PUBLIC LAW BOARD NO. 2206
AWARD No. 55
CASE No. 52
PARTIES TO DISPUTE:
Brotherhood of Maintenance of Way Employe,.:s
and
Burlington Northern, Inc.
STATEMEMT OF CLAIM:
_ Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement July 10 and 24 and August
8 and 20, 1978, and thereafter when assigning Bridge Tender
D. D. Williams to recharge the chemical toilet on Drawbridge
4#1 at Pasco, Washington, instead of Water Service Mechanic
N. J. Carrier. (System File P-P-404C)
(2) Water Service Mechanic N. J. Carrier be allowed 8 hours pay
at Claimants straight time rate of pay for violation on
July 10 and 24 and August 8 and 20, 1978, and for hours
violation continued as listed in Employe's Exhibib "B".
OPINION OF BOARD:
This claim involves the work of "charging" (i-ee., placing of fresh
water in the holding tank) of a chemical toilet located in the Drawbridge
Tenders' quarters on Bridge lit spanning the Columbia River at Paso, Washington.
In spring 1978 the Carrier replaced the old chemical toilet, which required
recharging with about 25 gallons of water and caustic chemicals, with a new,
more modern, toilet which required only 10 gallons of water. The task of
recharging specifically involves drawing fouled water from the toilet into a
holding tank, adding a packet of chemicals, and then adding 5 to 10 gallons
of fresh water from a nearby faucet.
~~E9 aaoG _,o-~o
ss-
The new toilet was installed by the local B&B crew and Water Service
employes covered by the BMWE Agreement. It is not disputed that with both
the old and new toilets the Water Service employes periodically pump out and
dispose of the waste from the holding tank below the toilet. The Organization
asserted, and submitted corroboration to support, that Water Service employes
recharged the old "non-recyclable" toilet on Bridge 111 periodically, at the
time they emptied and cleaned it, by filling its 25 gallon tank with water and
adding chemicals. The Organization maintains that the new toilet was installed
on March 22, 1978 but Carrier'says it was installed on May 22., 1978. In any
event, after its installation the Water Service employes did the servicing,
including recharging, until on or about June 28, 1978, when Bridge Tender
Williams was ordered by B&B Supervisor Wold henceforth to recharge his own
toilet. At Wold's direction, the Water Service employes who formerly had been
doing the charging as part of the servicing of the toilet, instructed the
Bridge Tender on the techniques of recharging the water tank. The Bridge
Tender thereafter started recharging the toilet approximately every two weeks,
and the claim thereafter was initiated by letter of September 1, 1978, reading
in pertinent part as follows:
Burlington Northern,Inc.,hereinafter referred to as Company,
violated the Effective Agreement on July 10, 1978, July 24,
August 8 and August 20, 1978 when it used other than water
service employes to charge the chemical toilet located on
drawbridge number 1 at Pasco, Washington.
Rules including but not limited to IA, 1B, SE, and 55 E, are
by referral made part of this letter.
The charging of this type toilet is work which comes under
the jurisdiction of water service employes. They have been
used exclusively for this work until recently when B & B
Supervisor O. R. Wold decided he would "discipline" Bridge
tender D. D. Williams by requiring him to
perform
this service.
PLB-2206
a
AWD. 55
Due to this violation we request that Claimant water ser~·ice
mechanic N. J. Carrier be allowed eight(8)hours at his straight
time rate of $7.28 per hour for a total amount claimed of $58.24.
This to be in addition to any other compensation he may have
earned.
This is a continuing claim until such time as the work of
charging this chemical toilet is reverted back to the water
service where it properly belongs.
The claim was handled to the top Carrier appeals officer on the property
who denied it on grounds that the work was "not described in either Rule 1 or
55-E",
that Water Service employes had not performed the work with "system-wide
exclusivity", and that arguendo, Claimant was "fully employed" on claim dates.
The claim subsequently was appealed to the Board and periodically supplemented
thereafter with additional data concerning subsequent recharging of the new
toilet by the Bridge Tender.
There is little room for doubt that the Organization has established the
existence of a custom, practice or tradition of exclusive performance of the
work of recharging the chemical toilet at Bridge 111 in Pasco, Washington.
However, to prevail under a theory of reservation through practice the Organization is required by principles, not of our own making but imposed by the.
great weight of precedent in this industry, to show such exclusive performance
on a system-wide basis. Not only does the record fail to show such exclusivity,
but the Organization apparently does not refute Carrier's evidence that for
some ten years chemical toilets in road crew Univans have been recharged by
the B&B employes using them, rather than exclusively by Water Service employes.
Accordingly, the claim cannot be sustained under Rule 1.
Pch a~-o~-A~.~,o S.T
i
It appears that this claim must rise or fall upon the express language
of Rule
55-E,
as follows:
"RULE 55. CLASSIFICATION OF WORK.
E.
Water Service Mechanic-Pump Repairer.
An employe skilled in and assigned to repair pumps, pipe
lines, or any other work in connection with the maintenance
of water or fuel supplies or steam heating plants, including
the bending, fitting, cutting or threading of pipe in connection with pipe work, coming under the jurisdiction of the
Bridge and Building Department, shall be classified as a
water service mechanic, pipefitter, steamfitter or plumber."
In our considered judgement, the foregoing language of Rule
55-E
does not
expressly reserve to employes covered thereby the work of pouring water and a
packet of chemicals in to a toilet. The Organization relies upon the words:
"...other work in connection with the maintenance of water". But that phrase
is not specific in its description of work and therefore requires adversion
to system-wide practice, which
is
not demonstrated on this record. Where the
language of Rule
55
is clear and unambiguous we have not hesitated to enforce
its work reservation impact. See PLB
2206-53.
But ambiguous or open-ended
language such as that at issue herein cannot be used to sustain this claim.
AWARD
Claim denied.