PUBLIC LAW BOARD NO. 2960
PARTIES Brotherhood of Maintenance of Way Employees
TO and
DISPUTE Chicago and North Western Transportation Company
STATEMENT OF CLAIM: "Claim filed in behalf of Mr.
J. P. Schumann, Employe No. 139721, as a result of the Company
denying Claimant of his contractual right,to timely assume his
Bulletined position."
FINDINGS: This Board, upon the whole record and all of the
evidence, finds that the Employees and Carrier involved in this
dispute are respectively Employees and Carrier within the meaning
of the Railway Labor Act as amended and that the Board has
jurisdiction over the dispute involved herein.
OPINION OF THE BOARD: On August 22, 1988, the Carrier issued an
assignment notice indicating that the Claimant was assigned to
Bulletin No. 88263. This assignment was to be effective August
22, 1988. Claimant was notified and took a physical on
August 22. The results of this physical exam were not received
by the Carrier's Medical Director until Friday, September 9,
1988. These records were reviewed and claimant was qualified to
return to service on Monday, September 12, 1988. The Claimant
was returned to the carrier's service on that date. The claim
seeks compensation for all time lost from August 22 until
September 12.
In response to the organization's argument that the delay in
this case was excessive, the Carrier points out that the Claimant
could have requested a physical in advance of the bulletin.
However, this doesn't explain why it took 21- days to fully
process his return-to-work physical.
Certainly the appointment was made expeditiously, as was the
medical director's review of the examination results. The real
problem is the excessive time in between. The question is why
did it take so long to get the results to the Medical Director.
The Carrier has not satisfactorily answered this question.
Moreover, there is no causal relationship between the Claimant
delaying his scheduling of the physical and the fact it took 18
days for the results of the examination to reach the medical
director. This delay is unreasonable, and there is no evidence
to suggest that it was due to anything but Carrier negligence.
~&/
0.1
i-1o -X96'0
Case No. 277
Page 2
It is the conclusion of the Board that the entire process of
approving the Claimant should have been completed by September 1.
Therefore, he is entitled to all time lost between and including
September 2 and September 12.
AWARD
The claim is sustained to the extent indicated in the
Opinion.
Gil Vernon, Chairman
D. D. Bartholomay Jo . Harvieux
14
Emplo ee Member Carrier Member
Dated: