PUBLIC LAW BOARD N0. 2556
Award No. 10
Case No. 12
Docket No. MW-184
Case No. 13
Docket No. MW-185
Case No. 14
' Docket No. MW-186
Parties Brotherhood of Maintenance of Way Employees
to and
Dispute Southern Railway Company
Statement
of Claim: Claim on behalf of E. R. Brown, et. al., for proportionate
share of man hours worked account contractor performed work
with ballast regulator and tamper on 11/8-10, 13-17, 20-22/78
and continuing.
Claim on behalf of D. T. Newport, et. al., account
contractor unloaded material, did ditching and laid
ribbon rail between M. P. 292 and 295 on 9/5-15,
18-22/78 and continuing.
Claim on behalf of D. T. Newport, et. al., for equal
proportionate share of total man hours worked account
contractor removed lap switches from main line and
joined siding with main line between M.P. 293.4 and 293.6
on 12-18-78.
Findings: The Board, after hearing upon the whole record and all evidence,
finds that the parties herein are Carrier and Employee within the meaning
of the Railway Labor Act, as amended, that this Board is duly constituted
by Agreement dated October 17, 1979, that it has jurisdiction of the
parties and the subject matter, and that the parties were given due
notice of the hearing held.
The instant claims involve the same issue as found in the claims
which resulted in our Board's Award No. 9 the findings of which, by
reference hereto, are incorporated herein and made part hereof.
In the instant case it became necessary to contract out work
involved in the consolidation of lap passing tracks at Evansville,
Tennessee, to perform one long siding on the Cincinnati, New Orleans,
-2- Award No. 10
and Texas Pacific Railway Company (NO&TP). As in our Award No. 9,
the record reflects that the General Chairman was given notice specifying
the nature and type of work to be contracted out.
Here, as in our Award No. 9, the record fails to show that the
Employees assumed the burden of proof necessary to establish through
presentation of probative evidence that the work contracted out was
of the type which only employees under MofW agreement have traditionally
and customarily performed.
Here, as in Award No. 9, we find, absent a showing that said MofW
employees have performed such work exclusively, that the record reflects
Carrier followed Agreement Rule 59 and the long established and well
recognized practices thereunder in contracting out the work complained of.
The record reflects that the work was required to be started at the
earliest possible date, that there were no furloughed employees on the
Northwest seniority region available to perform the work, that the
existing force of MofW employees were engaged in necessary maintenance
and construction work which could not be deferred, that necessary machines
and equipment were not available, and that even if such equipment were
available the work to be performed would be beyond the capacity of the
existing force to complete the work within the time allotted and at the
same time perform the other necessary maintenance and construction work
in which engaged.
The practice of contracting out work, as asserted by Carrier,
was reinforced by a demonstration of 11 instances in which upgrading
projects of similar character had been contracted out in recent years
under similar circumstances.
Therefore, on the record the Board finds the claim to be without
merit and the instant claim will be denied.
Award: Claim denied.
. ,(~ _ 4,
A. 0. Arnett, Emp o e Member R. ' enski, Carrier Member
Jkrth r
7.
Van Wart, airman -
and Neutral Member
Issued at Wilmington, Delaware, April 18, 1981.