PUBLIC LAW BOARD N0. 2206
AWARD N0. 59
CASE N0. 61
PARTIES TO DISPUTE:
Brotherhood of Maintenance of Way Employes
and .
Burlington Northern, Inc.
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when permitting outside
forces to install 100 feet of 24 inch corrugated metal pipe,
2 catch basins, 360 feet of 12 inch corrugated metal pipe,
350 feet of 6 inch sewer line, 375 feet of 2 inch water
line and constructing forms and pouring a 18 inch by 40
foot concrete strip at Auburn, Washington between August 15
and October 2, 1978. (System File S-P-178C)
(2) Because of said violation Claimants J. R. Mobley, A. G.
Robinson, K
. C. Beazley, L. J. Scheer, L. M. Richards,
S. R. Fulkerson and L. A. Fisher now be allowed 73 hours
each at their respective straight time rates of pay for
violation recorded in part one (1) of claim.
OPINION OF BOARD:
Under date of July 27, 1978 Carrier advised the Organization's General
Chairman, ostensibly pursuant to the Note to Rule 55 as follows:
It is proposed to construct a new automobile unloading
facility at Auburn, Washington for Volkswagen of America,
Inc.
Construction of the facility, to be in operation by October
1, 1978,
will involve construction of trackage, grading,
paving, drainage and fencing. The following items of work
will be handled by contract forces:
a~.o&
.awe ~9,
Place 3,000 cubic yards of embankment for track
construction.
Place 100 ft. of 24-inch corrugated metal pipe.
Excavate 3,000 cubic yards of top soil and sod.
Place 6,000 cubic yards of embankment for paved
area.
Place 3,500 cubic yards gravel base for paving.
Place 15,300 sq. yds. of asphalt paving (four
inches thick).
Place two parking lot type catch basins.
Place 360 ft. of 12-inch corrugated metal pipe.
Construct 350 lineal feet of six-inch sewer line.
Construct 375 lineal feet of two-inch water line.
Provide striping.
It will be necessary to handle the work as outlined above
by contract because of the magnitude of the project, time
constraints and lack of equipment. The borrow material
for the grading work will have to be hauled by a fleet of
trucks or special grading equipment which we do not have
at Auburn. The paving work will require special paving
equipment not possessed by the Carrier. Placement of the
CM culvert pipe will be coordinated with the grading operation. Installation of the water and sewer lines is
required to be contracted because of the need for licensed
personnel. Placement of catch basins and drain line will
be coordinated with the paving operation. The Carrier
does not possess equipment required to perform the
striping work.
The General Chairman objected to this proposal and, following a conference
to discuss the matter, notified Carrier on August 28, 1978 as follows:
Please refer to your letters of july'77, 1978 and August i, 1978
concerning your desire to caatract
construction of
nsv aatosobila
. anlaadinz facility at Aura!
Washington for Volkswagen of America,
Ian .. . .
During conference August 10, 1978, I infarwed yon that
7 csaaot
a=rse to this rock other than. the placement of base material prior to
piacemaat of the asphalt oareneat. Therefore, I scat clrisa that sm
desire to perform all other voric in connection, with this project.
8a%Mitti=g of. contract forms to pl- the ;ravel caaa for aspaait
sasf'aeing yould easy be with the esderstaading that it doss not es
tablish a precedent or vainer or tights of by
oar Or·.;anixaticn
.·,0
7arfora t.5ia work in the futures.
PLB-2206
' AWD. 59
Carrier went forward with project using outside forces, following which
the present claim was filed on October 4, 1978:
a .rte a:~i~.:5 i ,:x~3
?n veauli of/ G-aan J. R.
_6bley, ":Jtntur3,
.t.
i. _uti::acn, ... .:. Beuzley, L. J. .ichecr,
a.. :~.
:.1c~ar:.s. upara"r
..t
..aclvlOU tn~L-.:V .:y .,. .'.. ..:-kcr"f:, i. and 3.
L~cd 1GC.iC3a
at ,u.uzn,
na.
::1::
':ester
3=~'Y~CC i-:PCflaniC
L. a1. Fij:ier iocateu at uburu,
nF:S.~t7:xt..'.7, 'N.~>?.'1
i;:.e .aur_1r.Fton N.;rtarer
Lnz.,
aavreafter rt?r=Pp, to
:1W
are
C.-IDJ0V
71irtl
:tSide .°cr^.1l:
._. ?C tt18 °r·.Tynaj...,.
rrr~.
n13r8
1Ct) fnot r.`f
i.A ·.1c^7
c.)r-jF,ate,'
net al
':78,
!)lace 2 parting lot Me catch
baa139,
Dace aaG
f"t
O:
il -nc'1
currututed metal pi=e, place 3.iu foot of .a ~.i'.ca: ?ewe-
Lira,
n1ace 37= foot
u2 _::cn ':atz= lire and ')l:ild Zrrr:L %nd pour an iQ
·.ncr r..t
= Sr aaU
Trut
l:ng strip ..: cura.'rnte
at
an unioadintS :aci:it7 at asuul.r:a, ..sa:::gton for
t.ie ;V-~'-awa,;eft U'f
.i.:^t'ICC
Znc,,
rm
:omrany PrnLerti
;)etWNPn AluFrlbt _`, lyi:1
1. ,S y.
