show that such emergency time conditions obtained
to justify its failure to comply with the otherwise mandatory notice and
consultation requirements of the Note. After careful analysis of the record
we are persuaded that Carrier has carried that burden in this case.
The flood damage to Lake Kapowsin Branch was only part of catastrophic
damages caused by double the normal amount of rainfall in Washington state
in.1977. Unrefuted record .evidence indicates that flood damage resulted in
6
Awd. 46 - 2206 `-
delcaration of a state of emergency by the Governor. Carrier specifically
experienced bridge, culvert and roadbed damage on main line and branch
trackage on the 1st, 3rd, 4th, 12th and 15th subdivisions of its Pacific
Operating Division; with stranded trains, washed out bridges, impassable
trackage and rerouted service throughout the area. On the Lake Kapowsin
line, the Puyallup River overflowed, changed course and washed away 700
feet of track, thus cutting off rail access to the St. Regis Lumber Mill,
a major user of Carrier's service. We find the foregoing persuasive evidence
that an emergency condition existed which affected the movement of traffic
Moreover, the record persuades us that with the placement and occupation
of Carrier's equipment and forces elsewhere repairing the extensive damage
on the system, utilization of the available and willing St. Regis forces
and equipment was "required to clear up the emergency condition in the
shortest time possible".
Based upon the foregoing, we find'that the "emergency time requirement"
conditions of the last paragraph of the Note to Rule 55 obtained in this
case and, therefore, the Agreement was not violated.
AWARD
Claim denied.
Carrier Member Employe Member
Dana E. Eischen, ai n
Date:
~~