PUBLIC LAW BOARD NO. 2960
AWARD NO.
(0
CASE NO. 172
PARTIES TO DISPUTE:
Brotherhood of Maintenance of Way Employes
and
Chicago & North Western Transportation Company
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
(1) The five (5) day actual suspension and the ten
(10) day deferred suspension assessed D. R.
Smuck for his alleged responsibility for failure
to repair defective rail resulting in a
derailment is wholly unjust and improper.
(Organization File 2D-5033; Carrier File 81-8552-D)
(2) Claimant shall be allowed the remedy as
prescribed in Rule 19(d).
OPINION OF THE BOARD
This Board, upon the whole record and all of the evidence,
finds and holds that the Employe and Carrier involved in this
dispute are respectively Employe and Carrier within the meaning of
the Railway Labor Act, as amended, and that.the Board has jurisdiction over the dispute involved herein.
On October 12, 1984 the Carrier directed the following
notice to the Claimant:
"You are directed to appear for Formal Investigation as
indicated below:
PLB 2960 -2-
Ati p lap
PLACE: Engineering Offices
1937 Hull Avenue
Des Moines, Iowa
TIME: 11:00 A. M.
DATE: Monday, October 15, 1984
CHARGE: Your responsibility for failure to properly
repair defective rail on West # 4 Track Switch
at West Des Moines, Iowa on October 6, 1984,
resulting in derailment on October 9, 1984.
i
You may be accompanied by an employee and. or
representative of your own choosing, subject to provisions
of applicable rules in the applicable Schedule, and you
may, if you so desire, produce witnesses in your own behalf
wihtout expense to the Transportation Company."
Subsequent to the investigation the claimant was assessed the
discipline now on appeal before the board.
The basic facts are not disputed. On October 6, 1984,
Claimant was employed as Maintenance Foreman on the Weekend Gang
at Short Line Yard in Des Moines, Iowa. The previous day,
Assistant Roadmaster Jones told him that his crew should repair
a broken rail on No. 4 Track at West Des Moines sometime over
the weekend. Under Claimant's supervision, this repair was made
on October 6. On October 9, 1984, a derailment occurred at the
point where Claimant's crew had repaired the broken rail.
There is also no doubt that the method, of repair employed
by the Claimant was improper and caused the derailment. The
Assistant Roadmaster testified that the cause of the derailment
was the fact that two different size rails had been cut in,
improper size angle bars were used and the bolt holes had been
torch cut. This caused the wheel of the locomotive to climb
over the rail: In addition, the Claimant in essence admitted
PLB 2960 -3-
Awp
/30
the repairs were improper. The following testimony is
conclusive evidence of this:
"Q. And do you also feel that the repairs that were made
at that particular time, for whatever reason, were
inadequate for the operations of trains?
A. Yeah. I did not feel good about the repairs that were
made at the time."
Instead the Claimant's defense is that -- while he knew the
i
track wasn't repaired properly -- he had not released it for
use. Nessecarily, as a defense this would have to mean that the
Claimant intended to remedy the improper repairs. If this
defense were credible it would absolve the Claimant of
responsibility in the incident. However, there is more than a
substantial foundation in the record for a finding that this
defense is not credible.
The reasons it is not a credible defense include: (1) the
fact he had not made any attempt between the 7th and the 9th to
properly repair the track, (2) the fact he made no notation on
his work report that the track needed further repair, (3) the
fact he made no Claim to his supervisor when confronted with the
incident that he had not returned the trackto service, (4) the
fact his initial defense -- according to his supervisor -- was
as follows:
"I had a meeting with Mr. Mulvaney and Mr. Smuck at which
time I was upset about the derailment and I told them in
making repairs like that they should have either made the
repairs properly or kept the track out of service. And
they said to me, well you know how guys always complain
about overtime is the reason we went ahead and fixed it
like that."
PLB 2960 -4-
~;~o /30
(5) The fact there was an indication the Claimant was simply
just in a hurry to fix the rail is evidenced by his testimony as
follows:
"Really, you know, it was probably a bad calculation on my
part or something, but really didn't know what we getting
into out there. We had no idea what _was out there, we
didn't know where it was. And at that time; the time had
been coming close to the end' of the due. We was, you know,
we used up three hours over thereon one lousy broken
rail, which I kind of worried about our time consumption
out there. Didn't have the proper tools and didn't feel
there was time to go get such. So we tried to see what we
could do to get by with what we had."_ _
Accordingly, in view of these facts we cannot conclude
that a five-day suspension is unreasonable.
AWARD:
The Claim is denied.
Gil Vernon, Chairman
C. vein
D. . Bartholomay r · S' on
Employe Member arr erMe ber
Dated:
J4
e~
'I
r j,(7