On December 9, 1978 Zep-p's Bridge, Baltimore, Maryland was severely damaged by a derailment. Due to the magnitude of the repair project, the work was contracted to an outside concern.
Notwithstanding the above, the Petitioner submits that Claimant Duvall should have been called for available overtime work an the repair project.
Without prejudice to the respective ~ positions of either the Carrier or the Petitioner, in light of the particular facts and circumstances of this dispute this Board will sustain the claim but only to the extent of twelve (12) hours' pay at-the straight time rate. ,