Zee u. sad a. =orcea anti Machine t:aarat=a are .net cap^1Vltn
n; r~oino c~,1:.
",~"- UI '.iC=::.
Earl-
tl213
-par, ::?7 rC::pleted a al$1i&r
rJ'_CL
;It
'..3
. _.. 'r:
t..= .'.:
nr:
trCT:t r:
-..ant a . C
'A'_^. .. :.;1:::~ LOia.
:he ;&)-ioany is in violation
os
tP.s °!ollowinj bait -icrr 12.aitac!
to
-·^a4
-,-F itir
urZfacti~- ngree^ent
Gated ^:3y
1, 1"'i1,
'iu!Ez
l~a,da·,
~-rf, »-3,y,c,;_.r, _-a;
and -loan to Rule 55. Tti3 Claim is for a total of 511 h^~·r~ ~-
77
'·~ur.A ° ,.
?ac!: u:ploye at their r2s?ecti7e rate oI pay for
_r.a:::
:"nUq
rl%trr..l nt~lt,eov.
"1S33e
acvise i= this Claim will be allowed as ^,rasant~,
.~ _ ...~-.._~r .
Insir^_d and r8QL23t.-d -it an early .:ate.
The claim was denied by Carrier on familiar grounds of "non-exclusivity",
applicability of one or more of the conditions subsequent in the Note to
Rule 55, and "full employment'". However, by letter of July 25, 1979 Carrier's
top appeals officer denied the claim on an additional and alternative ground,
as follows:
This refers to conference held June 21, 1979, at which time
you discussed with Mr.
c.
J. Kallinen of my staff your
appeal of claim on behalf of J. R. Mobley and six others for
73 hours each between August 15 and October 2, 1978, when
contractor constructed a new automobile loading facility at
Auburn, Washington, for Volkswagen of America, Inc., your
I file S -P-178C.
As discussed in conference, the new automobile receiving
terminal to serve Volkswagen of America, Inc., is a facility
for the shipper and is not for use in the operation of the
company in common carrier service. This facility is no
tiffere_nt than grain elevators located on railroad property
and leased to a grain company. Work on This ?rojec~ was
3~-a ~ -~ Ac
.,-!r~
s ~ 4
progressed only after assurance had been obtained by the
shipper from the carrier that the premises would be covered .
by a formal lease. Attached is copy of lease No. 229,774
which was ultimately signed on October 31, 197,8. The
portion of vote to Rule 55 quoted below makes it clear the
Carrier has specifically reserved the right to contract work
when the conditions as stated above are present:
" . perform work in connection with the construc
tion and maintenance or repairs of and in connec
tion with the dismantling of tracks, structures,
or facilities located on the right of way and used
in the operation of the Comoan in the performance
o common carrier service ...." emphasis added)
In view of the foregoing, there was no necessity to serve
notice of intent to contract the work. In any event,
serving such notice of intent to contract, in error, does
not constitute admission that the disputed work is covered
within your scope rule.
It is well established that serving notice of intent to contract does not establish exclusive Scope Rule coverage of
the work involved, as stated in Third Division Award 20920:
"Additionally, Petitioner contends that the giving
of notice as to the contracting constituted an
admission by Carrier that the disputed work was
covered by the Scope Rule.
"We cannot agree. Such notice is required under
the Agreement in the event Carrier plans to con
tract out work. The giving of such notice,
therefore, merely serves as formal compliance with
the Agreement; it does not of itself establish ex
clusive Scope Rule coverage of the disputed work,
negatively or affirmatively. For example, had the
Carrier elected not to give notice it would not
logically follow that the work was _not within
Scope Rule coverage."
Third Division Award 14263, Referee Lynch, :'1W v. SP, denied
a similar claim, wherein the carrier leased ground to
Western Freight Association and engaged a contractor to construct a building thereon:
"There have been seven recent claims progressed by
the Organization to the Third Division involving
these same parties and the same issue. They were
considered by six referees, and denial awards were
issued in all seven cases, Award Mos. 9602, 10080,
10722, 10986, 11150, 11462, 14019."
A .f t
PLB-2260 5
AWD. 59
The foregoing contentions by Carrier with respect to the nonapplicability
of the Note to the project were not effectively rebutted by the Organization,
either in handling on the property nor in written submissions and oral argument
before this Board. Carrier buttressed and corroborated its positions with
unrebutted documentary evidence showing that the facility was built off
Carrier's right of way; that it was constructed to serve Volkswagen of America,
Inc., which entered into a year-to-year lease of the facility; and that it was
not used in the operation of the Carrier in the performance of common carrier
service. On the basis of the foregoing we are persuaded that the Note to
Rule 55 did not prohibit the subcontracting of the work on that project. The
claim must be denied.
AWARD
Claim denied.
Employe Member
Carrier Member
Dana E. Eischen, Chairman
//4J
Z
Date:
~(-`:~c,~.~C.~f