PUBLIC LAW BOARD NO. 2366
AWARD NO. 47
DOCKET N0. 61
PARTIES TO DISPUTE:
Brotherhood of Maintenance of Way Employees
and
Illinois Central Gulf Railroad Company
STATEMENT OF CLAIM
'"(1) The Carrier violated the Agreement when it reduced
below forty (40) hours,, and without the required
five (5) working day advance written notice, the
work week of the seventy-seven (77) employees listed in Employees' Exhibit "A-1". (Organization's
File: System; Carrier's File 1504)
(2) The Claimants shall each be allowed eight (8)
hours pay at their respective rates for January
15, 18, 19 and 20, 1982."'
OPINION OF BOARD
There is very little dispute
as
to the facts which gave
rise to the claim before us.
The Claimants were all regularly assigned employees who
were furloughed without being given five (5) working days
advanced written notice as required by rule 30 (b) of the Agreement. The Organization asserts that rule 19 (a) is also pertinent because it guarantees employees forty (40) hours of work
each week.
The Carrier asserts that severe weather including snow,
ice, freezing rain, etc. caused the lay-offs and a five (5)
working day written notice was not necessary because of the
exceptions set forth in rule 30 (d) which states that no advance notice is required before a temporary force reduction
under "emergency conditions" such as snow storms among other
causes as long as that emergency condition results in a suspension of operations in whole or in part. Further it is understood that the temporary work reduction will be confined solely
to the work locations directly affected by any suspension of
operations.
The Organization states that the snoia storm did not constitute an emergency and there was not a suspension. of the operation of trains.
The Carrier asserts that it presented evidence while
the case was under review on the property to show that there
was a significant cold weather problem in the area which was
not reasonably predictable and that that certainly constituted
an emergency within the language of rule 30(d). Moreover the
Carrier argues that the suspension of operations in whole or
in part does not refer to train operations but to the particular maintenance of way operations which otherwise would have
been performed.
There is, of course, some basic appeal in the contentions
of both parties. Normally when one considers the "operation"
of a rail carrier one thinks in terms of the movement of trains
however the Carrier's position is not totally inconsistent with
the reading of rule 30 (d) especially when one reads the portion
of the rule which says that temporary force reductions will be
confined solely to those work locations directly affected by
any suspension of operations.
The Organization has the burden of proof in the particular
case. The Board has considered the matter as handled on the
property and we find that the Organization has not presented
evidence of the parties intent when they use the words "suspension of operations". We will- dismiss the claim for failure of
proof however it should be understood that this dismissal may
not be precedential if in a future case the organization demonstrates factually that the parties to the negotiation intended
that the words of rule 30 (d) be restricted to instances where
train operations were suspended in whole or part.
FINDINGS
The Board, upon consideration of the entire record
and all of the evidence finds:
The parties herein are Carrier and Employee within
the meaning of the Railway Labor Act, as amended.
This Board has jurisdiction over the dispute involved
herein.
The parties to said dispute were given due and proper
notice of hearing thereon.
AWARD
Claim dismissed for failure of proof.
2
J ph A. Sic lChat ma and Neut ales
69
J. Gibbins Hugh G. Harper
Carrier Member Organization Member
2
8'3
/DA '/E
3